My company is operating as a subcontractor under this form of subcontract. While it has issued numerous quotations for notified compensation events, the Contractor has not disputed that these are compensation events within the period for reply stated in the subcontract data, neither has it responded in accordance with CL62.2 within the time period for replying to subcontractor quotations stsed in the subcontract data - other than to pay some of these/ part pay some of the events “on account” in interim valuation assessments. Are these quotations then treated as accepted under the subcontract (refer CL62.3) and a cannot be disputed by the Contractor now that the periods for reply have elapsed?
1 Like