Hi,
Employer issued Contract Award and subsequently revoked 3 months later as lack of funding. No cost incurred by Contractor but reduction in programme of 8 weeks, i.e planned completion now 8 weeks left. Is the Contractor able to claim for the weekly site set up costs x 8 weeks?
The Contract Award was specific to this site as each site is awarded individually. The Contractor is being paid for materials procured based on the Contract Award but no site work has taken place at all.