Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
46
|
26 February 2025
|
Treatment of Risk in Compensation Event Quotes
|
|
4
|
170
|
26 February 2025
|
Clause 31 Programme/Access Dates
|
|
1
|
47
|
20 February 2025
|
CE quotations & Programme Impact
|
|
0
|
48
|
19 February 2025
|
NEC 4 PSC Clause 50.3
|
|
2
|
36
|
12 February 2025
|
Company car insurance
|
|
1
|
71
|
10 February 2025
|
NEC4 Option C Defined Costs People
|
|
1
|
156
|
29 January 2025
|
How to assess a "delay" to a Key Date for an instruction to change a Key Date under NEC 4 Cl 14.3
|
|
1
|
84
|
29 January 2025
|
PSC Option A Short Schedule of Cost Components
|
|
0
|
35
|
23 January 2025
|
Liquidated Damages on paperwork
|
|
2
|
111
|
21 January 2025
|
NEC3 Professional Services Contract - Retrospective CE Paperwork
|
|
2
|
51
|
17 January 2025
|
Subcontractor fee % as part of a tender return
|
|
1
|
92
|
14 January 2025
|
NEC3 Short Subcontract - Assessing and Recovering the Cost of Delays
|
|
0
|
58
|
14 January 2025
|
X1 Base Date. First assessment immediately after base date has a Price adjustment
|
|
3
|
98
|
13 January 2025
|
Subcontractor fee percentage as part of tender price
|
|
2
|
56
|
10 January 2025
|
Additional Site Information post contract
|
|
5
|
85
|
8 January 2025
|
Dividing Date for a proposed instruction - NEC4 ECC
|
|
2
|
87
|
2 January 2025
|
NEC4: Engineering and Construction Short Subcontract
|
|
1
|
66
|
25 December 2024
|
X1 application on NEC Supply Contract
|
|
3
|
95
|
19 December 2024
|
NEC Option C - X16 Pain Gain
|
|
6
|
88
|
18 December 2024
|
Option B - Measurement method for PWDD
|
|
3
|
71
|
18 December 2024
|
Late issue of project managers assumptions
|
|
1
|
60
|
18 December 2024
|
NEC4 Core Clause 63.4
|
|
1
|
109
|
13 December 2024
|
NEC4: PM's mistake in Accepted Programme impact CE assessment
|
|
3
|
129
|
9 December 2024
|
NEC3 Option B - Contract Award Revoked
|
|
0
|
56
|
6 December 2024
|
NEC4 PSC Option A - Delays / Omissions from Activity Schedule
|
|
0
|
61
|
4 December 2024
|
NEC Option C with no SCC
|
|
2
|
60
|
4 December 2024
|
NEC 3 - Staff schedule of rates + fee percentage
|
|
3
|
221
|
4 December 2024
|
NEC4 Option C SOCC Sick Pay
|
|
0
|
50
|
4 December 2024
|
NEC4 Option B & Option D
|
|
3
|
146
|
23 November 2024
|