Late issue of project managers assumptions
|
|
2
|
73
|
9 June 2025
|
Quotation Assessments Under X2
|
|
1
|
103
|
15 May 2025
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
81
|
24 April 2025
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
275
|
10 April 2025
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
87
|
31 March 2025
|
Inclusion of 'Unimplemented' CE in Forecast and Assessment
|
|
1
|
58
|
25 March 2025
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
48
|
26 February 2025
|
Liquidated Damages on paperwork
|
|
2
|
118
|
21 January 2025
|
NEC4 Core Clause 63.4
|
|
1
|
126
|
13 December 2024
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
90
|
25 September 2024
|
Contract Document Clarifications
|
|
2
|
94
|
19 September 2024
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
315
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
101
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
200
|
15 August 2024
|
NEC3 ECC Early Warnings
|
|
1
|
55
|
15 August 2024
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
151
|
7 August 2024
|
NEC4 Option C quotes
|
|
3
|
138
|
6 August 2024
|
Instructing works outside Contractor's original Scope
|
|
8
|
316
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
91
|
16 July 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
249
|
15 July 2024
|
Can Prelim deductions occur under NEC 3 Option B
|
|
1
|
218
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
212
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
134
|
1 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
922
|
16 February 2024
|
Acceleration - Not achieving the new completion date
|
|
1
|
169
|
20 June 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
252
|
18 June 2024
|
Inclusion of Non-Accepted Compensation Events in Programme, governing Planned Completion
|
|
2
|
364
|
11 June 2024
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
223
|
11 June 2024
|
Can plant repairs be claimed under
|
|
2
|
204
|
8 June 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
292
|
23 April 2024
|