About the Compensation Events category
|
|
0
|
354
|
27 February 2020
|
Increased Costs - Covid Z Clause
|
|
2
|
17
|
1 July 2022
|
Accepted programme
|
|
3
|
86
|
25 June 2022
|
NEC3 Option B Subcontract - Omission of Works
|
|
1
|
49
|
25 June 2022
|
Prelims In a CE Quote
|
|
1
|
61
|
23 June 2022
|
Bank Holiday Cost Recovery
|
|
1
|
52
|
22 June 2022
|
Access Route to Site (Pedestrian Crossing with Lights)
|
|
1
|
50
|
16 June 2022
|
NEC 3 Option C ECSC Omitting SCope
|
|
4
|
84
|
15 June 2022
|
Ukraine War - Impact on material prices
|
|
7
|
832
|
12 June 2022
|
Considering allowances made in previous CE's when assessing new CE's
|
|
3
|
133
|
9 June 2022
|
NEC3 PSC (Option E) - Compensation Events for X1 & X2
|
|
2
|
139
|
6 June 2022
|
X2 change in law
|
|
1
|
106
|
25 May 2022
|
Material Price Increases
|
|
4
|
213
|
24 May 2022
|
Removing a Sectional Completion requirement
|
|
4
|
198
|
23 May 2022
|
Webinar - FastDraft Compensation Events Masterclass
|
|
34
|
396
|
12 May 2022
|
NEC4 dispute procedure W2.1
|
|
1
|
89
|
27 April 2022
|
Client trying to recover monies for a defect dispute p
|
|
1
|
218
|
25 April 2022
|
Assessment of Compensation Event by Subcontract
|
|
1
|
216
|
25 April 2022
|
Does Acceptance of a Compensation Event Notification Negate the Need for a Formal Instruction
|
|
1
|
297
|
25 April 2022
|
NEC4 - Unfair Main Contractor Assessment of Compensation Event Quotation
|
|
1
|
171
|
25 April 2022
|
NEC ECC: Compensation Event Time Bar Clause 61.3
|
|
3
|
860
|
22 April 2022
|
Justifying submitted CE costs
|
|
2
|
214
|
21 April 2022
|
Clause 31 Programme
|
|
6
|
163
|
19 April 2022
|
NEC4 Clause 61.4
|
|
4
|
185
|
7 April 2022
|
ECSC: 60.1(3) Client does not provide something
|
|
2
|
144
|
6 April 2022
|
NEC 3 Option B SC - Main Contractor Provisions
|
|
1
|
108
|
31 March 2022
|
Use of Subcontractor quotes in CE assessments in NEC4
|
|
2
|
335
|
29 March 2022
|
NEC 4 ECC Option A - Compensation event notified in error
|
|
1
|
153
|
18 March 2022
|
Pricing Plant Costs Under NEC Option A
|
|
3
|
265
|
18 March 2022
|
NEC4 Option C with activity schedule
|
|
4
|
232
|
14 March 2022
|