About the NEC3 and NEC4 Contracts category
|
|
1
|
1032
|
8 May 2024
|
Can X1.3 be applied after compensantion event implementation
|
|
1
|
26
|
7 March 2025
|
Competitiveness of SOCC 1 people cost
|
|
1
|
37
|
6 March 2025
|
Scope of Compensation Event did not materialise - how to resolve?
|
|
1
|
19
|
6 March 2025
|
NEC 4 Option C - SCCO, calculation of hourly rate to determine Define Cost
|
|
3
|
26
|
5 March 2025
|
Construction Tolerences and Bill of Quantities
|
|
1
|
34
|
28 February 2025
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
30
|
26 February 2025
|
Treatment of Risk in Compensation Event Quotes
|
|
4
|
78
|
26 February 2025
|
Clause 31 Programme/Access Dates
|
|
1
|
36
|
20 February 2025
|
CE quotations & Programme Impact
|
|
0
|
32
|
19 February 2025
|
NEC 4 PSC Clause 50.3
|
|
2
|
32
|
12 February 2025
|
Company car insurance
|
|
1
|
53
|
10 February 2025
|
NEC4 Option C Defined Costs People
|
|
1
|
128
|
29 January 2025
|
How to assess a "delay" to a Key Date for an instruction to change a Key Date under NEC 4 Cl 14.3
|
|
1
|
75
|
29 January 2025
|
PSC Option A Short Schedule of Cost Components
|
|
0
|
30
|
23 January 2025
|
Liquidated Damages on paperwork
|
|
2
|
94
|
21 January 2025
|
NEC3 Professional Services Contract - Retrospective CE Paperwork
|
|
2
|
48
|
17 January 2025
|
Subcontractor fee % as part of a tender return
|
|
1
|
83
|
14 January 2025
|
NEC3 Short Subcontract - Assessing and Recovering the Cost of Delays
|
|
0
|
54
|
14 January 2025
|
X1 Base Date. First assessment immediately after base date has a Price adjustment
|
|
3
|
77
|
13 January 2025
|
Subcontractor fee percentage as part of tender price
|
|
2
|
46
|
10 January 2025
|
Additional Site Information post contract
|
|
5
|
75
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
79
|
2 January 2025
|
NEC4: Engineering and Construction Short Subcontract
|
|
1
|
63
|
25 December 2024
|
X1 application on NEC Supply Contract
|
|
3
|
86
|
19 December 2024
|
NEC Option C - X16 Pain Gain
|
|
6
|
77
|
18 December 2024
|
Option B - Measurement method for PWDD
|
|
3
|
64
|
18 December 2024
|
Late issue of project managers assumptions
|
|
1
|
56
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
98
|
13 December 2024
|
NEC4: PM's mistake in Accepted Programme impact CE assessment
|
|
3
|
123
|
9 December 2024
|