|
About the NEC3 and NEC4 Contracts category
|
|
1
|
1102
|
8 May 2024
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
2
|
13
|
8 November 2025
|
|
NEC 4 Option B - Defined Cost or Rates?
|
|
2
|
51
|
6 November 2025
|
|
Prelims payments for a Contract where Planned Completion is beyond Contract Completion with no CE to award time
|
|
2
|
13
|
5 November 2025
|
|
Implementing a compensation event
|
|
1
|
29
|
3 November 2025
|
|
NEC4 ECC Option C - Reduction of Scope - Brings forward planned completion
|
|
1
|
44
|
30 October 2025
|
|
Tender Clarifications forming part of scope
|
|
1
|
24
|
30 October 2025
|
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
5
|
1689
|
22 October 2025
|
|
NEC4 Option A Term Service - Fee Percentage
|
|
0
|
25
|
20 October 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
30
|
20 October 2025
|
|
NEC4 Option A 'fee percentage'
|
|
0
|
32
|
15 October 2025
|
|
Payment under Clause 50.7
|
|
2
|
53
|
7 October 2025
|
|
NEC3 ECC Option A - Payment of Contractor's staff working outside the Working Areas
|
|
1
|
49
|
3 October 2025
|
|
NEC3 Can Temporary Works be subject to a Defect?
|
|
7
|
112
|
2 October 2025
|
|
Sectional Completion after Completion
|
|
1
|
27
|
2 October 2025
|
|
Pricing Schedule incorrectly calculated
|
|
4
|
65
|
25 September 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
49
|
25 September 2025
|
|
NEC4 ECC Option D - Adjusting Quantities in BoQ
|
|
1
|
44
|
24 September 2025
|
|
NEC 4 - Option C (X11 - Termination)
|
|
5
|
146
|
4 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
84
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
232
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
65
|
3 September 2025
|
|
NEC - the Site and the boundaries of the site
|
|
4
|
79
|
2 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
168
|
2 September 2025
|
|
Retention Bond Equivalent to Cash Retention
|
|
2
|
36
|
29 August 2025
|
|
NCE3 Opt A - Sectional Completion Dates
|
|
2
|
62
|
13 August 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
96
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
137
|
11 August 2025
|
|
NEC4 ECC PM Exam - Failed Twice
|
|
1
|
84
|
8 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3127
|
5 August 2025
|