|
About the SOCC SSOCC category
|
|
1
|
461
|
8 May 2024
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
99
|
22 June 2025
|
|
Competitiveness of SOCC 1 people cost
|
|
2
|
87
|
11 March 2025
|
|
NEC 4 Option C - SCCO, calculation of hourly rate to determine Define Cost
|
|
3
|
106
|
5 March 2025
|
|
NEC4 Option C SOCC Sick Pay
|
|
0
|
73
|
4 December 2024
|
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
209
|
7 August 2024
|
|
PSC4 - People or Subcontractor
|
|
1
|
241
|
25 April 2024
|
|
What does the term Subsistence cover in terms of Defined Costs under SOCC
|
|
0
|
459
|
13 October 2022
|
|
NEC ECS Option A - SSOCC - Items not listed
|
|
1
|
317
|
27 August 2023
|
|
NEC ECC Option C - Equipment rates
|
|
2
|
2302
|
23 July 2023
|
|
NEC3 - ECC3 Option A SSOCC - Contingency Provision in Quotation
|
|
5
|
505
|
23 July 2023
|
|
NEC3 ECC Option C: Equipment repair and maintenance
|
|
2
|
839
|
23 July 2023
|
|
NEC 3 & 4 SOCC - Fuel, Oils, Lubricants & Other Consumables used in relation to hired Equipment
|
|
1
|
750
|
5 January 2023
|
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
883
|
24 March 2022
|
|
Payments made in relation to People for Pensions
|
|
2
|
685
|
29 November 2021
|
|
NEC3 - ECC - SOCC - Expenses
|
|
1
|
1130
|
15 March 2021
|
|
NEC3 Supply Contract SOCC
|
|
2
|
561
|
23 February 2021
|
|
Sub contractor equipment cost
|
|
1
|
821
|
14 January 2021
|
|
NEC3 ECC - Shorter Schedule of Cost Components Percentages
|
|
2
|
3797
|
8 January 2021
|
|
NEC 3 SOCC - Medicine Reimbursements
|
|
1
|
569
|
4 January 2021
|
|
SSCC Equipment List - Non Existent
|
|
1
|
544
|
4 January 2021
|
|
Defined Cost - Percentages - Option A contract
|
|
1
|
822
|
31 December 2020
|
|
NEC3 ECC Option D – Schedule of Cost Components – Health Insurance
|
|
1
|
700
|
16 October 2020
|
|
NEC 3 - Headhunter's fee
|
|
1
|
984
|
16 October 2020
|
|
NEC3 ECC Schedule of Cost Compenents - Charges 4 - Specialist Services 43(h)
|
|
3
|
1784
|
4 September 2020
|
|
NEC4 ECC: Option C - Self Isolation covered under the SCC during Covid-19 period?
|
|
3
|
934
|
8 July 2020
|
|
NEC ECC: Change of CECA Rates When Pricing a Initial And Revised Compensation Event Quotations
|
|
1
|
784
|
3 July 2020
|
|
NEC ECC: Addition of fee to CECA Equipment Rates
|
|
2
|
2596
|
3 July 2020
|
|
NEC ECC: CECA Rates within a Compensation Event
|
|
2
|
1592
|
2 July 2020
|
|
NEC ECC: What if the Contractor installs something better than the Works Information?
|
|
1
|
479
|
26 June 2020
|