Additional Site Information post contract
|
|
5
|
76
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
81
|
2 January 2025
|
NEC4: Engineering and Construction Short Subcontract
|
|
1
|
65
|
25 December 2024
|
X1 application on NEC Supply Contract
|
|
3
|
87
|
19 December 2024
|
NEC Option C - X16 Pain Gain
|
|
6
|
84
|
18 December 2024
|
Option B - Measurement method for PWDD
|
|
3
|
64
|
18 December 2024
|
Late issue of project managers assumptions
|
|
1
|
58
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
103
|
13 December 2024
|
NEC4: PM's mistake in Accepted Programme impact CE assessment
|
|
3
|
127
|
9 December 2024
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
55
|
6 December 2024
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
56
|
4 December 2024
|
NEC Option C with no SCC
|
|
2
|
56
|
4 December 2024
|
NEC 3 - Staff schedule of rates + fee percentage
|
|
3
|
205
|
4 December 2024
|
NEC4 Option C SOCC Sick Pay
|
|
0
|
48
|
4 December 2024
|
NEC4 Option B & Option D
|
|
3
|
142
|
23 November 2024
|
NEC4: Maintaining Terminal Float while CE delay is being assessed
|
|
2
|
185
|
23 November 2024
|
Interpretation of Clause 63.1
|
|
1
|
89
|
22 November 2024
|
NEC 4 Framework Contract
|
|
0
|
43
|
8 November 2024
|
Consultants Fee Percentage (85%)
|
|
5
|
156
|
1 November 2024
|
Correction of a Project Managers Assumption or Acceleration?
|
|
1
|
59
|
25 October 2024
|
NEC 4 option B - discrepancy between the BOQ and contract drawings
|
|
1
|
120
|
17 October 2024
|
Fines & Tolls payable or not
|
|
1
|
79
|
17 October 2024
|
NEC 3 Option C - Change to the work sequence in the WI, removing restriction
|
|
3
|
49
|
16 October 2024
|
NEC 3 Contractor cant start work
|
|
2
|
84
|
16 October 2024
|
NEC3 Option X1 Price Adjustment for Inflation
|
|
2
|
245
|
16 October 2024
|
Damage to Employer's Property
|
|
1
|
82
|
16 October 2024
|
CE occuring Delays
|
|
3
|
131
|
15 October 2024
|
NEC4 - ECC Separable Portions
|
|
1
|
47
|
15 October 2024
|
NEC 3 - Option B - remeasurement CE
|
|
6
|
185
|
30 September 2024
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
71
|
25 September 2024
|