|
NEC4 Option B - Blank Quantities in the BOQ
|
|
3
|
80
|
29 July 2025
|
|
NEC4 - Additional Compensation Events
|
|
3
|
212
|
16 July 2025
|
|
Two interfacing Contracts, one in Delay, both with the same Contractor
|
|
1
|
47
|
15 July 2025
|
|
NEC4 - Schedule of Cost Components - Subcontract Cost
|
|
0
|
76
|
11 July 2025
|
|
NEC 3 CE Assessemnt
|
|
3
|
122
|
11 July 2025
|
|
NEC 4 Subcontract - CE Assessments
|
|
1
|
129
|
10 July 2025
|
|
Are legal fees allowable?
|
|
2
|
94
|
10 July 2025
|
|
Disallowed Cost
|
|
2
|
152
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
67
|
10 July 2025
|
|
Retrospective instructions
|
|
1
|
56
|
10 July 2025
|
|
NEC4 which programme dates?
|
|
5
|
143
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
72
|
10 July 2025
|
|
NEC4 - Working Areas
|
|
1
|
177
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
124
|
10 July 2025
|
|
NEC4 Option C - Payment for Equipment
|
|
5
|
228
|
1 July 2025
|
|
Subcontractor charging for plant/ labour without increase to Defined Cost
|
|
4
|
123
|
22 June 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
114
|
22 June 2025
|
|
NEC3 ECC Subcontract - De-Scoping the Works Information (costs in relation to)
|
|
3
|
177
|
9 June 2025
|
|
NEC4 Option A - Priced with a BoQ
|
|
2
|
210
|
9 June 2025
|
|
NEC4 Opt C - X22 - Inflation of Subcontractor Prices
|
|
1
|
84
|
6 June 2025
|
|
NEC4 PSC Option E - can I disallow time booked in a payment application
|
|
1
|
91
|
6 June 2025
|
|
NEC4 Clause 65 Proposed Instructions
|
|
1
|
152
|
29 May 2025
|
|
NEC 4 Option B - Cl60.4
|
|
2
|
124
|
23 May 2025
|
|
NEC3 Subcontractor non-compliance with licence
|
|
2
|
43
|
20 May 2025
|
|
Quotation Assessments Under X2
|
|
1
|
158
|
15 May 2025
|
|
NEC4 SSCC charges on downtime
|
|
1
|
63
|
14 May 2025
|
|
PM Instructing Additional Works After Defects Date
|
|
2
|
148
|
9 May 2025
|
|
Compensation Events and Delay
|
|
1
|
106
|
9 May 2025
|
|
NEC4 Option A Compensation Event
|
|
3
|
148
|
2 May 2025
|
|
CE quotations & Programme Impact
|
|
1
|
123
|
2 May 2025
|