About the Compensation Events category
|
|
1
|
711
|
8 May 2024
|
NEC3 - Correcting a PM Assumption
|
|
0
|
5
|
10 April 2025
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
20
|
10 April 2025
|
Nec3 compensation for information delay
|
|
1
|
34
|
25 March 2025
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
45
|
6 March 2025
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
45
|
26 February 2025
|
Additional Site Information post contract
|
|
5
|
83
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
85
|
2 January 2025
|
Late issue of project managers assumptions
|
|
1
|
60
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
107
|
13 December 2024
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
56
|
6 December 2024
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
58
|
4 December 2024
|
Interpretation of Clause 63.1
|
|
1
|
91
|
22 November 2024
|
NEC 4 option B - discrepancy between the BOQ and contract drawings
|
|
1
|
122
|
17 October 2024
|
CE occuring Delays
|
|
3
|
136
|
15 October 2024
|
NEC 3, Option B, Clause 63.13
|
|
2
|
78
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
100
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
166
|
15 August 2024
|
NEC4 Option C quotes
|
|
3
|
135
|
6 August 2024
|
Contractors delays & its affect on Key Dates
|
|
3
|
112
|
6 August 2024
|
NEC4 why does a scope reduction not bring the Completion Date forward
|
|
2
|
347
|
6 August 2024
|
Fee on CEs where the BoQ rates are used
|
|
4
|
150
|
23 July 2024
|
Project Manager gives additional time for Completion
|
|
2
|
120
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
83
|
16 July 2024
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
4
|
1588
|
15 July 2024
|
PM changes decision about accepting a CE
|
|
1
|
89
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
200
|
1 July 2024
|
Clause 63.6 - Equipment breakdown lost time
|
|
3
|
141
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
129
|
1 July 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
232
|
18 June 2024
|