NEC4 Items Previously Covered by Overhead Percentage (NEC3)
|
|
1
|
84
|
7 August 2024
|
NEC3 Late Access/Acceleration
|
|
1
|
38
|
6 August 2024
|
SOCC Company Car Calculation
|
|
5
|
73
|
6 August 2024
|
NEC4 Option C quotes
|
|
3
|
103
|
6 August 2024
|
Contractors delays & its affect on Key Dates
|
|
3
|
60
|
6 August 2024
|
Can we politely refuse to do a Compensation Event issued by the PM
|
|
4
|
127
|
6 August 2024
|
NEC4 why does a scope reduction not bring the Completion Date forward
|
|
2
|
82
|
6 August 2024
|
People rates for CE assessments
|
|
2
|
54
|
6 August 2024
|
Interest on late payments OHP
|
|
2
|
30
|
5 August 2024
|
NEC 4 Option A CE assessments
|
|
1
|
60
|
25 July 2024
|
Webinar - NEC4 ECC: How to Write Good Scope
|
|
6
|
146
|
23 July 2024
|
Fee on CEs where the BoQ rates are used
|
|
4
|
99
|
23 July 2024
|
Project Manager gives additional time for Completion
|
|
2
|
104
|
21 July 2024
|
Instructing works outside Contractor's original Scope
|
|
8
|
125
|
21 July 2024
|
NEC ECC: Process to implement Clause X1 where no indices have been included?
|
|
2
|
1145
|
19 July 2024
|
NEC3 Option A - Recovery of People cost in circumstances where access is denied by the Employer
|
|
4
|
73
|
16 July 2024
|
Information on NEC Contracts: Payment Assessment for Options C and D
|
|
1
|
236
|
15 July 2024
|
Can Prelim deductions occur under NEC 3 Option B
|
|
1
|
204
|
15 July 2024
|
NEC ECC: Instructing new works when Contractor is already in delay
|
|
4
|
1511
|
15 July 2024
|
PM changes decision about accepting a CE
|
|
1
|
67
|
15 July 2024
|
NEC3 - Clause 61.6 - Contractor Stating Durations as an Assumption
|
|
2
|
81
|
9 July 2024
|
NEC3 - Option C "Title"
|
|
1
|
56
|
4 July 2024
|
NEC4 - Client award to seperate contractor/specialist
|
|
11
|
85
|
2 July 2024
|
NEC3 - PSC - OPTION C - Time Verification Audit
|
|
1
|
70
|
2 July 2024
|
NEC4 - Assessing CEQs
|
|
3
|
164
|
1 July 2024
|
Clause 63.6 - Equipment breakdown lost time
|
|
3
|
103
|
1 July 2024
|
Are negative CE'S still applicable under a Contractors proposal
|
|
1
|
107
|
1 July 2024
|
Client requesting rate breakdown for bespoke item in bill - NEC 3 Short Form
|
|
2
|
100
|
28 June 2024
|
NEC4 Option A PM Assessment
|
|
1
|
131
|
27 June 2024
|
Material Supply Issues
|
|
1
|
480
|
26 June 2024
|