About the NEC3 and NEC4 Contracts category
|
|
1
|
1090
|
8 May 2024
|
NEC4 which programme dates?
|
|
4
|
50
|
1 July 2025
|
NEC4 Option C - Payment for Equipment
|
|
5
|
128
|
1 July 2025
|
Retrospective instructions
|
|
0
|
4
|
1 July 2025
|
NEC3 Option C: Recovering Prelims
|
|
0
|
18
|
26 June 2025
|
Are legal fees allowable?
|
|
1
|
18
|
23 June 2025
|
NEC 3 CE Assessemnt
|
|
1
|
47
|
22 June 2025
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
87
|
22 June 2025
|
Disallowed Cost
|
|
1
|
38
|
22 June 2025
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
25
|
22 June 2025
|
NEC 4 Subcontract - CE Assessments
|
|
0
|
57
|
9 June 2025
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
3
|
93
|
9 June 2025
|
Late issue of project managers assumptions
|
|
2
|
84
|
9 June 2025
|
NEC4 Option A - Priced with a BoQ
|
|
2
|
109
|
9 June 2025
|
NEC4 Opt C - X22 - Inflation of Subcontractor Prices
|
|
1
|
58
|
6 June 2025
|
NEC4 PSC Option E - can I disallow time booked in a payment application
|
|
1
|
38
|
6 June 2025
|
NEC4 Clause 65 Proposed Instructions
|
|
1
|
59
|
29 May 2025
|
NEC 4 Option B - Cl60.4
|
|
2
|
59
|
23 May 2025
|
NEC3 Subcontractor non-compliance with licence
|
|
2
|
36
|
20 May 2025
|
Quotation Assessments Under X2
|
|
1
|
116
|
15 May 2025
|
NEC4 SSCC charges on downtime
|
|
1
|
43
|
14 May 2025
|
PM Instructing Additional Works After Defects Date
|
|
2
|
77
|
9 May 2025
|
Compensation Events and Delay
|
|
1
|
84
|
9 May 2025
|
NEC4 Option A Compensation Event
|
|
3
|
114
|
2 May 2025
|
CE quotations & Programme Impact
|
|
1
|
94
|
2 May 2025
|
Project timelines/durations of Others, not defined at Tender stage
|
|
3
|
54
|
29 April 2025
|
Access to the site not granted due to weather conditions
|
|
1
|
51
|
28 April 2025
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
83
|
24 April 2025
|
NEC 4 - Equipment
|
|
2
|
66
|
22 April 2025
|
Nec3 compensation for information delay
|
|
2
|
65
|
22 April 2025
|