About the Title category
|
|
1
|
368
|
8 May 2024
|
Contractor doing work for another project within our Project's Working Area NEC Option A
|
|
1
|
409
|
18 May 2023
|
Pre-ordering materials under NEC4
|
|
1
|
466
|
11 November 2021
|
NEC ECC: Who is responsible for getting rid of excavated material from site?
|
|
5
|
1978
|
7 August 2020
|
NEC ECC: How is clause 72.1 interpreted in removing equipment?
|
|
1
|
776
|
22 June 2020
|
NEC ECC: Covid-19 and NEC3 Working Area
|
|
3
|
1574
|
30 March 2020
|
NEC ECC: Title when advance payment wasn't envisaged
|
|
1
|
1327
|
20 June 2019
|
NEC ECSC - Vested Material - at what point does the Employer become liable for insuring vested material?
|
|
1
|
746
|
30 April 2019
|
NEC4 ECC: Title to Materials
|
|
3
|
2995
|
19 September 2018
|
NEC ECC: Temporary Traffic Management - Security of Works Areas
|
|
1
|
821
|
4 December 2017
|
NEC ECC: Is there provision is included in the NEC for nomination of subcontractors
|
|
1
|
1066
|
21 June 2017
|
NEC3 ECC: Option C, what should the formal process be for warranties transferring to the Employer from the Contractor?
|
|
2
|
775
|
16 January 2017
|
NEC3 ECC: Title of equipment included in defined cost
|
|
3
|
4979
|
16 December 2015
|
Could you please give us your thoughts as to the practical application of the NEC3 clauses on Title in relation to excavated materials
|
|
1
|
962
|
30 July 2015
|
Is a Vesting Certificate required under Clause 70 of the un-amended NEC?
|
|
1
|
10215
|
4 February 2015
|
What is the purpose of section 7: Title?
|
|
1
|
1273
|
16 November 2012
|
Should the activity schedule show the items of Equipment, Plant or Materials which the Employer is to secure ownership of?
|
|
1
|
962
|
15 October 2012
|
Should the bill of quantities show the items of Equipment, Plant or Materials which the Employer is to secure ownership of?
|
|
1
|
845
|
15 October 2012
|
When does the Contractor receive payment for passing title of items of Equipment, Plant or Materials to the Employer?
|
|
1
|
918
|
15 October 2012
|
Should the Employer secure ownership of Equipment, Plant or Materials manufactured or stored outside the Working Areas?
|
|
1
|
838
|
15 October 2012
|
Does the Works Information include which materials from excavation and demolition are to be the property of the Contractor?
|
|
1
|
816
|
15 October 2012
|
Does the Contractor have title to materials from demolition?
|
|
1
|
905
|
15 October 2012
|
Does the Contractor have title to materials from excavation?
|
|
1
|
865
|
15 October 2012
|
Should the Contractor move an object of value or of historical interest which he has discovered within the Site?
|
|
1
|
814
|
15 October 2012
|
What should the Contractor do if he discovers an object of value or of historical interest within the Site?
|
|
1
|
977
|
15 October 2012
|
Does the Contractor have title to objects of historical interest or value found within the Site?
|
|
1
|
888
|
15 October 2012
|
Under what circumstances might Equipment be permitted to remain on Site?
|
|
1
|
801
|
15 October 2012
|
Is Equipment ever permitted to remain on the Site?
|
|
1
|
854
|
15 October 2012
|
When should the Contractor remove Equipment from the Site?
|
|
1
|
842
|
15 October 2012
|
Does the Supervisor mark Equipment, Plant or Materials outside the Working Areas if the Contractor has prepared them for marking?
|
|
1
|
1195
|
15 October 2012
|