|
About the Compensation Events category
|
|
1
|
725
|
8 May 2024
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
51
|
6 November 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
44
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
24
|
30 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1689
|
22 October 2025
|
|
NEC4 Option A 'fee percentage'
|
|
0
|
32
|
15 October 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
49
|
25 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
84
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
232
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
65
|
3 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
168
|
2 September 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
96
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
137
|
11 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3127
|
5 August 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
162
|
16 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
113
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
55
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
52
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
107
|
10 July 2025
|
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
113
|
22 June 2025
|
|
Quotation Assessments Under X2
|
|
1
|
147
|
15 May 2025
|
|
Compensation Events and Delay
|
|
1
|
100
|
9 May 2025
|
|
NEC4 Option A Compensation Event
|
|
3
|
135
|
2 May 2025
|
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
94
|
24 April 2025
|
|
Nec3 compensation for information delay
|
|
2
|
70
|
22 April 2025
|
|
NEC3 - Correcting a PM Assumption
|
|
2
|
102
|
13 April 2025
|
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
520
|
10 April 2025
|
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
58
|
6 March 2025
|
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
54
|
26 February 2025
|
|
Additional Site Information post contract
|
|
5
|
116
|
8 January 2025
|