About the SOCC SSOCC category
|
|
0
|
259
|
27 February 2020
|
NEC 3 & 4 SOCC - Fuel, Oils, Lubricants & Other Consumables used in relation to hired Equipment
|
|
1
|
159
|
5 January 2023
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
508
|
24 March 2022
|
Payments made in relation to People for Pensions
|
|
2
|
343
|
29 November 2021
|
NEC3 Supply Contract SOCC
|
|
2
|
340
|
23 February 2021
|
Sub contractor equipment cost
|
|
1
|
526
|
14 January 2021
|
NEC3 ECC - Shorter Schedule of Cost Components Percentages
|
|
2
|
1824
|
8 January 2021
|
NEC 3 SOCC - Medicine Reimbursements
|
|
1
|
341
|
4 January 2021
|
SSCC Equipment List - Non Existent
|
|
1
|
355
|
4 January 2021
|
Defined Cost - Percentages - Option A contract
|
|
1
|
479
|
31 December 2020
|
NEC3 ECC Option D – Schedule of Cost Components – Health Insurance
|
|
1
|
414
|
16 October 2020
|
NEC 3 - Headhunter's fee
|
|
1
|
564
|
16 October 2020
|
NEC3 ECC Schedule of Cost Compenents - Charges 4 - Specialist Services 43(h)
|
|
3
|
1054
|
4 September 2020
|
NEC ECC Option C - Equipment rates
|
|
1
|
985
|
20 July 2020
|
NEC4 ECC: Option C - Self Isolation covered under the SCC during Covid-19 period?
|
|
3
|
598
|
8 July 2020
|
NEC ECC: Change of CECA Rates When Pricing a Initial And Revised Compensation Event Quotations
|
|
1
|
427
|
3 July 2020
|
NEC ECC: Addition of fee to CECA Equipment Rates
|
|
2
|
1056
|
3 July 2020
|
NEC ECC: CECA Rates within a Compensation Event
|
|
2
|
840
|
2 July 2020
|
NEC ECC: What if the Contractor installs something better than the Works Information?
|
|
1
|
320
|
26 June 2020
|
NEC ECC: How are Prices reviewed for a compensation event that is an instruction from the Employer?
|
|
1
|
384
|
26 June 2020
|
NEC ECC: Interpretation of NEC4 SOCC
|
|
1
|
981
|
25 June 2020
|
NEC ECC: Same Subcontract fee percentage applied to subcontracts under option A and C?
|
|
2
|
561
|
16 June 2020
|
NEC ECC: Under an option C contract, how would items that have been instructed by the Project Manager be covered in the defined cost?
|
|
1
|
440
|
16 June 2020
|
NEC3 Option C disallowed Subcontractor costs
|
|
1
|
488
|
12 May 2020
|
NEC ECC: Defined Cost - Furlough Top Up Payments
|
|
1
|
795
|
23 April 2020
|
NEC ECC: Design Costs under the schedule of cost components
|
|
1
|
438
|
16 April 2020
|
NEC ECC: Severance cost for People incurred under SSCC (during Covid-19 period)
|
|
1
|
516
|
9 April 2020
|
NEC ECC: Is it correct to use 2019 CECA rates in lieu of 2011 CECA rates after the original completion date?
|
|
1
|
590
|
1 April 2020
|
NEC4 ECC: Option B: completion of data for sscc
|
|
2
|
517
|
28 February 2020
|
NEC ECS: Subcontractors category removed from schedule of cost components
|
|
1
|
440
|
17 February 2020
|