|
Welcome to ReachBack
|
|
1
|
3008
|
28 November 2021
|
|
Restricted Working/Access Compensation Event Entitlement
|
|
0
|
4
|
1 July 2026
|
|
Failure by the Client to certify completion within 7 days
|
|
1
|
17
|
1 July 2026
|
|
NEC4 Option A - Design change and who benefits
|
|
1
|
10
|
1 July 2026
|
|
NEC 4 CL 63.4 Option B
|
|
1
|
9
|
1 July 2026
|
|
Release Notes up to 2026-06-20 Contract Management Sprint 144
|
|
0
|
6
|
23 June 2026
|
|
Acceptance of programme
|
|
1
|
26
|
22 June 2026
|
|
Release Notes up to 2026-06-06 Contract Management Sprint 143
|
|
0
|
8
|
9 June 2026
|
|
NEC4 Amendment of assessment dates after the initial Assessment
|
|
2
|
97
|
3 June 2026
|
|
Release Notes up to 2026-05-23 Contract Management Sprint 142
|
|
0
|
14
|
27 May 2026
|
|
EOT entitlement for delay post handover
|
|
0
|
30
|
20 May 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
60
|
15 May 2026
|
|
Release Notes up to 2026-05-09 Contract Management Sprint 140 and 141
|
|
0
|
7
|
12 May 2026
|
|
JCT main contract
|
|
2
|
22
|
3 May 2026
|
|
JCT Sub-Contract
|
|
1
|
29
|
29 April 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
48
|
21 April 2026
|
|
Delay to Power On NEC4
|
|
3
|
46
|
20 April 2026
|
|
Does cl50.2 provide a valid method for reducing the amount due without the need to reopen implemented CEs?
|
|
2
|
95
|
20 April 2026
|
|
Programme acceptance where no PM response
|
|
5
|
70
|
17 April 2026
|
|
Release Notes up to 2026-04-11 Contract Management Sprint 139
|
|
0
|
12
|
13 April 2026
|
|
Effects on fuel prices due to the USA/Iran War
|
|
1
|
99
|
13 April 2026
|
|
NEC 4 remeasurement timescales
|
|
6
|
113
|
13 April 2026
|
|
Release Notes up to 2026-03-28 Contract Management Sprint 138
|
|
0
|
16
|
1 April 2026
|
|
NEC4 Option C - Income Protection
|
|
1
|
59
|
31 March 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
58
|
26 March 2026
|
|
Subcontracted costs in a NEC4 Option E CE
|
|
1
|
44
|
26 March 2026
|
|
Release Notes up to 2026-03-14 Contract Management Sprint 137
|
|
0
|
15
|
19 March 2026
|
|
Release Notes up to 2026-02-28 Contract Management Sprint 136
|
|
0
|
18
|
4 March 2026
|
|
NEC3 Short Contract hitting cashflow credit limit
|
|
1
|
32
|
27 February 2026
|
|
NEC4 Option A - Instructions / CE's
|
|
2
|
88
|
26 February 2026
|