About the Compensation Events category
|
|
1
|
699
|
8 May 2024
|
NEC 3, Option B, Clause 63.13
|
|
2
|
31
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
63
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
96
|
15 August 2024
|
NEC4 Option C quotes
|
|
3
|
94
|
6 August 2024
|
Contractors delays & its affect on Key Dates
|
|
3
|
54
|
6 August 2024
|
NEC4 why does a scope reduction not bring the Completion Date forward
|
|
2
|
69
|
6 August 2024
|
Fee on CEs where the BoQ rates are used
|
|
4
|
93
|
23 July 2024
|
Project Manager gives additional time for Completion
|
|
2
|
98
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
69
|
16 July 2024
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
4
|
1488
|
15 July 2024
|
PM changes decision about accepting a CE
|
|
1
|
62
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
155
|
1 July 2024
|
Clause 63.6 - Equipment breakdown lost time
|
|
3
|
97
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
103
|
1 July 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
163
|
18 June 2024
|
Free float and effects of duration reducing
|
|
2
|
186
|
13 June 2024
|
NEC3 Option B - Assessment of Compensation Event under ECC Clauses 60.4 and 60.6
|
|
2
|
344
|
8 June 2024
|
NEC3 - Accepting a Time Barred Event
|
|
1
|
221
|
7 June 2024
|
Drawing Inaccuracy
|
|
2
|
239
|
28 May 2024
|
Compensation Event Review Delayed by Client NEC4 Option A
|
|
1
|
281
|
20 May 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
256
|
23 April 2024
|
Compensation Event and Quotation
|
|
1
|
188
|
7 May 2024
|
NEC4 ECC Clause 60.1 (8) in association with clause 61.4
|
|
2
|
608
|
30 April 2024
|
Planned Completion & Completion Date
|
|
1
|
177
|
28 April 2024
|
NEC Option A Compensation Events with drawing revisions- How is Fee applied
|
|
1
|
171
|
26 April 2024
|
People Rates for Specialist Sub-contractor
|
|
0
|
137
|
23 April 2024
|
NEC3 - Cl.60.1.(8)
|
|
1
|
493
|
15 April 2024
|
NEC Option B 60.4
|
|
1
|
271
|
15 April 2024
|
People in Compensation Event Quotations
|
|
1
|
162
|
10 April 2024
|