|
Welcome to ReachBack
|
|
1
|
2965
|
28 November 2021
|
|
Valuations after completion
|
|
2
|
8
|
17 November 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
60
|
12 November 2025
|
|
NEC3: Recover Staff Costs During Christmas Shutdown?
|
|
0
|
17
|
11 November 2025
|
|
Costs of Producing a Quotation during a delay period
|
|
0
|
10
|
11 November 2025
|
|
Release Notes up to 2025-11-08 Contract Management Sprint 128
|
|
0
|
5
|
11 November 2025
|
|
NEC4 ECC Change to Critical Path
|
|
0
|
10
|
10 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
63
|
6 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
29
|
5 November 2025
|
|
NEC4 Option B CE Reduces total quantity
|
|
0
|
13
|
5 November 2025
|
|
Implementing a compensation event
|
|
1
|
31
|
3 November 2025
|
|
Release Notes upto 2025-10-31 Academy
|
|
0
|
3
|
31 October 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
67
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
27
|
30 October 2025
|
|
Release Notes up to 2025-10-25 Contract Management Sprint 127
|
|
0
|
8
|
28 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1693
|
22 October 2025
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
0
|
33
|
20 October 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
38
|
20 October 2025
|
|
NEC4 Option A 'fee percentage'
|
|
0
|
35
|
15 October 2025
|
|
Release Notes up to 2025-10-11 Contract Management Sprint 126
|
|
0
|
5
|
15 October 2025
|
|
Payment under Clause 50.7
|
|
2
|
58
|
7 October 2025
|
|
NEC3 ECC Option A - Payment of Contractor's staff working outside the Working Areas
|
|
1
|
62
|
3 October 2025
|
|
Management Costs on Changes, Loss & Expense, JCT Design and Build
|
|
0
|
16
|
3 October 2025
|
|
NEC3 Can Temporary Works be subject to a Defect?
|
|
7
|
115
|
2 October 2025
|
|
Sectional Completion after Completion
|
|
1
|
28
|
2 October 2025
|
|
Release Notes upto 2025-09-30 Academy
|
|
0
|
14
|
30 September 2025
|
|
Release Notes up to 2025-09-27 Contract Management Sprint 125
|
|
0
|
6
|
30 September 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
65
|
25 September 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
52
|
25 September 2025
|
|
NEC4 ECC Option D - Adjusting Quantities in BoQ
|
|
1
|
46
|
24 September 2025
|