|
Welcome to ReachBack
|
|
1
|
2994
|
28 November 2021
|
|
Release Notes up to 2026-03-28 Contract Management Sprint 138
|
|
0
|
3
|
1 April 2026
|
|
NEC4 Option C - Income Protection
|
|
1
|
16
|
31 March 2026
|
|
NEC 4 remeasurement timescales
|
|
0
|
11
|
27 March 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
34
|
26 March 2026
|
|
Subcontracted costs in a NEC4 Option E CE
|
|
1
|
21
|
26 March 2026
|
|
Release Notes up to 2026-03-14 Contract Management Sprint 137
|
|
0
|
8
|
19 March 2026
|
|
Release Notes up to 2026-02-28 Contract Management Sprint 136
|
|
0
|
13
|
4 March 2026
|
|
NEC3 Short Contract hitting cashflow credit limit
|
|
1
|
21
|
27 February 2026
|
|
NEC4 Option A - Instructions / CE's
|
|
2
|
40
|
26 February 2026
|
|
NEC4 ECSC “short contract” Compensation Event Time
|
|
1
|
31
|
25 February 2026
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
7
|
49
|
23 February 2026
|
|
NEC Termination Process and the Role of The Employer
|
|
6
|
84
|
18 February 2026
|
|
NEC3 Option A - Can we recover the cost of resources not mobilised to the Working Areas?
|
|
3
|
106
|
11 February 2026
|
|
NEC3 Option E - Costs for correcting defects and resulting delay
|
|
3
|
57
|
11 February 2026
|
|
Release Notes up to 2026-01-31 Contract Management Sprint 134 & 135
|
|
0
|
17
|
3 February 2026
|
|
Interim Payments
|
|
2
|
45
|
29 January 2026
|
|
X22 Completion Procedure
|
|
3
|
44
|
24 January 2026
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
6
|
146
|
23 January 2026
|
|
NEC4 contract - accepted programme - changed decision
|
|
5
|
50
|
22 January 2026
|
|
Under FIDIC, can the Employer require the Contractor to purchase fencing instead of continuing to hire fencing that is already being provided?
|
|
2
|
23
|
21 January 2026
|
|
Release Notes up to 2026-01-17 Contract Management Sprint 131 132 133
|
|
0
|
12
|
20 January 2026
|
|
EOT under X22 - Stage 1 Impacts to Stage 2 Prior to NTP
|
|
0
|
22
|
20 January 2026
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
2
|
66
|
16 January 2026
|
|
Design Liability
|
|
2
|
82
|
16 January 2026
|
|
NEC4 Option C Sectional Completions and Scope removal
|
|
2
|
62
|
15 January 2026
|
|
NEC4 Option B CE Reduces total quantity
|
|
2
|
47
|
15 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
2
|
75
|
15 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
2
|
78
|
15 January 2026
|
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
2
|
37
|
14 January 2026
|