NEC4 Option B & Option D

Dear All,

I have a project using NEC4 option B (BOQ was prepared by the Client) – I am unsure if my reading of the relevant clauses relating to errors in the BOQ are correct, can someone clarify if I am correct?

Clause 60.4 – a difference in quantity when the work is completed is only a compensation events if the three bullets’ points are meet – does the PM prove there has been a change in the defined cost i.e. reduced or alternatively the contractor has to prove the defined cost per unit has increased. So, a change in QTY alone is not a CE?

60.5 – A difference between quantities that cause a delay in completion – e.g. a quantity increases leads to a delay in completion – this is paid as a CE.

60.6 – Any departure from the agreed method of measurement or ambiguity or inconsistency – this is paid as a CE

How are undermeasures or over measures dealt with – is it under 60.6 as an ambiguity or inconsistency with the scope/drawings/project information. Clause 11.2(30) says PWDD is “the measure of the work which the contractor has completed for each item in the bill of quantities multiplied by the rate – am I correct in saying outside of the above clauses the contractor gets paid for the work done e.g. 100/m2 of tiles are in the tendered BOQ but 120/m2 was actually done – the contractor applies for the 120/m2 and the revised quantity multiplied by the tendered rate is the PWDD? -SO, outside of the terms of the above clauses it is not a CE but a remeasure? Or is it dealt with under 60.6?

I assume a reduction in quantities is also a remeasure and treated the same way?

1 Like

The short answer is yes.
Under an Option B the quantity risk sits with the Employer, the BoQ is re-measurable based on the initial WI/Scope but various additional CEs are available to cover errors on the BoQ.

Thank you for your responce - how are differences in quantities dealt with that do not fall under the above listed clauses - is there an additional clause that deals with “straghtforward” remeasures - e.g. 100/m2 of tiles not 120/m2 tiles? - is this included in the PWDD

The PWDD under an Option B, for BoQ items, is the total of the qty of work completed for each BoQ item multiplied by the rate (See NEC3 clause 11.2(28))