| 
            
            
              About the Title category
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            377
           | 
          
            8 May 2024
           | 
        
        
          | 
            
            
              Contractor doing work for another project within our Project's Working Area NEC Option A
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            417
           | 
          
            18 May 2023
           | 
        
        
          | 
            
            
              Pre-ordering materials under NEC4
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            485
           | 
          
            11 November 2021
           | 
        
        
          | 
            
            
              NEC ECC: Who is responsible for getting rid of excavated material from site?
            
            
           | 
          
              
                 
              
              
                 
              
              
                 
              
              
                 
              
           | 
          
            5
           | 
          
            2067
           | 
          
            7 August 2020
           | 
        
        
          | 
            
            
              NEC ECC: How is clause 72.1 interpreted in removing equipment?
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            811
           | 
          
            22 June 2020
           | 
        
        
          | 
            
            
              NEC ECC: Covid-19 and NEC3 Working Area
            
            
           | 
          
              
                 
              
              
                 
              
              
                 
              
           | 
          
            3
           | 
          
            1582
           | 
          
            30 March 2020
           | 
        
        
          | 
            
            
              NEC ECC: Title when advance payment wasn't envisaged
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            1346
           | 
          
            20 June 2019
           | 
        
        
          | 
            
            
              NEC ECSC -  Vested Material - at what point does the Employer become liable for insuring vested material?
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            764
           | 
          
            30 April 2019
           | 
        
        
          | 
            
            
              NEC4 ECC: Title to Materials
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            3
           | 
          
            3113
           | 
          
            19 September 2018
           | 
        
        
          | 
            
            
              NEC ECC: Temporary Traffic Management - Security of Works Areas
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            828
           | 
          
            4 December 2017
           | 
        
        
          | 
            
            
              NEC ECC: Is there provision is included in the NEC for nomination of subcontractors
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            1075
           | 
          
            21 June 2017
           | 
        
        
          | 
            
            
              NEC3 ECC: Option C, what should the formal process be for warranties transferring to the Employer from the Contractor?
            
            
           | 
          
              
                 
              
              
                 
              
              
                 
              
           | 
          
            2
           | 
          
            784
           | 
          
            16 January 2017
           | 
        
        
          | 
            
            
              NEC3 ECC: Title of equipment included in defined cost
            
            
           | 
          
              
                 
              
              
                 
              
              
                 
              
           | 
          
            3
           | 
          
            5060
           | 
          
            16 December 2015
           | 
        
        
          | 
            
            
              Could you please give us your thoughts as to the practical application of the NEC3 clauses on Title in relation to excavated materials
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            973
           | 
          
            30 July 2015
           | 
        
        
          | 
            
            
              Is a Vesting Certificate required under Clause 70 of the un-amended NEC?
            
            
           | 
          
              
                 
              
              
                 
              
           | 
          
            1
           | 
          
            10232
           | 
          
            4 February 2015
           | 
        
        
          | 
            
            
              What is the purpose of section 7: Title?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            1275
           | 
          
            16 November 2012
           | 
        
        
          | 
            
            
              Should the activity schedule show the items of Equipment, Plant or Materials which the Employer is to secure ownership of?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            963
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Should the bill of quantities show the items of Equipment, Plant or Materials which the Employer is to secure ownership of?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            845
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              When does the Contractor receive payment for passing title of items of Equipment, Plant or Materials to the Employer?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            921
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Should the Employer secure ownership of Equipment, Plant or Materials manufactured or stored outside the Working Areas?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            841
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Does the Works Information include which materials from excavation and demolition are to be the property of the Contractor?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            818
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Does the Contractor have title to materials from demolition?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            911
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Does the Contractor have title to materials from excavation?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            868
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Should the Contractor move an object of value or of historical interest which he has discovered within the Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            816
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              What should the Contractor do if he discovers an object of value or of historical interest within the Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            1002
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Does the Contractor have title to objects of historical interest or value found within the Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            941
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Under what circumstances might Equipment be permitted to remain on Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            802
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Is Equipment ever permitted to remain on the Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            858
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              When should the Contractor remove Equipment from the Site?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            845
           | 
          
            15 October 2012
           | 
        
        
          | 
            
            
              Does the Supervisor mark Equipment, Plant or Materials outside the Working Areas if the Contractor has prepared them for marking?
            
            
           | 
          
              
                 
              
           | 
          
            1
           | 
          
            1213
           | 
          
            15 October 2012
           |