About the Payment category
|
|
0
|
259
|
27 February 2020
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
85
|
19 July 2022
|
NEC4 Clause 50.4 If the Contractor does not submit an application
|
|
0
|
118
|
5 July 2022
|
ECC3 Pain/Gain Share Calculation
|
|
2
|
133
|
14 June 2022
|
NEC3 Professional Services Contract- Application for Payment or Invoice?
|
|
3
|
122
|
20 May 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
202
|
28 February 2022
|
Interim Deduction of Delay Damages
|
|
1
|
197
|
4 February 2022
|
No response to PA from contractor by the due date
|
|
1
|
142
|
27 January 2022
|
Clause X16 - Take over and its impact on retention
|
|
1
|
215
|
21 January 2022
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
2612
|
27 November 2021
|
Default Payment Notice under NEC 4 Subcontract
|
|
7
|
564
|
9 November 2021
|
NEC3 ECC option A - change in activity schedule
|
|
2
|
3616
|
8 November 2021
|
NEC Option C - Level of Cost Substantiation
|
|
1
|
344
|
2 November 2021
|
NEC Option E Defined Cost
|
|
0
|
185
|
27 October 2021
|
Adjustment of Target (total of the prices) after Adjudication NEC3 ECC Option C
|
|
3
|
209
|
5 August 2021
|
Withholding Payments
|
|
1
|
402
|
2 August 2021
|
Counters to "on account" certifications
|
|
0
|
204
|
21 July 2021
|
Cleaning Equipment Following a Change to the WI
|
|
1
|
263
|
19 July 2021
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
2
|
270
|
25 June 2021
|
NEC3 Option C Insurance Premium Cost Recovery
|
|
2
|
398
|
19 May 2021
|
NEC4 - Termination of sub contract by sub contractor
|
|
1
|
424
|
27 April 2021
|
NEC ECC: Under Option C are agency staff considered as Subcontractor or People Cost, when considering the application of the working area overhead?
|
|
4
|
665
|
21 April 2021
|
NEC3 Option A - Access Dates/Prelims Reduction
|
|
7
|
446
|
8 April 2021
|
PSC3 Option C - withholding payment
|
|
0
|
262
|
7 April 2021
|
NEC 3 Option E Deduction of cost based upon initial budget
|
|
2
|
444
|
4 February 2021
|
Staff costs for a quotation not requested by the Project Manager
|
|
3
|
343
|
2 February 2021
|
NEC3 ECS Option B - Contra charges
|
|
1
|
321
|
15 January 2021
|
NEC4 PSC Correct a payment certificate
|
|
1
|
590
|
14 January 2021
|
NEC4 Non Payment
|
|
3
|
388
|
21 December 2020
|
NEC4 ECC Option C - PWDD definition includes for 'advance payments' based on forecasts?
|
|
3
|
1005
|
9 December 2020
|