|
About the NEC3 and NEC4 Contracts category
|
|
1
|
1107
|
8 May 2024
|
|
Does cl50.2 provide a valid method for reducing the amount due without the need to reopen implemented CEs?
|
|
2
|
7
|
20 April 2026
|
|
Programme acceptance where no PM response
|
|
5
|
23
|
17 April 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
0
|
9
|
16 April 2026
|
|
NEC 4 remeasurement timescales
|
|
6
|
45
|
13 April 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
0
|
10
|
13 April 2026
|
|
NEC4 Option C - Income Protection
|
|
1
|
36
|
31 March 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
43
|
26 March 2026
|
|
NEC3 Short Contract hitting cashflow credit limit
|
|
1
|
24
|
27 February 2026
|
|
NEC4 Option A - Instructions / CE's
|
|
2
|
49
|
26 February 2026
|
|
NEC4 ECSC “short contract” Compensation Event Time
|
|
1
|
37
|
25 February 2026
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
7
|
57
|
23 February 2026
|
|
NEC Termination Process and the Role of The Employer
|
|
6
|
90
|
18 February 2026
|
|
NEC3 Option A - Can we recover the cost of resources not mobilised to the Working Areas?
|
|
3
|
115
|
11 February 2026
|
|
X22 Completion Procedure
|
|
3
|
48
|
24 January 2026
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
2
|
66
|
16 January 2026
|
|
Design Liability
|
|
2
|
84
|
16 January 2026
|
|
NEC4 Option C Sectional Completions and Scope removal
|
|
2
|
63
|
15 January 2026
|
|
Possible Defect After the Defects Certificate
|
|
1
|
68
|
14 January 2026
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
78
|
2 January 2026
|
|
Subcontract documents not submitted by Contractor
|
|
3
|
88
|
2 January 2026
|
|
What to show on impacted programme?
|
|
1
|
46
|
2 January 2026
|
|
NEC4 Optional Clause X1
|
|
1
|
65
|
22 December 2025
|
|
Ambiguity or Inconsistency
|
|
4
|
87
|
12 December 2025
|
|
NEC4 Option C dispute timescales and entitlement
|
|
3
|
52
|
10 December 2025
|
|
Inflation uplift calculation fro Framework
|
|
1
|
30
|
6 December 2025
|
|
Acceptance of NCE
|
|
1
|
41
|
6 December 2025
|
|
Design Prelims on an Activity Schedule
|
|
1
|
38
|
5 December 2025
|
|
Application of Fees for Subcontracted Works
|
|
1
|
43
|
3 December 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
50
|
28 November 2025
|