About the Contract Data category
|
|
0
|
249
|
27 February 2020
|
Dispute Resolution
|
|
1
|
141
|
23 January 2023
|
NEC3 Works Information - Document/Information by Reference
|
|
2
|
360
|
3 October 2022
|
Boundaries of the Site
|
|
3
|
367
|
17 May 2022
|
NEC ECC: What items should be included / allowed for when calculating percentage for peoples overheads?
|
|
5
|
3144
|
9 July 2021
|
NEC 4 Option C Pain / Gain Percentages
|
|
3
|
1020
|
7 June 2021
|
Key Date, X5 & X7
|
|
3
|
424
|
19 April 2021
|
NEC4 Option C ECC clause 50.7 and Contract Data Part 1
|
|
1
|
522
|
4 January 2021
|
NEC3 ECC Option D - Data for Schedule of Cost Components
|
|
1
|
424
|
11 December 2020
|
NEC3 ECS: option A tender but Contract Data contains no dates
|
|
4
|
423
|
8 June 2020
|
NEC ECS: Do i have to provide the Contractor a full Defined Cost Breakdown to my Tender sum under an NEC3 Option A ECS?
|
|
2
|
481
|
29 May 2020
|
NEC ECC: Contractor to provide Insurance
|
|
1
|
691
|
28 April 2020
|
NEC ECS: Costs of rates included under NEC3 options C and E, CD2
|
|
1
|
644
|
28 April 2020
|
NEC PSC: Under NEC3, does the Employer's Agent have to be a named individual (or can it be a company)?
|
|
1
|
825
|
6 March 2020
|
NEC ECC: Are there any disadvantages from employer perspective of leaving tenderers to define activities?
|
|
1
|
688
|
3 March 2020
|
NEC ECC: Have submitted a design for a floor which Works Information was non-specific about in its type. Employer is now considering marble
|
|
3
|
457
|
3 March 2020
|
NEC ECS: Completion Date for a Subcontract which includes Maintenance
|
|
2
|
566
|
13 February 2020
|
NEC ECS: Applying Delay Damages
|
|
1
|
523
|
31 January 2020
|
NEC ECC: Can access dates be introduced mid-contract?
|
|
1
|
439
|
5 November 2019
|
NEC ECC: Completing Contract Data Part 2 Part 6 of NEC4 Option B
|
|
1
|
558
|
28 October 2019
|
NEC3 Option A - Working Area and defined cost of design.
|
|
1
|
506
|
24 October 2019
|
NEC ECC: Delay in Contract Award
|
|
1
|
670
|
18 October 2019
|
NEC ECC: Option A - Contract Data Part 2
|
|
1
|
868
|
16 October 2019
|
NEC ECC: Works Information reference in Contract Data 1
|
|
1
|
476
|
3 October 2019
|
NEC4 ECC: Appendix 5 Example tender assessment sheet
|
|
2
|
1497
|
27 September 2019
|
NEC ECC: Does the period for reply apply to the Contractor as well
|
|
6
|
2333
|
11 September 2019
|
NEC ECS: What is the purpose of naming the Employer/Client and Project Manager in CD1?
|
|
1
|
416
|
5 August 2019
|
NEC ECC: Contract Data Part 2 - How do we respond with more than a Single Fee
|
|
2
|
1190
|
25 July 2019
|
NEC ECS: Additional terms associated with key people
|
|
2
|
806
|
24 July 2019
|
NEC ECC: If the Project Manager accepts a Project programme and the Planned Dates are later than the Contract Dates what is the client accepting?
|
|
2
|
445
|
16 July 2019
|