About the Compensation Events category
|
|
1
|
723
|
8 May 2024
|
Prelims costs due to Extension of Time - Option A
|
|
0
|
11
|
1 August 2025
|
Use of CECA Rate
|
|
1
|
48
|
28 July 2025
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
2
|
42
|
16 July 2025
|
NEC 4 - Additional Compensation Events
|
|
3
|
52
|
16 July 2025
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
90
|
10 July 2025
|
NEC3 Option C: Recovering Prelims
|
|
1
|
45
|
10 July 2025
|
CE that includes extra over / weekend working rates
|
|
1
|
41
|
10 July 2025
|
Late issue of project managers assumptions
|
|
3
|
101
|
10 July 2025
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
95
|
22 June 2025
|
Quotation Assessments Under X2
|
|
1
|
131
|
15 May 2025
|
Compensation Events and Delay
|
|
1
|
90
|
9 May 2025
|
NEC4 Option A Compensation Event
|
|
3
|
122
|
2 May 2025
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
87
|
24 April 2025
|
Nec3 compensation for information delay
|
|
2
|
67
|
22 April 2025
|
NEC3 - Correcting a PM Assumption
|
|
2
|
88
|
13 April 2025
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
392
|
10 April 2025
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
54
|
6 March 2025
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
49
|
26 February 2025
|
Additional Site Information post contract
|
|
5
|
97
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
107
|
2 January 2025
|
NEC4 Core Clause 63.4
|
|
1
|
137
|
13 December 2024
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
59
|
6 December 2024
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
72
|
4 December 2024
|
Interpretation of Clause 63.1
|
|
1
|
95
|
22 November 2024
|
NEC 4 option B - discrepancy between the BOQ and contract drawings
|
|
1
|
135
|
17 October 2024
|
CE occuring Delays
|
|
3
|
146
|
15 October 2024
|
NEC 3, Option B, Clause 63.13
|
|
2
|
92
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
107
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
228
|
15 August 2024
|