|
About the General category
|
|
0
|
513
|
27 February 2020
|
|
NEC4 Option A - Design change and who benefits
|
|
3
|
108
|
7 August 2026
|
|
Defect Correction
|
|
3
|
77
|
15 July 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
78
|
26 March 2026
|
|
NEC4 Optional Clause X1
|
|
1
|
79
|
22 December 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
99
|
25 September 2025
|
|
NEC 4 - Equipment
|
|
2
|
130
|
22 April 2025
|
|
NEC3 EC Short Contract - Communcations and Period of Reply
|
|
1
|
95
|
19 March 2025
|
|
NEC4 Option B & Option D
|
|
3
|
234
|
23 November 2024
|
|
NEC 3 Contractor cant start work
|
|
2
|
97
|
16 October 2024
|
|
NEC 4 ECC Opt A Design and 27.1
|
|
1
|
96
|
21 August 2024
|
|
NEC3 ECC Early Warnings
|
|
1
|
97
|
15 August 2024
|
|
Use of schedules for Defined Cost
|
|
2
|
160
|
26 June 2024
|
|
NEC Framework Contract - inclusion of non NEC Contracts for Task orders
|
|
1
|
245
|
11 June 2024
|
|
X1 in Contract but not being used
|
|
1
|
264
|
10 June 2024
|
|
NEC4 PSC Option E Programme changes
|
|
0
|
224
|
26 April 2024
|
|
Built Connections 2024 - NEC User Group Conference
|
|
0
|
481
|
4 March 2024
|
|
Webinar - NEC4 ECS Part 1/6: How the NEC4 Engineering and Construction Subcontract (ECS) is structured – the Options and documents
|
|
3
|
619
|
13 May 2022
|
|
Assignment or Novation?
|
|
2
|
687
|
26 October 2023
|
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
323
|
26 October 2023
|
|
Works Information and the accepted contractor design
|
|
2
|
772
|
19 October 2023
|
|
NEC3 ECC: Option C - Completion, Public Liability, Defects
|
|
1
|
622
|
18 October 2023
|
|
Webinar - An Overview of Risk Management
|
|
2
|
300
|
11 October 2023
|
|
NEC4 Terms Service Contract / Short Contract
|
|
1
|
318
|
11 October 2023
|
|
Rejecting a Contractor's Plan/Programme
|
|
1
|
318
|
20 September 2023
|
|
Contractor remedy missing
|
|
4
|
420
|
15 September 2023
|
|
Appropriate Contract Type
|
|
6
|
392
|
24 August 2023
|
|
TSC3 Contract dispute
|
|
6
|
420
|
3 August 2023
|
|
Can you say Scope will be completed during the defects period when it is not a defect?
|
|
5
|
679
|
1 August 2023
|
|
NEC TSC Contract - Option A
|
|
2
|
558
|
28 July 2023
|