Options and SSCC in NEC 3 TSSC
|
|
1
|
73
|
25 April 2022
|
Nec3 short schedule of cost components
|
|
1
|
112
|
25 April 2022
|
NEC4 - Unfair Main Contractor Assessment of Compensation Event Quotation
|
|
1
|
130
|
25 April 2022
|
NEC ECC: Compensation Event Time Bar Clause 61.3
|
|
3
|
816
|
22 April 2022
|
Justifying submitted CE costs
|
|
2
|
168
|
21 April 2022
|
X1 PAF calculations
|
|
5
|
594
|
19 April 2022
|
Clause 31 Programme
|
|
6
|
142
|
19 April 2022
|
NEC ECC: X1 - Price Adjustment Factor - Proportion Calculation
|
|
8
|
3139
|
19 April 2022
|
NEC4 Option A , SOR increases
|
|
1
|
81
|
11 April 2022
|
Ukraine War - Impact on material prices
|
|
6
|
645
|
11 April 2022
|
NEC3 - Negative CE for removal of methodology restriction
|
|
2
|
107
|
8 April 2022
|
NEC4 Clause 61.4
|
|
4
|
151
|
7 April 2022
|
ECSC: 60.1(3) Client does not provide something
|
|
2
|
127
|
6 April 2022
|
NEC ECC: Under an Option C contract - is cost motor vehicle insurance for equipment be claimed as a defined cost?
|
|
2
|
735
|
5 April 2022
|
NEC3 W1 W2 Dispute Resolution
|
|
1
|
70
|
4 April 2022
|
NEC4 - Retention
|
|
1
|
103
|
1 April 2022
|
NEC 3 Option B SC - Main Contractor Provisions
|
|
1
|
88
|
31 March 2022
|
Dispute Resolution NEC 4 TSC
|
|
3
|
75
|
30 March 2022
|
Use of Subcontractor quotes in CE assessments in NEC4
|
|
2
|
309
|
29 March 2022
|
NEC3 and the Specification for Highway Works
|
|
4
|
125
|
25 March 2022
|
X2 - Red Diesel
|
|
2
|
363
|
25 March 2022
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
256
|
24 March 2022
|
NEC Design Liability
|
|
3
|
87
|
24 March 2022
|
NEC4 Option A with Pricing Schedule Equipment Rates
|
|
3
|
158
|
19 March 2022
|
NEC 4 ECC Option A - Compensation event notified in error
|
|
1
|
111
|
18 March 2022
|
Pricing Plant Costs Under NEC Option A
|
|
3
|
215
|
18 March 2022
|
Option X 18 - Limitation of Liability - Design Resource
|
|
3
|
182
|
18 March 2022
|
NEC3 ECS Option B - Correcting a Defect & cost assocaited with damage to other works
|
|
2
|
196
|
17 March 2022
|
NEC ECSC: Who runs risk of items missed off the Price List?
|
|
2
|
715
|
15 March 2022
|
NEC4 Option C with activity schedule
|
|
4
|
156
|
14 March 2022
|