|
About the Payment category
|
|
0
|
621
|
27 February 2020
|
|
NEC PSC – Incomplete Monthly Reporting: Defect or Failure to Complete an Activity?
|
|
1
|
27
|
13 November 2026
|
|
NEC4 Amendment of assessment dates after the initial Assessment
|
|
2
|
209
|
3 June 2026
|
|
Does cl50.2 provide a valid method for reducing the amount due without the need to reopen implemented CEs?
|
|
2
|
160
|
20 April 2026
|
|
NEC4 Option C - Income Protection
|
|
1
|
103
|
31 March 2026
|
|
Valuations after completion
|
|
2
|
117
|
17 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
118
|
5 November 2025
|
|
Payment under Clause 50.7
|
|
2
|
114
|
7 October 2025
|
|
Retention Bond Equivalent to Cash Retention
|
|
2
|
85
|
29 August 2025
|
|
Are legal fees allowable?
|
|
2
|
139
|
10 July 2025
|
|
NEC4 Option C - Payment for Equipment
|
|
5
|
298
|
1 July 2025
|
|
NEC4 TSC contracts
|
|
2
|
86
|
2 April 2025
|
|
NEC Option C - X16 Pain Gain
|
|
6
|
361
|
18 December 2024
|
|
NEC Option C with no SCC
|
|
2
|
117
|
4 December 2024
|
|
NEC4 Option C Disallowed Costs Reasonable Hours
|
|
2
|
508
|
13 September 2024
|
|
NEC 3 - ECC - Direct / Subcontract Fee
|
|
2
|
95
|
3 September 2024
|
|
Bonus payments for People included as Defined Cost ECS3 Option C
|
|
4
|
264
|
29 August 2024
|
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
271
|
15 July 2024
|
|
NEC3 - PSC - OPTION C - Time Verification Audit
|
|
1
|
154
|
2 July 2024
|
|
Forecast Cost of the Work Not Done (Cl. 63.1)
|
|
4
|
402
|
12 June 2024
|
|
'Smash and grab' payment applications ad infinitum
|
|
1
|
326
|
28 April 2024
|
|
PSC3 Option C - withholding payment
|
|
1
|
620
|
15 April 2024
|
|
Payless Notice Requirements
|
|
5
|
670
|
19 March 2024
|
|
NEC 4 Option E - Bespoke Fee clause
|
|
1
|
638
|
8 March 2024
|
|
Unforeseen cost increases
|
|
0
|
470
|
6 October 2021
|
|
Compensation Event - Omits for existing scope
|
|
2
|
521
|
19 October 2023
|
|
Counters to "on account" certifications
|
|
1
|
562
|
19 October 2023
|
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
4
|
824
|
5 October 2023
|
|
Final accounting subcontractors and disallowed cost in the main contract
|
|
0
|
427
|
7 September 2023
|
|
PSC Payment of Subconsultant Costs
|
|
3
|
638
|
18 July 2023
|