|
Welcome to ReachBack
|
|
1
|
3102
|
28 November 2021
|
|
Release Notes up to 2026-10-24 Contract Management Sprint 153
|
|
0
|
18
|
29 October 2026
|
|
Release Notes up to 2026-10-10 Contract Management Sprint 152
|
|
0
|
16
|
29 October 2026
|
|
Carbon border adjustment mechanism (CBAM)
|
|
2
|
33
|
28 October 2026
|
|
NEC4 ECC clause 63.5 – effect of a compensation event on X7 delay damages
|
|
1
|
43
|
22 October 2026
|
|
CECA rates use by contractor
|
|
1
|
55
|
21 October 2026
|
|
Programme/CE and Contractor lost opportunity
|
|
2
|
62
|
19 October 2026
|
|
Release Notes up to 2026-09-26 Contract Management Sprint 151
|
|
0
|
31
|
29 September 2026
|
|
Release Notes up to 2026-09-12 Contract Management Sprint 150
|
|
0
|
32
|
16 September 2026
|
|
Release Notes up to 2026-08-29 Contract Management Sprint 149
|
|
0
|
40
|
8 September 2026
|
|
Capping X7 Delay Damages
|
|
4
|
213
|
24 August 2026
|
|
Release Notes up to 2026-08-15 Contract Management Sprint 148
|
|
0
|
39
|
17 August 2026
|
|
EOT entitlement for delay post handover
|
|
3
|
158
|
13 August 2026
|
|
Webinar - Disallowed Cost in Practice: Why Issues Persist Despite Open-Book Principles
|
|
0
|
92
|
11 August 2026
|
|
NEC4 Option A - Design change and who benefits
|
|
3
|
219
|
7 August 2026
|
|
Release Notes up to 2026-08-01 Contract Management Sprint 147
|
|
0
|
67
|
4 August 2026
|
|
Release Notes up to 2026-07-18 Contract Management Sprint 146
|
|
0
|
39
|
22 July 2026
|
|
Should changes in law under NEC3 ECC clause X2 be notified even if they are planned to come into effect after the Completion Date?
|
|
3
|
124
|
17 July 2026
|
|
Defect Correction
|
|
3
|
166
|
15 July 2026
|
|
Release Notes up to 2026-07-04 Contract Management Sprint 145
|
|
0
|
75
|
7 July 2026
|
|
Restricted Working/Access Compensation Event Entitlement
|
|
3
|
154
|
3 July 2026
|
|
Failure by the Client to certify completion within 7 days
|
|
1
|
134
|
1 July 2026
|
|
NEC 4 CL 63.4 Option B
|
|
1
|
87
|
1 July 2026
|
|
Release Notes up to 2026-06-20 Contract Management Sprint 144
|
|
0
|
40
|
23 June 2026
|
|
Acceptance of programme
|
|
1
|
138
|
22 June 2026
|
|
Release Notes up to 2026-06-06 Contract Management Sprint 143
|
|
0
|
43
|
9 June 2026
|
|
NEC4 Amendment of assessment dates after the initial Assessment
|
|
2
|
203
|
3 June 2026
|
|
Release Notes up to 2026-05-23 Contract Management Sprint 142
|
|
0
|
50
|
27 May 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
143
|
15 May 2026
|
|
Release Notes up to 2026-05-09 Contract Management Sprint 140 and 141
|
|
0
|
40
|
12 May 2026
|