|
About the NEC3 and NEC4 Contracts category
|
|
0
|
1141
|
27 February 2020
|
|
NEC4 Subcontract - Drawings & BoQ descrepency CE
|
|
0
|
13
|
25 November 2026
|
|
NEC PSC – Incomplete Monthly Reporting: Defect or Failure to Complete an Activity?
|
|
1
|
31
|
13 November 2026
|
|
NEC4 PSC OPTION a - Costof preparing quotation
|
|
2
|
42
|
12 November 2026
|
|
NEC4 ECC clause 63.5 – effect of a compensation event on X7 delay damages
|
|
1
|
59
|
22 October 2026
|
|
CECA rates use by contractor
|
|
1
|
77
|
21 October 2026
|
|
Programme/CE and Contractor lost opportunity
|
|
2
|
101
|
19 October 2026
|
|
Capping X7 Delay Damages
|
|
4
|
228
|
24 August 2026
|
|
Webinar - Disallowed Cost in Practice: Why Issues Persist Despite Open-Book Principles
|
|
0
|
101
|
11 August 2026
|
|
NEC4 Option A - Design change and who benefits
|
|
3
|
230
|
7 August 2026
|
|
Should changes in law under NEC3 ECC clause X2 be notified even if they are planned to come into effect after the Completion Date?
|
|
3
|
131
|
17 July 2026
|
|
Defect Correction
|
|
3
|
179
|
15 July 2026
|
|
Failure by the Client to certify completion within 7 days
|
|
1
|
140
|
1 July 2026
|
|
NEC 4 CL 63.4 Option B
|
|
1
|
91
|
1 July 2026
|
|
Acceptance of programme
|
|
1
|
149
|
22 June 2026
|
|
NEC4 Amendment of assessment dates after the initial Assessment
|
|
2
|
212
|
3 June 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
149
|
15 May 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
103
|
21 April 2026
|
|
Does cl50.2 provide a valid method for reducing the amount due without the need to reopen implemented CEs?
|
|
2
|
161
|
20 April 2026
|
|
Programme acceptance where no PM response
|
|
5
|
143
|
17 April 2026
|
|
NEC 4 remeasurement timescales
|
|
6
|
184
|
13 April 2026
|
|
NEC4 Option C - Income Protection
|
|
1
|
105
|
31 March 2026
|
|
Definition and Context of the term "Others"
|
|
1
|
123
|
26 March 2026
|
|
NEC3 Short Contract hitting cashflow credit limit
|
|
1
|
54
|
27 February 2026
|
|
NEC4 Option A - Instructions / CE's
|
|
2
|
180
|
26 February 2026
|
|
NEC4 ECSC “short contract” Compensation Event Time
|
|
1
|
94
|
25 February 2026
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
7
|
145
|
23 February 2026
|
|
NEC Termination Process and the Role of The Employer
|
|
6
|
216
|
18 February 2026
|
|
NEC3 Option A - Can we recover the cost of resources not mobilised to the Working Areas?
|
|
3
|
209
|
11 February 2026
|
|
X22 Completion Procedure
|
|
3
|
110
|
24 January 2026
|