NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
25
|
10 April 2025
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
41
|
31 March 2025
|
Inclusion of 'Unimplemented' CE in Forecast and Assessment
|
|
1
|
49
|
25 March 2025
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
45
|
26 February 2025
|
Liquidated Damages on paperwork
|
|
2
|
107
|
21 January 2025
|
Late issue of project managers assumptions
|
|
1
|
60
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
107
|
13 December 2024
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
73
|
25 September 2024
|
Contract Document Clarifications
|
|
2
|
94
|
19 September 2024
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
312
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
100
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
166
|
15 August 2024
|
NEC3 ECC Early Warnings
|
|
1
|
55
|
15 August 2024
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
131
|
7 August 2024
|
NEC4 Option C quotes
|
|
3
|
135
|
6 August 2024
|
Instructing works outside Contractor's original Scope
|
|
8
|
257
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
83
|
16 July 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
245
|
15 July 2024
|
Can Prelim deductions occur under NEC 3 Option B
|
|
1
|
218
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
200
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
129
|
1 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
919
|
16 February 2024
|
Acceleration - Not achieving the new completion date
|
|
1
|
159
|
20 June 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
233
|
18 June 2024
|
Inclusion of Non-Accepted Compensation Events in Programme, governing Planned Completion
|
|
2
|
337
|
11 June 2024
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
216
|
11 June 2024
|
Can plant repairs be claimed under
|
|
2
|
195
|
8 June 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
286
|
23 April 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
199
|
26 April 2024
|
Built Connections 2024 - NEC User Group Conference
|
|
2
|
466
|
10 May 2024
|