|
About the Compensation Events category
|
|
1
|
725
|
8 May 2024
|
|
Application of Fees for Subcontracted Works
|
|
1
|
21
|
3 December 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
26
|
28 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
79
|
6 November 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
95
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
33
|
30 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1708
|
22 October 2025
|
|
NEC4 Option A 'fee percentage'
|
|
0
|
38
|
15 October 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
60
|
25 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
96
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
302
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
71
|
3 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
185
|
2 September 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
103
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
154
|
11 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3141
|
5 August 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
182
|
16 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
118
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
58
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
56
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
113
|
10 July 2025
|
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
114
|
22 June 2025
|
|
Quotation Assessments Under X2
|
|
1
|
150
|
15 May 2025
|
|
Compensation Events and Delay
|
|
1
|
100
|
9 May 2025
|
|
NEC4 Option A Compensation Event
|
|
3
|
141
|
2 May 2025
|
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
97
|
24 April 2025
|
|
Nec3 compensation for information delay
|
|
2
|
73
|
22 April 2025
|
|
NEC3 - Correcting a PM Assumption
|
|
2
|
124
|
13 April 2025
|
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
549
|
10 April 2025
|
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
63
|
6 March 2025
|