About the Secondary X, W and Y options category
|
|
0
|
307
|
27 February 2020
|
NEC3 ECC: Option C - no X1 but CE's Extend Programme over Financial Year
|
|
3
|
1086
|
27 July 2023
|
Ukraine War and CE's
|
|
1
|
171
|
6 July 2023
|
NEC4 PSC Option A X1 Price Adjustment Factor Calculator
|
|
1
|
246
|
16 May 2023
|
X29 Is anyone using this?
|
|
0
|
158
|
13 April 2023
|
NEC ECC: How does X18 'Limitation of Liability' determine what the Liability is limited to?
|
|
2
|
4194
|
19 December 2022
|
Delay Damages from Contractor to Subcontractor - Penalty?
|
|
2
|
359
|
16 November 2022
|
NEC4 Option C secondary options advice please
|
|
2
|
452
|
10 November 2022
|
Subcontractor Delay Damages
|
|
1
|
554
|
14 May 2022
|
X18 Supply Contract
|
|
2
|
481
|
25 April 2022
|
X1 PAF calculations
|
|
5
|
1288
|
19 April 2022
|
NEC ECC: X1 - Price Adjustment Factor - Proportion Calculation
|
|
8
|
5772
|
19 April 2022
|
X7 daily damages
|
|
1
|
327
|
21 February 2022
|
Is it possible to use NEC 4 Secondary Clasues in a NEC 3 option A Sub-Contract?
|
|
1
|
422
|
31 January 2022
|
NEC Option X1 Start date for fluctuation calculation
|
|
2
|
753
|
7 December 2021
|
NEC4 Option A Inflation
|
|
1
|
587
|
29 July 2021
|
NEC3 PSC: Applying Indexation
|
|
2
|
717
|
20 May 2021
|
ECI X22 Managing Changes to Stage 2 Before the Notice to Proceed
|
|
1
|
417
|
17 February 2021
|
NEC4 X22 (ECI) and it's relationship with the Scope
|
|
2
|
1205
|
29 January 2021
|
NEC ECC: Use of Secondary Option X18
|
|
2
|
2603
|
21 September 2020
|
NEC ECC: Should we notify early warnings during stage 1 ECI?
|
|
1
|
545
|
16 July 2020
|
NEC3 TSC: What volume of reactive works can be carried out under an NEC3 TSC contract with no X19 clause
|
|
2
|
336
|
24 June 2020
|
NEC ECC: Collateral Warranty for Framework Agreement
|
|
1
|
430
|
18 June 2020
|
NEC ECC: W2 dispute resolution - period to notify
|
|
1
|
483
|
8 June 2020
|
NEC ECC: Retention on contracts
|
|
1
|
701
|
6 May 2020
|
NEC ECC: ECI - Additional clause for use with the NEC3 Engineering and Construction Contract (ECC)
|
|
1
|
447
|
16 April 2020
|
NEC TSC: Frequency of Price Adjustments for Inflation when using NEC4 TSC + X19
|
|
2
|
559
|
3 April 2020
|
NEC ECC: Notification associated with X2
|
|
3
|
907
|
3 April 2020
|
NEC ECC: Amendment to secondary clause wording such as X22
|
|
3
|
663
|
27 March 2020
|
NEC ECC: What happens if Project Manager is beyond time to assess a quotation?
|
|
1
|
501
|
28 February 2020
|