|
About the Contract Data category
|
|
1
|
395
|
8 May 2024
|
|
PSC Option A Short Schedule of Cost Components
|
|
0
|
49
|
23 January 2025
|
|
X1 Base Date. First assessment immediately after base date has a Price adjustment
|
|
3
|
197
|
13 January 2025
|
|
Consultants Fee Percentage (85%)
|
|
5
|
206
|
1 November 2024
|
|
NEC3 ECS Opt A - X1 Price Adjustment for Inflation
|
|
5
|
624
|
1 December 2023
|
|
S/C not included fee in quotation NEC3 ECS OptA
|
|
2
|
223
|
10 November 2023
|
|
NEC3 ECC: Option E - Working & Design Area Overheads
|
|
4
|
2188
|
6 September 2023
|
|
Dispute Resolution
|
|
1
|
358
|
23 January 2023
|
|
NEC3 Works Information - Document/Information by Reference
|
|
2
|
704
|
3 October 2022
|
|
Boundaries of the Site
|
|
3
|
996
|
17 May 2022
|
|
NEC ECC: What items should be included / allowed for when calculating percentage for peoples overheads?
|
|
5
|
5328
|
9 July 2021
|
|
NEC 4 Option C Pain / Gain Percentages
|
|
3
|
2491
|
7 June 2021
|
|
Key Date, X5 & X7
|
|
3
|
836
|
19 April 2021
|
|
NEC4 Option C ECC clause 50.7 and Contract Data Part 1
|
|
1
|
880
|
4 January 2021
|
|
NEC3 ECC Option D - Data for Schedule of Cost Components
|
|
1
|
605
|
11 December 2020
|
|
NEC3 ECS: option A tender but Contract Data contains no dates
|
|
4
|
582
|
8 June 2020
|
|
NEC ECS: Do i have to provide the Contractor a full Defined Cost Breakdown to my Tender sum under an NEC3 Option A ECS?
|
|
2
|
868
|
29 May 2020
|
|
NEC ECC: Contractor to provide Insurance
|
|
1
|
1227
|
28 April 2020
|
|
NEC ECS: Costs of rates included under NEC3 options C and E, CD2
|
|
1
|
928
|
28 April 2020
|
|
NEC PSC: Under NEC3, does the Employer's Agent have to be a named individual (or can it be a company)?
|
|
1
|
1356
|
6 March 2020
|
|
NEC ECC: Are there any disadvantages from employer perspective of leaving tenderers to define activities?
|
|
1
|
1000
|
3 March 2020
|
|
NEC ECC: Have submitted a design for a floor which Works Information was non-specific about in its type. Employer is now considering marble
|
|
3
|
639
|
3 March 2020
|
|
NEC ECS: Completion Date for a Subcontract which includes Maintenance
|
|
2
|
994
|
13 February 2020
|
|
NEC ECS: Applying Delay Damages
|
|
1
|
840
|
31 January 2020
|
|
NEC ECC: Can access dates be introduced mid-contract?
|
|
1
|
745
|
5 November 2019
|
|
NEC ECC: Completing Contract Data Part 2 Part 6 of NEC4 Option B
|
|
1
|
773
|
28 October 2019
|
|
NEC3 Option A - Working Area and defined cost of design.
|
|
1
|
690
|
24 October 2019
|
|
NEC ECC: Delay in Contract Award
|
|
1
|
1102
|
18 October 2019
|
|
NEC ECC: Option A - Contract Data Part 2
|
|
1
|
1276
|
16 October 2019
|
|
NEC ECC: Works Information reference in Contract Data 1
|
|
1
|
744
|
3 October 2019
|