|
Inflation uplift calculation fro Framework
|
|
1
|
11
|
6 December 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
100
|
12 November 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
42
|
20 October 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
60
|
25 September 2025
|
|
NEC4 ECC Option D - Adjusting Quantities in BoQ
|
|
1
|
52
|
24 September 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
34
|
15 August 2025
|
|
Are legal fees allowable?
|
|
2
|
78
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
58
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
56
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
113
|
10 July 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
95
|
22 June 2025
|
|
Quotation Assessments Under X2
|
|
1
|
150
|
15 May 2025
|
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
97
|
24 April 2025
|
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
549
|
10 April 2025
|
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
111
|
31 March 2025
|
|
Inclusion of 'Unimplemented' CE in Forecast and Assessment
|
|
1
|
72
|
25 March 2025
|
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
57
|
26 February 2025
|
|
Liquidated Damages on paperwork
|
|
2
|
133
|
21 January 2025
|
|
NEC4 Core Clause 63.4
|
|
1
|
172
|
13 December 2024
|
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
117
|
25 September 2024
|
|
Contract Document Clarifications
|
|
2
|
106
|
19 September 2024
|
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
333
|
13 September 2024
|
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
112
|
29 August 2024
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
273
|
15 August 2024
|
|
NEC3 ECC Early Warnings
|
|
1
|
75
|
15 August 2024
|
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
206
|
7 August 2024
|
|
NEC4 Option C quotes
|
|
3
|
169
|
6 August 2024
|
|
Instructing works outside Contractor's original Scope
|
|
8
|
459
|
21 July 2024
|
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
100
|
16 July 2024
|
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
253
|
15 July 2024
|