About the NEC3 and NEC4 Contracts category
|
|
1
|
1080
|
8 May 2024
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
3
|
36
|
10 June 2025
|
NEC 4 Subcontract - CE Assessments
|
|
0
|
22
|
9 June 2025
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
3
|
84
|
9 June 2025
|
Late issue of project managers assumptions
|
|
2
|
73
|
9 June 2025
|
NEC4 Option A - Priced with a BoQ
|
|
2
|
87
|
9 June 2025
|
NEC4 Opt C - X22 - Inflation of Subcontractor Prices
|
|
1
|
43
|
6 June 2025
|
NEC4 PSC Option E - can I disallow time booked in a payment application
|
|
1
|
16
|
6 June 2025
|
NEC4 Clause 65 Proposed Instructions
|
|
1
|
53
|
29 May 2025
|
NEC4 Option C - Payment for Equipment
|
|
3
|
84
|
28 May 2025
|
NEC 4 Option B - Cl60.4
|
|
2
|
44
|
23 May 2025
|
NEC3 Subcontractor non-compliance with licence
|
|
2
|
34
|
20 May 2025
|
Quotation Assessments Under X2
|
|
1
|
98
|
15 May 2025
|
NEC4 SSCC charges on downtime
|
|
1
|
35
|
14 May 2025
|
PM Instructing Additional Works After Defects Date
|
|
2
|
69
|
9 May 2025
|
Compensation Events and Delay
|
|
1
|
73
|
9 May 2025
|
NEC4 Option A Compensation Event
|
|
3
|
108
|
2 May 2025
|
CE quotations & Programme Impact
|
|
1
|
89
|
2 May 2025
|
Project timelines/durations of Others, not defined at Tender stage
|
|
3
|
53
|
29 April 2025
|
Access to the site not granted due to weather conditions
|
|
1
|
48
|
28 April 2025
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
78
|
24 April 2025
|
NEC 4 - Equipment
|
|
2
|
62
|
22 April 2025
|
Nec3 compensation for information delay
|
|
2
|
63
|
22 April 2025
|
Cost of Correction of Defects in a NEC 3 Option F
|
|
0
|
33
|
16 April 2025
|
NEC3 - Correcting a PM Assumption
|
|
2
|
70
|
13 April 2025
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
267
|
10 April 2025
|
Defect in an NEC Option A subcontractors works
|
|
3
|
64
|
9 April 2025
|
NEC3 Lack of Access CE
|
|
5
|
164
|
9 April 2025
|
NEC4 TSC contracts
|
|
2
|
39
|
2 April 2025
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
84
|
31 March 2025
|