|
NEC4 Option C - Payment for Equipment
|
|
5
|
186
|
1 July 2025
|
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
114
|
22 June 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
97
|
22 June 2025
|
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
3
|
162
|
9 June 2025
|
|
NEC4 Option A - Priced with a BoQ
|
|
2
|
171
|
9 June 2025
|
|
NEC4 Opt C - X22 - Inflation of Subcontractor Prices
|
|
1
|
68
|
6 June 2025
|
|
NEC4 PSC Option E - can I disallow time booked in a payment application
|
|
1
|
78
|
6 June 2025
|
|
NEC4 Clause 65 Proposed Instructions
|
|
1
|
112
|
29 May 2025
|
|
NEC 4 Option B - Cl60.4
|
|
2
|
102
|
23 May 2025
|
|
NEC3 Subcontractor non-compliance with licence
|
|
2
|
41
|
20 May 2025
|
|
Quotation Assessments Under X2
|
|
1
|
150
|
15 May 2025
|
|
NEC4 SSCC charges on downtime
|
|
1
|
55
|
14 May 2025
|
|
PM Instructing Additional Works After Defects Date
|
|
2
|
119
|
9 May 2025
|
|
Compensation Events and Delay
|
|
1
|
100
|
9 May 2025
|
|
NEC4 Option A Compensation Event
|
|
3
|
141
|
2 May 2025
|
|
CE quotations & Programme Impact
|
|
1
|
115
|
2 May 2025
|
|
Project timelines/durations of Others, not defined at Tender stage
|
|
3
|
68
|
29 April 2025
|
|
Access to the site not granted due to weather conditions
|
|
1
|
60
|
28 April 2025
|
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
97
|
24 April 2025
|
|
NEC 4 - Equipment
|
|
2
|
89
|
22 April 2025
|
|
Nec3 compensation for information delay
|
|
2
|
73
|
22 April 2025
|
|
Cost of Correction of Defects in a NEC 3 Option F
|
|
0
|
45
|
16 April 2025
|
|
NEC3 - Correcting a PM Assumption
|
|
2
|
127
|
13 April 2025
|
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
552
|
10 April 2025
|
|
Defect in an NEC Option A subcontractors works
|
|
3
|
94
|
9 April 2025
|
|
NEC3 Lack of Access CE
|
|
5
|
193
|
9 April 2025
|
|
NEC4 TSC contracts
|
|
2
|
55
|
2 April 2025
|
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
113
|
31 March 2025
|
|
Percentage for adjustment for Equipment in the published list
|
|
2
|
116
|
27 March 2025
|
|
How to certify payment when an advanced payment bond is required
|
|
2
|
67
|
27 March 2025
|