About the Testing and Defects category
|
|
1
|
397
|
8 May 2024
|
NEC3 contract - single Defects notice with Schedule of Defects attached
|
|
1
|
297
|
18 October 2023
|
Repeat Test due to Defect
|
|
1
|
468
|
18 October 2023
|
NEC (3) option A
|
|
2
|
442
|
8 August 2023
|
How to close out a notified Defect that turns out not to have been a Defect
|
|
1
|
528
|
17 February 2023
|
NEC 4 accepting defect costs
|
|
3
|
1020
|
20 October 2022
|
NEC3: Option B Correction of Notified Defects
|
|
5
|
566
|
30 September 2022
|
Testing of applied Membrane
|
|
3
|
436
|
24 May 2022
|
Option X 18 - Limitation of Liability - Design Resource
|
|
3
|
613
|
18 March 2022
|
NEC3 ECS Option B - Correcting a Defect & cost assocaited with damage to other works
|
|
2
|
630
|
17 March 2022
|
NEC 3 Defect Notice... or Not?
|
|
1
|
678
|
7 January 2022
|
NEC4 Option A CL46 queries
|
|
2
|
787
|
7 January 2022
|
Nec 4 defect query
|
|
1
|
655
|
21 December 2021
|
NEC ECSC Option A Contract - defect correction period
|
|
4
|
1212
|
3 December 2021
|
NEC ECC: Defect notification and administration
|
|
2
|
2942
|
3 December 2021
|
43.4 - Who pays for the costs of allowing the contractor access for correcting a Defect?
|
|
9
|
1090
|
23 October 2021
|
Contesting Defects - NEC4 Option A
|
|
1
|
499
|
3 September 2021
|
Paying for repeat test due to Defect
|
|
1
|
476
|
25 August 2021
|
ECC Option A contract - Defect
|
|
2
|
1209
|
5 August 2021
|
NEC 3 Option B Disputed Defects
|
|
1
|
653
|
26 July 2021
|
Does the Supervisor have any responsibilities for design?
|
|
2
|
504
|
14 June 2021
|
Liability for stored Parts
|
|
1
|
434
|
15 April 2021
|
Challenging Supervisor's Defect Notification
|
|
1
|
553
|
9 April 2021
|
When can a defect be raised?
|
|
3
|
1110
|
7 December 2020
|
NEC ECC: Cracks in paving construction ECC Option A Client Design - is this a defect?
|
|
4
|
2074
|
6 December 2020
|
NEC 3 Option A disputed defects
|
|
1
|
687
|
27 November 2020
|
NEC ECC: More than one defects date?
|
|
4
|
1035
|
1 July 2020
|
NEC ECC: Defect correction prior to completion
|
|
1
|
1714
|
26 June 2020
|
NEC SC: What is the difference between the defects correction period and defects access period in an NEC 4 Supply contract
|
|
3
|
895
|
22 June 2020
|
NEC ECC: Option E Defects cost
|
|
1
|
1145
|
28 April 2020
|