NEC 4 PSC Clause 50.3

What types of amounts can be classified as “other amounts to be paid to the Consultant” in Clause 50.3 of the PSC?

You don’t say which main option this applies to, although for all main options this would relate to a payment under the contract which is not included in the definition of Price for Service Provided to Date (PSPD) (1st bullet) or expenses (2nd bullet).

Examples of ‘other payments’ include; interest on a late payment, VAT, share amount (main option C), price adjustment for inflation (option X1), payment for meeting a KPI (option X12 or X20).

Thank Andrew. The main option for the contract is Option C.