About the Payment category
|
|
0
|
360
|
27 February 2020
|
Payment of prelims under NEC3 option B
|
|
1
|
161
|
5 March 2023
|
NEC4 Term Service Subcontract Option C
|
|
1
|
81
|
17 February 2023
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
2
|
154
|
9 February 2023
|
NEC4 Option C Advance Works
|
|
2
|
134
|
28 January 2023
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
478
|
23 January 2023
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
591
|
11 January 2023
|
Advance Payments on the Payment Certificate
|
|
1
|
227
|
23 November 2022
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
554
|
19 July 2022
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
506
|
5 July 2022
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
324
|
14 June 2022
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
363
|
20 May 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
372
|
28 February 2022
|
Interim Deduction of Delay Damages
|
|
1
|
316
|
4 February 2022
|
No response to PA from contractor by the due date
|
|
1
|
230
|
27 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
427
|
21 January 2022
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
3288
|
27 November 2021
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
765
|
9 November 2021
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
4118
|
8 November 2021
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
468
|
2 November 2021
|
NEC Option E Defined Cost
|
|
0
|
288
|
27 October 2021
|
Adjustment of Target (total of the prices) after Adjudication NEC3 ECC Option C
|
|
3
|
281
|
5 August 2021
|
Withholding Payments
|
|
1
|
493
|
2 August 2021
|
Counters to "on account" certifications
|
|
0
|
285
|
21 July 2021
|
Cleaning Equipment Following a Change to the WI
|
|
1
|
337
|
19 July 2021
|
NEC3 Option C Insurance Premium Cost Recovery
|
|
2
|
552
|
19 May 2021
|
NEC4 - Termination of sub contract by sub contractor
|
|
1
|
588
|
27 April 2021
|
NEC ECC: Under Option C are agency staff considered as Subcontractor or People Cost, when considering the application of the working area overhead?
|
|
4
|
910
|
21 April 2021
|
NEC3 Option A - Access Dates/Prelims Reduction
|
|
7
|
681
|
8 April 2021
|
PSC3 Option C - withholding payment
|
|
0
|
355
|
7 April 2021
|