Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
30
|
26 February 2025
|
Liquidated Damages on paperwork
|
|
2
|
95
|
21 January 2025
|
Late issue of project managers assumptions
|
|
1
|
56
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
98
|
13 December 2024
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
71
|
25 September 2024
|
Contract Document Clarifications
|
|
2
|
92
|
19 September 2024
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
307
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
96
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
155
|
15 August 2024
|
NEC3 ECC Early Warnings
|
|
1
|
54
|
15 August 2024
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
108
|
7 August 2024
|
NEC4 Option C quotes
|
|
3
|
131
|
6 August 2024
|
Instructing works outside Contractor's original Scope
|
|
8
|
228
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
82
|
16 July 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
243
|
15 July 2024
|
Can Prelim deductions occur under NEC 3 Option B
|
|
1
|
216
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
195
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
123
|
1 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
914
|
16 February 2024
|
Acceleration - Not achieving the new completion date
|
|
1
|
154
|
20 June 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
212
|
18 June 2024
|
Inclusion of Non-Accepted Compensation Events in Programme, governing Planned Completion
|
|
2
|
329
|
11 June 2024
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
213
|
11 June 2024
|
Can plant repairs be claimed under
|
|
2
|
189
|
8 June 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
283
|
23 April 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
196
|
26 April 2024
|
Built Connections 2024 - NEC User Group Conference
|
|
2
|
464
|
10 May 2024
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
591
|
13 May 2022
|
NEC4 - CE to reduce scope
|
|
1
|
580
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
450
|
8 March 2024
|