About the Payment category
|
|
1
|
574
|
8 May 2024
|
NEC4 Option C Disallowed Costs Reasonable Hours
|
|
2
|
253
|
13 September 2024
|
NEC 3 - ECC - Direct / Subcontract Fee
|
|
2
|
46
|
3 September 2024
|
Bonus payments for People included as Defined Cost ECS3 Option C
|
|
4
|
72
|
29 August 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
236
|
15 July 2024
|
NEC3 - PSC - OPTION C - Time Verification Audit
|
|
1
|
70
|
2 July 2024
|
Forecast Cost of the Work Not Done (Cl. 63.1)
|
|
4
|
307
|
12 June 2024
|
'Smash and grab' payment applications ad infinitum
|
|
1
|
261
|
28 April 2024
|
PSC3 Option C - withholding payment
|
|
1
|
572
|
15 April 2024
|
Payless Notice Requirements
|
|
5
|
391
|
19 March 2024
|
NEC 4 Option E - Bespoke Fee clause
|
|
1
|
355
|
8 March 2024
|
Unforeseen cost increases
|
|
0
|
446
|
6 October 2021
|
Compensation Event - Omits for existing scope
|
|
2
|
429
|
19 October 2023
|
Counters to "on account" certifications
|
|
1
|
527
|
19 October 2023
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
4
|
737
|
5 October 2023
|
Final accounting subcontractors and disallowed cost in the main contract
|
|
0
|
377
|
7 September 2023
|
PSC Payment of Subconsultant Costs
|
|
3
|
464
|
18 July 2023
|
NEC3 ECC: Option A - an auditor has suggested clause 52.1 defined cost “deductions for discounts, rebates and taxes which can be recovered” applies to the total of the Prices (not just compensation events), is this correct?
|
|
5
|
1853
|
6 July 2023
|
NEC4 clause 51.1 & 51.2 late payment
|
|
1
|
714
|
6 June 2023
|
NEC ECC: Under option C, are the costs of dealing with an adjudication brought by a subcontractor disallowed?
|
|
3
|
1855
|
1 June 2023
|
Advanced Payment on Subcontract Order
|
|
5
|
507
|
11 May 2023
|
Miscalculation in activity schedule
|
|
6
|
447
|
25 April 2023
|
NEC4 PSC Option C 11.2 (21) PSPD Query
|
|
0
|
377
|
23 April 2023
|
Advanced payment for material products not yet manufactured
|
|
3
|
524
|
17 April 2023
|
NEC ECC - Option C, Title for materials where payment due during payment period (particularly during Corona Virus period)
|
|
4
|
1766
|
13 April 2023
|
NEC - Schedule of rates and fee %
|
|
3
|
1031
|
6 April 2023
|
NEC3 Option C: Changing a Subcontractor
|
|
1
|
411
|
15 March 2023
|
Payment of prelims under NEC3 option B
|
|
1
|
857
|
5 March 2023
|
NEC4 Term Service Subcontract Option C
|
|
1
|
355
|
17 February 2023
|
NEC4 Option C Advance Works
|
|
2
|
414
|
28 January 2023
|