Compensation Events Time Only
|
|
1
|
372
|
10 November 2023
|
S/C not included fee in quotation NEC3 ECS OptA
|
|
2
|
101
|
10 November 2023
|
NEC4: Developing quotation time
|
|
1
|
85
|
9 November 2023
|
Unforeseen cost increases
|
|
0
|
308
|
6 October 2021
|
Negative Compensation Event
|
|
0
|
420
|
28 September 2021
|
NEC4 Short Subcontract Negative CE
|
|
0
|
409
|
8 January 2022
|
What does the term Subsistence cover in terms of Defined Costs under SOCC
|
|
0
|
302
|
13 October 2022
|
NEC3 - Cl.60.1.(8)
|
|
0
|
301
|
11 November 2022
|
NEC3 Option B - Preliminary Item
|
|
0
|
283
|
17 February 2023
|
Cl 63.1 in NEC3 OpA Supply
|
|
0
|
208
|
1 June 2023
|
NEC 4 Option B - Late assessment of Compensation Event and Impact to Interim Payment
|
|
0
|
182
|
27 June 2023
|
Bill items included in priced BoQ, but not included in Works Information
|
|
3
|
130
|
7 November 2023
|
NEC ECC: Which accepted programme is used to measure a CE impact?
|
|
8
|
3060
|
6 November 2023
|
Does a Compensation Event comprise an instruction to carry out additional works?
|
|
3
|
241
|
5 November 2023
|
NEC 3 Opt A - Activity Schedule
|
|
1
|
71
|
3 November 2023
|
Tenderer not able to provide a Performance Bond or Parent Company Guarantee
|
|
1
|
123
|
3 November 2023
|
Large Instructions to Subcontractor
|
|
5
|
504
|
1 November 2023
|
Is failure to comply with a constraint in the Works Information a Defect
|
|
1
|
313
|
1 November 2023
|
NEC4 - The amount due on termination
|
|
0
|
89
|
1 November 2023
|
Multiple CEs under one instruction
|
|
0
|
385
|
9 June 2021
|
Provsional Sum in Option B
|
|
2
|
223
|
28 October 2023
|
NEC4. Limitation of delay damages under X7
|
|
0
|
101
|
25 October 2023
|
Assignment or Novation?
|
|
2
|
115
|
26 October 2023
|
NEC3 TSC - PM changing the Works Information
|
|
0
|
98
|
26 October 2023
|
NEC3 - FastDraft Submission with Quote
|
|
3
|
104
|
26 October 2023
|
Setting share band percentages in NEC3 Option C
|
|
0
|
95
|
25 October 2023
|
NEC4 Subcontract - Which would be the best to use for multiple contracts with same subcontractor?
|
|
8
|
699
|
24 October 2023
|
NEC3 - ECS - Plant Stand Down Costs due to Prevention of Access
|
|
1
|
107
|
23 October 2023
|
Value Engineering - NEC4 Option A
|
|
1
|
117
|
23 October 2023
|
Contract Programme renegotiation due to Contractor Delay
|
|
3
|
118
|
20 October 2023
|