About the SOCC SSOCC category
|
|
1
|
448
|
8 May 2024
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
91
|
7 August 2024
|
PSC4 - People or Subcontractor
|
|
1
|
198
|
25 April 2024
|
What does the term Subsistence cover in terms of Defined Costs under SOCC
|
|
0
|
443
|
13 October 2022
|
NEC ECS Option A - SSOCC - Items not listed
|
|
1
|
291
|
27 August 2023
|
NEC ECC Option C - Equipment rates
|
|
2
|
2102
|
23 July 2023
|
NEC3 - ECC3 Option A SSOCC - Contingency Provision in Quotation
|
|
5
|
475
|
23 July 2023
|
NEC3 ECC Option C: Equipment repair and maintenance
|
|
2
|
721
|
23 July 2023
|
NEC 3 & 4 SOCC - Fuel, Oils, Lubricants & Other Consumables used in relation to hired Equipment
|
|
1
|
693
|
5 January 2023
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
849
|
24 March 2022
|
Payments made in relation to People for Pensions
|
|
2
|
643
|
29 November 2021
|
NEC3 - ECC - SOCC - Expenses
|
|
1
|
1023
|
15 March 2021
|
NEC3 Supply Contract SOCC
|
|
2
|
540
|
23 February 2021
|
Sub contractor equipment cost
|
|
1
|
803
|
14 January 2021
|
NEC3 ECC - Shorter Schedule of Cost Components Percentages
|
|
2
|
3608
|
8 January 2021
|
NEC 3 SOCC - Medicine Reimbursements
|
|
1
|
549
|
4 January 2021
|
SSCC Equipment List - Non Existent
|
|
1
|
536
|
4 January 2021
|
Defined Cost - Percentages - Option A contract
|
|
1
|
785
|
31 December 2020
|
NEC3 ECC Option D – Schedule of Cost Components – Health Insurance
|
|
1
|
683
|
16 October 2020
|
NEC 3 - Headhunter's fee
|
|
1
|
963
|
16 October 2020
|
NEC3 ECC Schedule of Cost Compenents - Charges 4 - Specialist Services 43(h)
|
|
3
|
1700
|
4 September 2020
|
NEC4 ECC: Option C - Self Isolation covered under the SCC during Covid-19 period?
|
|
3
|
903
|
8 July 2020
|
NEC ECC: Change of CECA Rates When Pricing a Initial And Revised Compensation Event Quotations
|
|
1
|
763
|
3 July 2020
|
NEC ECC: Addition of fee to CECA Equipment Rates
|
|
2
|
2365
|
3 July 2020
|
NEC ECC: CECA Rates within a Compensation Event
|
|
2
|
1432
|
2 July 2020
|
NEC ECC: What if the Contractor installs something better than the Works Information?
|
|
1
|
477
|
26 June 2020
|
NEC ECC: How are Prices reviewed for a compensation event that is an instruction from the Employer?
|
|
1
|
620
|
26 June 2020
|
NEC ECC: Interpretation of NEC4 SOCC
|
|
1
|
1762
|
25 June 2020
|
NEC ECC: Same Subcontract fee percentage applied to subcontracts under option A and C?
|
|
2
|
983
|
16 June 2020
|
NEC ECC: Under an option C contract, how would items that have been instructed by the Project Manager be covered in the defined cost?
|
|
1
|
680
|
16 June 2020
|