About the Termination category
|
|
1
|
410
|
8 May 2024
|
Cl 93.2 - The amount due on termination
|
|
2
|
167
|
16 April 2024
|
NEC4 - The amount due on termination
|
|
0
|
220
|
1 November 2023
|
Un-communicative sub-contractor is pushing defect remedials past completion
|
|
1
|
507
|
4 February 2022
|
NEC4 Short Professional services contract termination
|
|
1
|
418
|
28 July 2021
|
NEC3 R18 Termination
|
|
1
|
811
|
17 August 2020
|
NEC ECC: Employer termination
|
|
2
|
977
|
2 July 2020
|
NEC ECS: Works removed in entirety from Subcontractor due to Covid
|
|
2
|
494
|
2 June 2020
|
NEC ECS: Instruction de-scoping work - do I terminate a Subcontractor or follow CE process with them?
|
|
1
|
566
|
2 June 2020
|
NEC ECC: Option A with Options X11 incorporated
|
|
1
|
1287
|
9 May 2020
|
NEC TSC: Is Independent Checking Engineer a subcontractor under TSC?
|
|
1
|
581
|
28 April 2020
|
NEC ECC: As a Contractor I want to terminate with the client should they not provide a minimum number of jobs per day, how do I do this and which R clause do I use?
|
|
1
|
473
|
1 April 2020
|
NEC ECC: Termination fee Option A item A4 no fault termination
|
|
1
|
912
|
25 February 2020
|
NEC ECC: Termination of NEC 4 Contract (Option A)
|
|
1
|
1317
|
12 February 2020
|
NEC ECC: What details should be included in a default notice issued under Clause 91.2?
|
|
1
|
1490
|
29 January 2020
|
NEC ECC: Contractor misses Key Date and PM fails to assess on time
|
|
1
|
477
|
26 January 2020
|
NEC ECS: Option A Contract Termination clauses
|
|
1
|
807
|
17 January 2020
|
NEC ECS: Option A Contract termination
|
|
2
|
754
|
10 January 2020
|
NEC3 ECS: Option A termination
|
|
1
|
718
|
1 October 2019
|
NEC3 PSC: To Terminate or Not to Terminate?
|
|
3
|
1666
|
30 September 2019
|
NEC ECC: Would it be a CE if the employer had excluded bullet point 3 of section 9 in their amendments?
|
|
2
|
1552
|
17 September 2019
|
NEC ECC: Project Manager issuing a termination certificate?
|
|
2
|
1581
|
15 August 2019
|
NEC ECC: Do I have to credit management charges for cancelled scope due to the Employer terminating the Contract?
|
|
1
|
583
|
15 July 2019
|
NEC ECS: Insolvency Termination - Take over
|
|
1
|
608
|
28 May 2019
|
NEC ECS: Option A - Procedure for a sub-contractor to terminate contract due to insolvency
|
|
1
|
576
|
15 March 2019
|
NEC ECC: Termination for any reason
|
|
1
|
1354
|
14 March 2019
|
NEC ECS: Is payment on termination due 13 weeks after notice of termination or 13 weeks after issue of the certificate of termination
|
|
1
|
1581
|
21 February 2019
|
NEC ECC: Termination & Pain Gain calculation
|
|
1
|
792
|
21 February 2019
|
NEC TSSC: Termination
|
|
1
|
668
|
8 January 2019
|
NEC ECS: Clause 90.3 intention to terminate contract
|
|
3
|
2343
|
6 November 2018
|