About the Secondary X, W and Y options category
|
|
0
|
380
|
27 February 2020
|
NEC 4 - Use of X20
|
|
0
|
117
|
5 March 2024
|
When can budget be set for X22 contract
|
|
2
|
242
|
22 December 2023
|
Utility Performance - CE or Not?
|
|
1
|
228
|
17 November 2023
|
Defect Plus Liquidated Damages
|
|
3
|
163
|
14 November 2023
|
Tenderer not able to provide a Performance Bond or Parent Company Guarantee
|
|
1
|
179
|
3 November 2023
|
NEC3 ECC: Option C - no X1 but CE's Extend Programme over Financial Year
|
|
3
|
1386
|
27 July 2023
|
Ukraine War and CE's
|
|
1
|
267
|
6 July 2023
|
NEC4 PSC Option A X1 Price Adjustment Factor Calculator
|
|
1
|
405
|
16 May 2023
|
X29 Is anyone using this?
|
|
0
|
293
|
13 April 2023
|
X1 for steel NEC Option A
|
|
2
|
496
|
2 February 2023
|
NEC ECC: How does X18 'Limitation of Liability' determine what the Liability is limited to?
|
|
2
|
5484
|
19 December 2022
|
Change to White Diesel Recovery Options
|
|
5
|
575
|
6 December 2022
|
Delay Damages from Contractor to Subcontractor - Penalty?
|
|
2
|
500
|
16 November 2022
|
NEC4 Option C secondary options advice please
|
|
2
|
709
|
10 November 2022
|
NEC3 Term Service X19 not accepting Task Order Dispute
|
|
3
|
446
|
4 July 2022
|
X5 sectional completion dates vs contract date
|
|
2
|
675
|
25 May 2022
|
Delay Damages X7 Option C
|
|
1
|
372
|
24 May 2022
|
Subcontractor Delay Damages
|
|
1
|
765
|
14 May 2022
|
NEC4 ECC Option C - X1 Effect on Contract Data Pt 2 SoCC Rates
|
|
1
|
438
|
11 May 2022
|
Variations to X1 Option A NEC 3 TSC and assessing compensation events
|
|
2
|
543
|
11 May 2022
|
X18 Supply Contract
|
|
2
|
591
|
25 April 2022
|
X1 PAF calculations
|
|
5
|
1663
|
19 April 2022
|
NEC ECC: X1 - Price Adjustment Factor - Proportion Calculation
|
|
8
|
6519
|
19 April 2022
|
X7 daily damages
|
|
1
|
392
|
21 February 2022
|
Is it possible to use NEC 4 Secondary Clasues in a NEC 3 option A Sub-Contract?
|
|
1
|
570
|
31 January 2022
|
NEC Option X1 Start date for fluctuation calculation
|
|
2
|
920
|
7 December 2021
|
NEC4 Option A Inflation
|
|
1
|
664
|
29 July 2021
|
NEC3 PSC: Applying Indexation
|
|
2
|
829
|
20 May 2021
|
ECI X22 Managing Changes to Stage 2 Before the Notice to Proceed
|
|
1
|
502
|
17 February 2021
|