|
About the NEC3 and NEC4 Contracts category
|
|
1
|
1105
|
8 May 2024
|
|
NEC4 Option A 'fee percentage'
|
|
1
|
49
|
2 January 2026
|
|
Subcontract documents not submitted by Contractor
|
|
3
|
56
|
2 January 2026
|
|
What to show on impacted programme?
|
|
1
|
26
|
2 January 2026
|
|
NEC4 ECSC "short contract" Quotation Assumptions
|
|
6
|
15
|
22 December 2025
|
|
NEC4 Optional Clause X1
|
|
1
|
34
|
22 December 2025
|
|
Ambiguity or Inconsistency
|
|
4
|
59
|
12 December 2025
|
|
NEC4 Option C dispute timescales and entitlement
|
|
3
|
35
|
10 December 2025
|
|
Inflation uplift calculation fro Framework
|
|
1
|
17
|
6 December 2025
|
|
Acceptance of NCE
|
|
1
|
34
|
6 December 2025
|
|
Design Prelims on an Activity Schedule
|
|
1
|
20
|
5 December 2025
|
|
Application of Fees for Subcontracted Works
|
|
1
|
26
|
3 December 2025
|
|
Subcontractors in Compensation Event Quotations
|
|
1
|
30
|
28 November 2025
|
|
Error in BoQ NEC3 Option B
|
|
3
|
76
|
25 November 2025
|
|
NEC4 ECC PMs required, Dublin
|
|
0
|
33
|
19 November 2025
|
|
Valuations after completion
|
|
2
|
50
|
17 November 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
107
|
12 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
82
|
6 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
57
|
5 November 2025
|
|
Implementing a compensation event
|
|
1
|
41
|
3 November 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
95
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
33
|
30 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1711
|
22 October 2025
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
0
|
36
|
20 October 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
44
|
20 October 2025
|
|
Payment under Clause 50.7
|
|
2
|
71
|
7 October 2025
|
|
NEC3 ECC Option A - Payment of Contractor's staff working outside the Working Areas
|
|
1
|
64
|
3 October 2025
|
|
NEC3 Can Temporary Works be subject to a Defect?
|
|
7
|
123
|
2 October 2025
|
|
Sectional Completion after Completion
|
|
1
|
33
|
2 October 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
69
|
25 September 2025
|