About the Main options category
|
|
0
|
365
|
27 February 2020
|
Provisional items under NEC Type A contract
|
|
2
|
238
|
25 March 2024
|
Value Engineering - NEC4 Option A
|
|
1
|
208
|
23 October 2023
|
NEC 3: Option B: Cl.60.4
|
|
3
|
578
|
26 March 2023
|
Ambiguities 17.1
|
|
2
|
513
|
7 January 2022
|
NEC3 ECC Option B: Contractor has not priced an item in the Bill of Quantities
|
|
1
|
501
|
23 October 2021
|
60.1(1) exception bullet 2 not for valuation engineering
|
|
1
|
560
|
16 September 2021
|
ECC Option C Contract - WI
|
|
1
|
1110
|
5 August 2021
|
NEC ECC: Instructed works carried out in a different calendar month?
|
|
3
|
1069
|
2 June 2021
|
NEC ECC: conflict in Works Information
|
|
3
|
1822
|
20 May 2021
|
NEC PSC: When would a PSC Option G contract be the right procurement approach?
|
|
4
|
6472
|
23 February 2021
|
NEC3 ECC Hybrid contract; option A & C
|
|
1
|
725
|
23 September 2020
|
NEC Option B: Client saying Contractor responsible for quantities
|
|
1
|
635
|
15 September 2020
|
NEC ECC: Option A - Can the Employer define quantities as this is not an Option B?
|
|
1
|
605
|
3 July 2020
|
NEC ECC: Can you add to the Activity Schedule in NEC 3 Option C
|
|
1
|
501
|
27 June 2020
|
NEC ECC: Option A - difference between activity schedule and Works Information regarding payment
|
|
5
|
2295
|
17 June 2020
|
NEC ECC: Option A - change to a key date
|
|
1
|
839
|
7 April 2020
|
NEC ECC: Change from main Option B to E due to uncertainty over effects of COVID-19
|
|
1
|
928
|
7 April 2020
|
NEC ECC: Which contract option would be most suitable?
|
|
2
|
1275
|
30 March 2020
|
NEC ECC - Notify a CE under X2.1
|
|
1
|
477
|
26 March 2020
|
NEC ECC: Is Coronavirus / COVID-19 relief under X2 an option in Scotland?
|
|
1
|
757
|
18 March 2020
|
NEC ECC: Coronavirus - contractual implications
|
|
1
|
862
|
17 March 2020
|
NEC: Coronavirus what are the contractual implication with the NEC?
|
|
1
|
1322
|
16 March 2020
|
NEC ECC: Can an accepted programme under NEC be retracted for a wrong contract Completion Date
|
|
1
|
882
|
11 March 2020
|
NEC PSC: Which option?
|
|
1
|
1098
|
18 February 2020
|
NEC ECC: Option E payments
|
|
1
|
1186
|
17 February 2020
|
NEC ECC: Is an option E or F appropriate when the unit price of a subcontractor is fixed but not programme nor cost of the Contractor who will be managing those works
|
|
1
|
1399
|
17 February 2020
|
NEC TSC: Who is responsible for Price List quantities in an X19 Task Order?
|
|
1
|
1588
|
13 February 2020
|
NEC ECC: Retention in Option F
|
|
1
|
480
|
10 February 2020
|
NEC ECC: Under Option B do we have to provide all delivery tickets to the Client?
|
|
2
|
518
|
4 February 2020
|