About the Termination category
|
|
0
|
296
|
27 February 2020
|
Un-communicative sub-contractor is pushing defect remedials past completion
|
|
1
|
360
|
4 February 2022
|
NEC3 R18 Termination
|
|
1
|
657
|
17 August 2020
|
NEC ECC: Employer termination
|
|
2
|
789
|
2 July 2020
|
NEC ECS: Works removed in entirety from Subcontractor due to Covid
|
|
2
|
384
|
2 June 2020
|
NEC ECS: Instruction de-scoping work - do I terminate a Subcontractor or follow CE process with them?
|
|
1
|
409
|
2 June 2020
|
NEC ECC: Option A with Options X11 incorporated
|
|
1
|
1043
|
9 May 2020
|
NEC TSC: Is Independent Checking Engineer a subcontractor under TSC?
|
|
1
|
448
|
28 April 2020
|
NEC ECC: As a Contractor I want to terminate with the client should they not provide a minimum number of jobs per day, how do I do this and which R clause do I use?
|
|
1
|
340
|
1 April 2020
|
NEC ECC: Termination fee Option A item A4 no fault termination
|
|
1
|
740
|
25 February 2020
|
NEC ECC: Termination of NEC 4 Contract (Option A)
|
|
1
|
967
|
12 February 2020
|
NEC ECC: What details should be included in a default notice issued under Clause 91.2?
|
|
1
|
1104
|
29 January 2020
|
NEC ECC: Contractor misses Key Date and PM fails to assess on time
|
|
1
|
352
|
26 January 2020
|
NEC ECS: Option A Contract Termination clauses
|
|
1
|
618
|
17 January 2020
|
NEC ECS: Option A Contract termination
|
|
2
|
593
|
10 January 2020
|
NEC3 ECS: Option A termination
|
|
1
|
544
|
1 October 2019
|
NEC3 PSC: To Terminate or Not to Terminate?
|
|
3
|
1272
|
30 September 2019
|
NEC ECC: Would it be a CE if the employer had excluded bullet point 3 of section 9 in their amendments?
|
|
2
|
1419
|
17 September 2019
|
NEC ECC: Project Manager issuing a termination certificate?
|
|
2
|
1393
|
15 August 2019
|
NEC ECC: Do I have to credit management charges for cancelled scope due to the Employer terminating the Contract?
|
|
1
|
477
|
15 July 2019
|
NEC ECS: Insolvency Termination - Take over
|
|
1
|
485
|
28 May 2019
|
NEC ECS: Option A - Procedure for a sub-contractor to terminate contract due to insolvency
|
|
1
|
429
|
15 March 2019
|
NEC ECC: Termination for any reason
|
|
1
|
1079
|
14 March 2019
|
NEC ECS: Is payment on termination due 13 weeks after notice of termination or 13 weeks after issue of the certificate of termination
|
|
1
|
1268
|
21 February 2019
|
NEC ECC: Termination & Pain Gain calculation
|
|
1
|
583
|
21 February 2019
|
NEC TSSC: Termination
|
|
1
|
528
|
8 January 2019
|
NEC ECS: Clause 90.3 intention to terminate contract
|
|
3
|
1707
|
6 November 2018
|
NEC ECC: Can someone describe the process the Employer will do in termination P1 & P2
|
|
1
|
1035
|
29 October 2018
|
NEC ECC: Roles in termination
|
|
1
|
1105
|
17 October 2018
|
NEC ECC: Employer Notified Termination Under Reason 90.3 R3
|
|
1
|
516
|
12 September 2018
|