About the Risk and Insurance category
|
|
1
|
388
|
8 May 2024
|
Risk allowance under NEC
|
|
1
|
751
|
14 June 2024
|
NEC4 PSC: PII Level v Cap
|
|
1
|
411
|
6 February 2024
|
Professional Indemnity Insurance query (NEC4)
|
|
4
|
345
|
21 November 2023
|
Contract Data part one: Insurances and Policy Excesses
|
|
6
|
423
|
3 August 2023
|
Contract Data part one: Risks and Insurance
|
|
0
|
436
|
5 April 2023
|
NEC4 - Contra Charges
|
|
1
|
701
|
30 March 2023
|
NEC4 ECC Option B - Stolen Materials
|
|
3
|
793
|
30 March 2023
|
3rd Party Damage Liability
|
|
1
|
613
|
9 May 2022
|
NEC3 Professional Services Contract - Provision of Resource
|
|
4
|
729
|
28 February 2022
|
NEC4 Subcontract: Recovery of costs under Clause 82
|
|
0
|
806
|
5 October 2021
|
Damage to Subcontractor's Equipment by the Contractor
|
|
2
|
647
|
29 June 2021
|
Takeover & Sectional Completion under NEC 3 Option A
|
|
1
|
727
|
22 June 2021
|
NEC3 ECC Option A
|
|
0
|
612
|
2 February 2021
|
NEC3: Insurance cost increase
|
|
1
|
619
|
31 December 2020
|
NEC ECC Option C: Activity Schedule, Risk and total of the Prices (target cost)
|
|
5
|
2600
|
11 December 2020
|
NEC 4 TSC x18 Consequential Loss
|
|
2
|
1192
|
26 November 2020
|
ECC Option B - Contractors Design Risk
|
|
1
|
787
|
10 August 2020
|
NEC ECC: If the insurance policy for the Contractor expires after completing the works,, how would this be dealt with under the NEC3 ECC contract??
|
|
3
|
1189
|
24 June 2020
|
NEC ECC: Take Off Risks under Option C Contracts
|
|
1
|
818
|
19 May 2020
|
NEC ECC: Who carries the risk when a subcontractor goes into administration
|
|
1
|
956
|
4 May 2020
|
NEC ECSC: Contractors Design Liability under ECSC
|
|
1
|
1180
|
28 April 2020
|
NEC ECSC: Does the ECSC adequately deal with the Contractors obligation and liability for Contractors design?
|
|
2
|
950
|
23 April 2020
|
NEC ECS: Take over before Completion Date and Sectional Completion
|
|
2
|
676
|
5 March 2020
|
NEC PSC - Appropriate durations for liability insurances
|
|
2
|
893
|
26 February 2020
|
NEC ECSC: Indemnities Cl.81.2
|
|
3
|
969
|
5 December 2019
|
NEC ECC: If an area of the Site physically changes post award of the contract who's risk is it?
|
|
6
|
915
|
2 December 2019
|
NEC ECC: Actual Defined Cost
|
|
1
|
960
|
29 November 2019
|
NEC ECC: Effects of IR35 Legislation
|
|
1
|
1041
|
29 November 2019
|
NEC ECS: Option A - lost plant on site
|
|
1
|
696
|
22 November 2019
|