|
About the General category
|
|
0
|
511
|
27 February 2020
|
|
NEC4 Option A - Design change and who benefits
|
|
1
|
37
|
1 July 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
61
|
26 March 2026
|
|
NEC4 Optional Clause X1
|
|
1
|
75
|
22 December 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
86
|
25 September 2025
|
|
NEC 4 - Equipment
|
|
2
|
121
|
22 April 2025
|
|
NEC3 EC Short Contract - Communcations and Period of Reply
|
|
1
|
86
|
19 March 2025
|
|
NEC4 Option B & Option D
|
|
3
|
209
|
23 November 2024
|
|
NEC 3 Contractor cant start work
|
|
2
|
92
|
16 October 2024
|
|
NEC 4 ECC Opt A Design and 27.1
|
|
1
|
87
|
21 August 2024
|
|
NEC3 ECC Early Warnings
|
|
1
|
86
|
15 August 2024
|
|
Use of schedules for Defined Cost
|
|
2
|
155
|
26 June 2024
|
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
237
|
11 June 2024
|
|
X1 in Contract but not being used
|
|
1
|
257
|
10 June 2024
|
|
NEC4 PSC Option E Programme changes
|
|
0
|
220
|
26 April 2024
|
|
Built Connections 2024 - NEC User Group Conference
|
|
0
|
476
|
4 March 2024
|
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
612
|
13 May 2022
|
|
Assignment or Novation?
|
|
2
|
678
|
26 October 2023
|
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
308
|
26 October 2023
|
|
Works Information and the accepted contractor design
|
|
2
|
759
|
19 October 2023
|
|
NEC3 ECC: Option C - Completion, Public Liability, Defects
|
|
1
|
616
|
18 October 2023
|
|
Webinar - An Overview of Risk Management
|
|
2
|
289
|
11 October 2023
|
|
NEC4 Terms Service Contract / Short Contract
|
|
1
|
310
|
11 October 2023
|
|
Rejecting a Contractor's Plan/Programme
|
|
1
|
315
|
20 September 2023
|
|
Contractor remedy missing
|
|
4
|
406
|
15 September 2023
|
|
Appropriate Contract Type
|
|
6
|
381
|
24 August 2023
|
|
TSC3 Contract dispute
|
|
6
|
403
|
3 August 2023
|
|
Can you say Scope will be completed during the defects period when it is not a defect?
|
|
5
|
659
|
1 August 2023
|
|
NEC TSC Contract - Option A
|
|
2
|
547
|
28 July 2023
|
|
Procuring NEC sub-subcontractors
|
|
1
|
505
|
21 July 2023
|