About the Payment category
|
|
0
|
435
|
27 February 2020
|
Final accounting subcontractors and disallowed cost in the main contract
|
|
0
|
67
|
7 September 2023
|
PSC Payment of Subconsultant Costs
|
|
3
|
136
|
18 July 2023
|
NEC3 ECC: Option A - an auditor has suggested clause 52.1 defined cost “deductions for discounts, rebates and taxes which can be recovered” applies to the total of the Prices (not just compensation events), is this correct?
|
|
5
|
1351
|
6 July 2023
|
NEC4 clause 51.1 & 51.2 late payment
|
|
1
|
210
|
6 June 2023
|
NEC ECC: Under option C, are the costs of dealing with an adjudication brought by a subcontractor disallowed?
|
|
3
|
1492
|
1 June 2023
|
Advanced Payment on Subcontract Order
|
|
5
|
221
|
11 May 2023
|
Miscalculation in activity schedule
|
|
6
|
248
|
25 April 2023
|
NEC4 PSC Option C 11.2 (21) PSPD Query
|
|
0
|
142
|
23 April 2023
|
Advanced payment for material products not yet manufactured
|
|
3
|
257
|
17 April 2023
|
NEC ECC - Option C, Title for materials where payment due during payment period (particularly during Corona Virus period)
|
|
4
|
1130
|
13 April 2023
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
3
|
409
|
28 March 2023
|
Payment of prelims under NEC3 option B
|
|
1
|
426
|
5 March 2023
|
NEC4 Term Service Subcontract Option C
|
|
1
|
186
|
17 February 2023
|
NEC4 Option C Advance Works
|
|
2
|
253
|
28 January 2023
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
655
|
23 January 2023
|
NEC ECC: What is "the amount of payments due to Subcontractors"?
|
|
2
|
767
|
11 January 2023
|
Advance Payments on the Payment Certificate
|
|
1
|
358
|
23 November 2022
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
904
|
19 July 2022
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
789
|
5 July 2022
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
464
|
14 June 2022
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
557
|
20 May 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
456
|
28 February 2022
|
Interim Deduction of Delay Damages
|
|
1
|
399
|
4 February 2022
|
No response to PA from contractor by the due date
|
|
1
|
281
|
27 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
597
|
21 January 2022
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
3831
|
27 November 2021
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
1054
|
9 November 2021
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
4538
|
8 November 2021
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
542
|
2 November 2021
|