Our project is a design and built contract and the Contractor is responsible to design a drainage pipe from one location to another. The Contractor designed it along a road which would require diversion of other utilities by other utility owner (the Others). While liaising with the Others, the Contractor included this plan in their programme but input a wrong date for Others to complete their work in the programme (e.g. Q4 2024), despite Others had already notified both the Contractor and the Project Manager that they would require 2 years time to complete (Q4 2026). The Project Manager overlooked and accepted it, making it the latest Accepted Programme. Subsequently, the Contractor issued a notification of CE claiming for 60.1(5) the Others not work according to the Accepted Programme. The Project Manager stated the following two reason not to accept the NCE:
- 61.4 it is arise by the Contractor’s fault of putting a wrong date, and
- The Contractor could have other alternatives to complete the work (constructing it along other road)
In view that the Project Manager already accepted it, is the Contractor entitle for CE?
Thank you.