NEC ECC: Abatement of compensation events without a valid pay less notification
|
|
5
|
843
|
26 November 2018
|
NEC ECC: Defects arising from poor workmanship
|
|
2
|
1192
|
18 June 2019
|
Is there a limit on the Contractor’s total liability to the Employer under Option X18?
|
|
1
|
820
|
14 November 2012
|
What is the procedure if the Contractor and Project Manager are prepared to accept a Defect?
|
|
1
|
820
|
15 October 2012
|
NEC ECC: Employer rights to enforce a term of the subcontracts
|
|
1
|
819
|
20 August 2018
|
The Contractor has insured a risk which the Employer was contractually obliged to insure but did not. Who pays the cost of this insurance?
|
|
1
|
819
|
11 October 2012
|
NEC ECC: Challenge of a Z Clause relating to Corona Virus
|
|
6
|
778
|
31 March 2020
|
NEC ECC: Employer cost of correcting defect after Completion - recoverable?
|
|
2
|
1188
|
24 May 2018
|
NEC 3 Option B SC - Main Contractor Provisions
|
|
1
|
460
|
31 March 2022
|
NEC3 - Negative CE for removal of methodology restriction
|
|
3
|
578
|
22 March 2023
|
Contractors Quotation doesn't match Subcontractors Quotation
|
|
1
|
816
|
22 September 2014
|
Does the Works Information include which materials from excavation and demolition are to be the property of the Contractor?
|
|
1
|
816
|
15 October 2012
|
Should the Contractor move an object of value or of historical interest which he has discovered within the Site?
|
|
1
|
816
|
15 October 2012
|
NEC3 ECC: Damage to the works under a CE instruction
|
|
1
|
815
|
7 April 2016
|
What is the defects date?
|
|
1
|
815
|
15 October 2012
|
Can the insurance company recoup expenses for a claim paid out when another Party should have been responsible for paying at least a portion of that claim?
|
|
1
|
815
|
11 October 2012
|
Sub contractor equipment cost
|
|
1
|
815
|
14 January 2021
|
NEC ECC: Adjudicator's decision and Retention - X16
|
|
2
|
664
|
13 July 2017
|
Works information clause included in an appendix to an appendix
|
|
2
|
664
|
4 December 2014
|
NEC3 ECC: Evaluation of Missing BQ Items when not arising from a change to the WI
|
|
1
|
811
|
7 July 2016
|
NEC ECC: Disallowed Costs for stand down at Contractor's fault
|
|
1
|
1442
|
19 October 2018
|
NEC ECC: Liability of acceptance of design
|
|
1
|
1442
|
14 February 2018
|
NEC ECC: Contractor is not replacing a key person
|
|
1
|
1440
|
5 August 2019
|
NEC3 ECC: Failure by PM to respond to a CE
|
|
2
|
661
|
15 February 2016
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
91
|
16 July 2024
|
How the PM instructs changes to the working areas (increasing) whilst also delaying access dates even though Contractor is not ready?
|
|
1
|
807
|
19 November 2014
|
NEC ECC: Insurances Post Completion
|
|
4
|
907
|
15 November 2018
|
NEC3 ECC: Categories of people in SSCC
|
|
1
|
806
|
27 October 2015
|
NEC ECC: Clarification of Ambiguities of Works Information under Clause 17.1
|
|
2
|
1171
|
25 July 2018
|
ECC Option C - Contract
|
|
2
|
1169
|
5 August 2021
|
NEC TSC: Are the provisions of Clause 91.2 dependent on following the procedure as listed under Clause 90.1 or can termination be effected directly
|
|
2
|
1170
|
11 April 2018
|
NEC3 - Accepting a Time Barred Event
|
|
1
|
254
|
7 June 2024
|
NEC3 ECC: The role of the Supervisor in a Design and Build Contract
|
|
1
|
1428
|
12 December 2016
|
NEC ECC: how does PM assess a late CE
|
|
2
|
655
|
22 February 2019
|
NEC ECC: Shallow underground services in a town centre environment
|
|
2
|
655
|
15 December 2017
|
NEC ECC: Option A Subcontractor fee percentage
|
|
1
|
802
|
14 May 2017
|
NEC3 PSC: In the PSSC, where in the Contract Data is the statement referred to in PSSC 11.2(7) regarding the documents that the Scope is in?
|
|
1
|
802
|
2 November 2015
|
Webinar - How to produce and update your programme under NEC3 ECS
|
|
5
|
463
|
14 September 2023
|
NEC 3 & 4 Option X2 - Red diesel ban 2022
|
|
1
|
1426
|
4 April 2021
|
NEC ECC: a CE Weather Event - is it calendar days or working days?
|
|
1
|
1426
|
16 April 2020
|
Using both SCC and SSCC under ECC Main Option A & C?
|
|
1
|
801
|
25 August 2016
|
Under what circumstances might Equipment be permitted to remain on Site?
|
|
1
|
801
|
15 October 2012
|
The Project Manager has instructed the Contractor to stop or not start any substantial work or all work. Can the Contractor terminate?
|
|
1
|
801
|
12 October 2012
|
NEC ECC: Can time bar principles be applied to accepted CE's?
|
|
2
|
1163
|
15 September 2017
|
NEC ECC: Value Engineering - NEC3 ECC Option C
|
|
1
|
1424
|
15 December 2017
|
Is overtime payable under ECC Option C?
|
|
1
|
1424
|
12 December 2012
|
NEC 3 Option B Clause 61.3
|
|
1
|
253
|
20 May 2024
|
NEC3 ECC: X5 & 7 - Damages that Contractor would incur
|
|
1
|
800
|
18 May 2016
|
NEC ECC: Option E payments
|
|
1
|
1423
|
17 February 2020
|
What can the Employer do if he feels time has not been properly spent?
|
|
1
|
799
|
19 November 2012
|