The Contractor has specified the following fee percentages - direct, sub contracted, adjustment for Equipment and people overheads.
The main Contractor has sub contracted a section of the works. When Assessing a compensation event in accordance with SSoCC, with respect to the sub contractor, do i use the main contractors adjustment for Equipment for assessing the sub contractors equipment cost?