|
Welcome to ReachBack
|
|
1
|
2972
|
28 November 2021
|
|
Articles of Agreement - purpose and uses instead of or together with JCT
|
|
2
|
15
|
14 January 2026
|
|
NEC4 contract - accepted programme - changed decision
|
|
0
|
1
|
14 January 2026
|
|
Design Liability
|
|
1
|
43
|
14 January 2026
|
|
Possible Defect After the Defects Certificate
|
|
1
|
44
|
14 January 2026
|
|
Assessing Time Impact CEs out of chronological order
|
|
1
|
42
|
14 January 2026
|
|
NEC 4 option A SSCC people costs
|
|
1
|
49
|
14 January 2026
|
|
Work schedules JCT Minor Works
|
|
1
|
24
|
14 January 2026
|
|
JCT SBC subcontract - omission of works
|
|
1
|
25
|
14 January 2026
|
|
General notice 2:15
|
|
1
|
18
|
14 January 2026
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
1
|
44
|
14 January 2026
|
|
Management Costs on Changes, Loss & Expense, JCT Design and Build
|
|
1
|
24
|
14 January 2026
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
1
|
38
|
14 January 2026
|
|
NEC4 Option B CE Reduces total quantity
|
|
1
|
26
|
14 January 2026
|
|
Application of X1.4 if Contractor is past Completion Date
|
|
1
|
20
|
5 January 2026
|
|
Authority imposing conditions
|
|
1
|
31
|
2 January 2026
|
|
NEC4 ECC Change to Critical Path
|
|
1
|
41
|
2 January 2026
|
|
Costs of Producing a Quotation during a delay period
|
|
1
|
30
|
2 January 2026
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
56
|
2 January 2026
|
|
Disallow costs for LADs non applied
|
|
3
|
21
|
2 January 2026
|
|
Subcontract documents not submitted by Contractor
|
|
3
|
64
|
2 January 2026
|
|
What to show on impacted programme?
|
|
1
|
32
|
2 January 2026
|
|
NEC forecasting unknown pricing
|
|
1
|
21
|
2 January 2026
|
|
2025: The Year in Review
|
|
0
|
4
|
1 January 2026
|
|
The use of AI to support scope writing
|
|
0
|
13
|
26 December 2025
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
6
|
22
|
22 December 2025
|
|
NEC4 Optional Clause X1
|
|
1
|
40
|
22 December 2025
|
|
Under FIDIC, can the Employer require the Contractor to purchase fencing instead of continuing to hire fencing that is already being provided?
|
|
0
|
11
|
17 December 2025
|
|
Ambiguity or Inconsistency
|
|
4
|
65
|
12 December 2025
|
|
Programme impact to be shown on CE quotations
|
|
3
|
23
|
10 December 2025
|