Welcome to ReachBack
|
|
1
|
1216
|
28 November 2021
|
NEC4 Option B - Subcontractor
|
|
1
|
14
|
30 January 2023
|
NEC ECC: Do high temperatures constitute a Compensation Event under the conditions of the contract?
|
|
2
|
477
|
30 January 2023
|
Client requests/demands before they will issue award letter
|
|
0
|
29
|
28 January 2023
|
NEC4 Option C Advance Works
|
|
2
|
34
|
28 January 2023
|
Lack of Acceptances - Need some help please
|
|
1
|
41
|
27 January 2023
|
Is Cl 61.6 applicable to a Project Manager's assessment of a compensation event?
|
|
2
|
51
|
25 January 2023
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
394
|
23 January 2023
|
Dispute Resolution
|
|
1
|
55
|
23 January 2023
|
NEC4 ECS - Main Contract Scope
|
|
1
|
56
|
19 January 2023
|
Clause 16.1 - Notice of Early Warning
|
|
1
|
52
|
19 January 2023
|
Owned Equipment
|
|
4
|
74
|
18 January 2023
|
NEC - Acceleration with Outstanding CEs
|
|
1
|
46
|
18 January 2023
|
Defects Certificate - NEC4 ECC Option A
|
|
1
|
525
|
25 April 2022
|
Contract execution - Are wet signatures a legal requirement?
|
|
1
|
57
|
18 January 2023
|
NEC4 Option A - Quote substantiation
|
|
3
|
116
|
17 January 2023
|
JCT Final Account
|
|
2
|
356
|
16 January 2023
|
NEC4 ECS Option A - Cl60.1(19) - Materials Off Site
|
|
3
|
82
|
16 January 2023
|
NEC3 Option C: Risk items in the Target price
|
|
1
|
72
|
16 January 2023
|
NEC3 Option C: Non Working Equipment on Site
|
|
4
|
86
|
16 January 2023
|
Webinar - FastDraft Compensation Events Masterclass
|
|
48
|
760
|
16 January 2023
|
Construction Programmes
|
|
3
|
81
|
15 January 2023
|
Inclusion of Risk in a CE NEC4 Option A
|
|
1
|
89
|
15 January 2023
|
NEC3 Option A: Request for quotation through response to EWN
|
|
1
|
93
|
12 January 2023
|
Weather Data (or lack of)
|
|
2
|
78
|
12 January 2023
|
NEC3 ECC - Access Following Take Over
|
|
1
|
75
|
12 January 2023
|
What is the Dividing Date when PMI is Issued after a CE
|
|
1
|
94
|
12 January 2023
|
NEC ECC: Deemed acceptance of CE Quotation outside of time period
|
|
2
|
478
|
11 January 2023
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
524
|
11 January 2023
|
NEC4 Option C - PC Costs for Defect Revisits
|
|
8
|
202
|
10 January 2023
|