About the Compensation Events category
|
|
1
|
702
|
8 May 2024
|
Additional Site Information post contract
|
|
5
|
60
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
64
|
2 January 2025
|
Late issue of project managers assumptions
|
|
1
|
51
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
65
|
13 December 2024
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
50
|
6 December 2024
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
46
|
4 December 2024
|
Interpretation of Clause 63.1
|
|
1
|
78
|
22 November 2024
|
NEC 4 option B - discrepancy between the BOQ and contract drawings
|
|
1
|
105
|
17 October 2024
|
CE occuring Delays
|
|
3
|
121
|
15 October 2024
|
NEC 3, Option B, Clause 63.13
|
|
2
|
68
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
95
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
141
|
15 August 2024
|
NEC4 Option C quotes
|
|
3
|
123
|
6 August 2024
|
Contractors delays & its affect on Key Dates
|
|
3
|
90
|
6 August 2024
|
NEC4 why does a scope reduction not bring the Completion Date forward
|
|
2
|
228
|
6 August 2024
|
Fee on CEs where the BoQ rates are used
|
|
4
|
137
|
23 July 2024
|
Project Manager gives additional time for Completion
|
|
2
|
115
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
81
|
16 July 2024
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
4
|
1555
|
15 July 2024
|
PM changes decision about accepting a CE
|
|
1
|
78
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
179
|
1 July 2024
|
Clause 63.6 - Equipment breakdown lost time
|
|
3
|
134
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
116
|
1 July 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
195
|
18 June 2024
|
Free float and effects of duration reducing
|
|
2
|
202
|
13 June 2024
|
NEC3 Option B - Assessment of Compensation Event under ECC Clauses 60.4 and 60.6
|
|
2
|
367
|
8 June 2024
|
NEC3 - Accepting a Time Barred Event
|
|
1
|
238
|
7 June 2024
|
Drawing Inaccuracy
|
|
2
|
249
|
28 May 2024
|
Compensation Event Review Delayed by Client NEC4 Option A
|
|
1
|
300
|
20 May 2024
|