Welcome to ReachBack
|
|
1
|
2925
|
28 November 2021
|
NCE3 Opt A - Sectional Completion Dates
|
|
1
|
4
|
18 July 2025
|
Assessing Time Impact CEs out of chronological order
|
|
0
|
9
|
17 July 2025
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
2
|
15
|
16 July 2025
|
NEC 4 - Additional Compensation Events
|
|
3
|
24
|
16 July 2025
|
Two interfacing Contracts, one in Delay, both with the same Contractor
|
|
1
|
12
|
15 July 2025
|
Possible Defect After the Defects Certificate
|
|
0
|
6
|
15 July 2025
|
Subcontract documents not submitted by Contractor
|
|
0
|
9
|
14 July 2025
|
Design Liability
|
|
0
|
9
|
11 July 2025
|
NEC4 - Schedule of Cost Components - Subcontract Cost
|
|
0
|
19
|
11 July 2025
|
NEC 3 CE Assessemnt
|
|
3
|
76
|
11 July 2025
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
86
|
10 July 2025
|
Are legal fees allowable?
|
|
2
|
40
|
10 July 2025
|
Disallowed Cost
|
|
2
|
58
|
10 July 2025
|
NEC - Consequential Loss
|
|
5
|
60
|
10 July 2025
|
NEC3 Option C: Recovering Prelims
|
|
1
|
39
|
10 July 2025
|
Retrospective instructions
|
|
1
|
28
|
10 July 2025
|
NEC4 which programme dates?
|
|
5
|
79
|
10 July 2025
|
CE that includes extra over / weekend working rates
|
|
1
|
33
|
10 July 2025
|
NEC4 - Working Areas
|
|
1
|
48
|
10 July 2025
|
NEC3 Non payment by the Employer - Compensation Event with Y(UK)2
|
|
2
|
11
|
10 July 2025
|
Late issue of project managers assumptions
|
|
3
|
96
|
10 July 2025
|
Release Notes up to 2025-07-06 Contract Management Sprint 119
|
|
0
|
5
|
8 July 2025
|
NEC4 Option C - X1 adjustments to the target
|
|
2
|
31
|
4 July 2025
|
Damage and payments
|
|
0
|
20
|
2 July 2025
|
NEC4 Option C - Payment for Equipment
|
|
5
|
140
|
1 July 2025
|
Release Notes upto 2025-06-27 Academy
|
|
0
|
8
|
27 June 2025
|
Release Notes up to 2025-06-21 Contract Management Sprint 118
|
|
0
|
13
|
23 June 2025
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
94
|
22 June 2025
|
NEC 4 Option A - ECI?
|
|
2
|
39
|
22 June 2025
|