Welcome to ReachBack
|
|
1
|
1657
|
28 November 2021
|
NEC4 ECC Option C: Is EW the only gateway to CEs?
|
|
1
|
36
|
3 October 2023
|
Clause 32 Programme
|
|
0
|
16
|
3 October 2023
|
NEC4 ECSC - Defined Cost of People preparing quotation
|
|
1
|
37
|
3 October 2023
|
NEC4 Terms Service Contract / Short Contract
|
|
0
|
15
|
3 October 2023
|
ECC Option C: Are progressive scope of work treated as CEs?
|
|
1
|
49
|
2 October 2023
|
NEC 3 - Incentivised Key Dates
|
|
2
|
49
|
2 October 2023
|
Webinar - An Overview of Risk Management
|
|
1
|
32
|
29 September 2023
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
0
|
28
|
28 September 2023
|
Retrospective assessment of delay for compensation events
|
|
1
|
89
|
26 September 2023
|
Withdrawal of a subcontractor and Clause 60.1(19)
|
|
2
|
56
|
26 September 2023
|
Contract Administration Software - Cost Component
|
|
1
|
66
|
26 September 2023
|
NEC4 Subcontract - Which would be the best to use for multiple contracts with same subcontractor?
|
|
4
|
520
|
26 September 2023
|
Webinar - Apprenticeships in Surveying
|
|
0
|
33
|
25 September 2023
|
Release Notes up to 2023-09-24 Contract Management (Sprint 72 & 73)
|
|
0
|
25
|
25 September 2023
|
CDM Requirements for Non-Intrusive Site Surveys
|
|
0
|
54
|
22 September 2023
|
NEC4 Option A Third Party Design Review
|
|
1
|
45
|
21 September 2023
|
Rejecting a Contractor's Plan/Programme
|
|
1
|
53
|
20 September 2023
|
Tendered Start Date delayed as Contract Award Delayed, Contractor Wants Additional Payment What are our options?
|
|
2
|
461
|
20 September 2023
|
JCT Fluctuations
|
|
3
|
43
|
20 September 2023
|
NEC4 ECSS Defined Cost and Fee
|
|
3
|
67
|
19 September 2023
|
NEC4 Option C. Omitted section of work on Pmi
|
|
3
|
86
|
18 September 2023
|
Contractor remedy missing
|
|
4
|
165
|
15 September 2023
|
NEC3 Option A - Assessing a CE under 60.1(1)
|
|
1
|
107
|
14 September 2023
|
Webinar - How to produce and update your programme under NEC3 ECS
|
|
5
|
360
|
14 September 2023
|
Reversed Site Instruction
|
|
1
|
73
|
13 September 2023
|
Provsional Sum in Option B
|
|
0
|
67
|
13 September 2023
|
NEC4 ECC PM Scope of Services
|
|
0
|
51
|
12 September 2023
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
0
|
70
|
12 September 2023
|
Is failure to comply with a constraint in the Works Information a Defect
|
|
0
|
121
|
12 September 2023
|