Late issue of project managers assumptions
|
|
1
|
40
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
38
|
13 December 2024
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
60
|
25 September 2024
|
Contract Document Clarifications
|
|
2
|
83
|
19 September 2024
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
295
|
13 September 2024
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
92
|
29 August 2024
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
132
|
15 August 2024
|
NEC3 ECC Early Warnings
|
|
1
|
47
|
15 August 2024
|
NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
99
|
7 August 2024
|
NEC4 Option C quotes
|
|
3
|
120
|
6 August 2024
|
Instructing works outside Contractor's original Scope
|
|
8
|
182
|
21 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
78
|
16 July 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
238
|
15 July 2024
|
Can Prelim deductions occur under NEC 3 Option B
|
|
1
|
210
|
15 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
176
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
114
|
1 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
904
|
16 February 2024
|
Acceleration - Not achieving the new completion date
|
|
1
|
151
|
20 June 2024
|
NEC 4 ECC - PM Correct a Previous Decision Workflow
|
|
1
|
181
|
18 June 2024
|
Inclusion of Non-Accepted Compensation Events in Programme, governing Planned Completion
|
|
2
|
318
|
11 June 2024
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
211
|
11 June 2024
|
Can plant repairs be claimed under
|
|
2
|
183
|
8 June 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
276
|
23 April 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
190
|
26 April 2024
|
Built Connections 2024 - NEC User Group Conference
|
|
2
|
457
|
10 May 2024
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
590
|
13 May 2022
|
NEC4 - CE to reduce scope
|
|
1
|
544
|
8 March 2024
|
Does the SSCC need to be comprehensive?
|
|
6
|
437
|
8 March 2024
|
CE's on Option A Contract
|
|
4
|
704
|
23 February 2024
|
NEC3 ECC - Option B - Remeasurement Basis
|
|
5
|
1018
|
23 February 2024
|