|
NEC 4 - Option C (X11 - Termination)
|
|
5
|
635
|
4 September 2025
|
|
NEC3 Option B - Re-measure of prelims
|
|
3
|
220
|
3 September 2025
|
|
NEC4 Option A - Subcontract fee % in Compensation Events
|
|
6
|
724
|
3 September 2025
|
|
NEC3 Option C: Notice of Failure to Respond
|
|
3
|
108
|
3 September 2025
|
|
NEC - the Site and the boundaries of the site
|
|
4
|
241
|
2 September 2025
|
|
60.4 - A difference between the final total quantity of work done and the quantity stated for an item in the Bill of Quantities
|
|
5
|
374
|
2 September 2025
|
|
Retention Bond Equivalent to Cash Retention
|
|
2
|
85
|
29 August 2025
|
|
NCE3 Opt A - Sectional Completion Dates
|
|
2
|
91
|
13 August 2025
|
|
Prelims costs due to Extension of Time - Option A
|
|
2
|
194
|
13 August 2025
|
|
Use of CECA Rate
|
|
2
|
265
|
11 August 2025
|
|
NEC4 ECC PM Exam - Failed Twice
|
|
1
|
230
|
8 August 2025
|
|
NEC ECC: Cancelling Compensation Events
|
|
3
|
3235
|
5 August 2025
|
|
NEC4 Option B - Blank Quantities in the BOQ
|
|
3
|
106
|
29 July 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
256
|
16 July 2025
|
|
Two interfacing Contracts, one in Delay, both with the same Contractor
|
|
1
|
65
|
15 July 2025
|
|
NEC4 - Schedule of Cost Components - Subcontract Cost
|
|
0
|
88
|
11 July 2025
|
|
NEC 3 CE Assessemnt
|
|
3
|
135
|
11 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
157
|
10 July 2025
|
|
Are legal fees allowable?
|
|
2
|
136
|
10 July 2025
|
|
Disallowed Cost
|
|
2
|
190
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
100
|
10 July 2025
|
|
Retrospective instructions
|
|
1
|
82
|
10 July 2025
|
|
NEC4 which programme dates?
|
|
5
|
197
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
99
|
10 July 2025
|
|
NEC4 - Working Areas
|
|
1
|
237
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
155
|
10 July 2025
|
|
NEC4 Option C - Payment for Equipment
|
|
5
|
293
|
1 July 2025
|
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
173
|
22 June 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
150
|
22 June 2025
|
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
3
|
221
|
9 June 2025
|