About the Risk and Insurance category
|
|
0
|
228
|
27 February 2020
|
NEC4 ECC Option B - Stolen Materials
|
|
2
|
114
|
12 March 2023
|
3rd Party Damage Liability
|
|
1
|
352
|
9 May 2022
|
NEC3 Professional Services Contract - Provision of Resource
|
|
4
|
335
|
28 February 2022
|
NEC4 Subcontract: Recovery of costs under Clause 82
|
|
0
|
317
|
5 October 2021
|
Damage to Subcontractor's Equipment by the Contractor
|
|
2
|
311
|
29 June 2021
|
Takeover & Sectional Completion under NEC 3 Option A
|
|
1
|
382
|
22 June 2021
|
NEC3 ECC Option A
|
|
0
|
425
|
2 February 2021
|
NEC3: Insurance cost increase
|
|
1
|
409
|
31 December 2020
|
NEC ECC Option C: Activity Schedule, Risk and total of the Prices (target cost)
|
|
5
|
1086
|
11 December 2020
|
NEC 4 TSC x18 Consequential Loss
|
|
2
|
597
|
26 November 2020
|
ECC Option B - Contractors Design Risk
|
|
1
|
521
|
10 August 2020
|
NEC ECC: If the insurance policy for the Contractor expires after completing the works,, how would this be dealt with under the NEC3 ECC contract??
|
|
3
|
646
|
24 June 2020
|
NEC ECC: Take Off Risks under Option C Contracts
|
|
1
|
481
|
19 May 2020
|
NEC ECC: Who carries the risk when a subcontractor goes into administration
|
|
1
|
540
|
4 May 2020
|
NEC ECSC: Contractors Design Liability under ECSC
|
|
1
|
731
|
28 April 2020
|
NEC ECSC: Does the ECSC adequately deal with the Contractors obligation and liability for Contractors design?
|
|
2
|
653
|
23 April 2020
|
NEC ECS: Take over before Completion Date and Sectional Completion
|
|
2
|
424
|
5 March 2020
|
NEC PSC - Appropriate durations for liability insurances
|
|
2
|
561
|
26 February 2020
|
NEC ECSC: Indemnities Cl.81.2
|
|
3
|
554
|
5 December 2019
|
NEC ECC: If an area of the Site physically changes post award of the contract who's risk is it?
|
|
6
|
627
|
2 December 2019
|
NEC ECC: Actual Defined Cost
|
|
1
|
700
|
29 November 2019
|
NEC ECC: Effects of IR35 Legislation
|
|
1
|
727
|
29 November 2019
|
NEC ECS: Option A - lost plant on site
|
|
1
|
435
|
22 November 2019
|
NEC3/4 Risk Allocation
|
|
1
|
393
|
8 November 2019
|
NEC ECC: When does 'pro active risk mitigation' become 'change'
|
|
2
|
448
|
27 August 2019
|
NEC ECC: Option C Risk in CE quotes.
|
|
2
|
758
|
24 August 2019
|
NEC ECS: Option A – Extent of Subcontractor’s Liability under Clause 82.1.
|
|
1
|
1138
|
15 June 2019
|
NEC4 PSS - does X18 limitation exclude matters covered under insurances?
|
|
1
|
856
|
29 May 2019
|
NEC ECC: Who is culpable for the programme delay where free issue plant is damaged by the Contractor when offloaded?
|
|
1
|
384
|
29 March 2019
|