|
About the Compensation Events category
|
|
0
|
731
|
27 February 2020
|
|
Should changes in law under NEC3 ECC clause X2 be notified even if they are planned to come into effect after the Completion Date?
|
|
3
|
72
|
17 July 2026
|
|
NEC 4 CL 63.4 Option B
|
|
1
|
52
|
1 July 2026
|
|
Acceptance of programme
|
|
1
|
89
|
22 June 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
97
|
15 May 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
70
|
21 April 2026
|
|
NEC4 Option A - Instructions / CE's
|
|
2
|
140
|
26 February 2026
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
7
|
114
|
23 February 2026
|
|
NEC3 Option A - Can we recover the cost of resources not mobilised to the Working Areas?
|
|
3
|
188
|
11 February 2026
|
|
X22 Completion Procedure
|
|
3
|
84
|
24 January 2026
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
103
|
2 January 2026
|
|
Application of Fees for Subcontracted Works
|
|
1
|
67
|
3 December 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
79
|
28 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
106
|
6 November 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
147
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
58
|
30 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1778
|
22 October 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
110
|
25 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
194
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
667
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
91
|
3 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
347
|
2 September 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
177
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
245
|
11 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3214
|
5 August 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
246
|
16 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
149
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
85
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
89
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
153
|
10 July 2025
|