NEC3 W1 W2 Dispute Resolution
|
|
1
|
91
|
4 April 2022
|
NEC4 - Retention
|
|
1
|
125
|
1 April 2022
|
NEC 3 Option B SC - Main Contractor Provisions
|
|
1
|
109
|
31 March 2022
|
Dispute Resolution NEC 4 TSC
|
|
3
|
96
|
30 March 2022
|
Use of Subcontractor quotes in CE assessments in NEC4
|
|
2
|
335
|
29 March 2022
|
NEC3 and the Specification for Highway Works
|
|
4
|
137
|
25 March 2022
|
X2 - Red Diesel
|
|
2
|
442
|
25 March 2022
|
NEC4 Employers Liability in SoCC under People
|
|
2
|
299
|
24 March 2022
|
NEC Design Liability
|
|
3
|
105
|
24 March 2022
|
NEC4 Option A with Pricing Schedule Equipment Rates
|
|
3
|
193
|
19 March 2022
|
NEC 4 ECC Option A - Compensation event notified in error
|
|
1
|
153
|
18 March 2022
|
Pricing Plant Costs Under NEC Option A
|
|
3
|
265
|
18 March 2022
|
Option X 18 - Limitation of Liability - Design Resource
|
|
3
|
233
|
18 March 2022
|
NEC3 ECS Option B - Correcting a Defect & cost assocaited with damage to other works
|
|
2
|
230
|
17 March 2022
|
NEC ECSC: Who runs risk of items missed off the Price List?
|
|
2
|
774
|
15 March 2022
|
NEC4 Option C with activity schedule
|
|
4
|
232
|
14 March 2022
|
Clause 61.3 Time Bar - Awareness of Event or Awareness of Compensation Event?
|
|
4
|
224
|
11 March 2022
|
Sectional Completion and Delay Damages
|
|
2
|
199
|
11 March 2022
|
NEC4 Option C - CE payments
|
|
3
|
227
|
9 March 2022
|
Reviewing Main Contracts
|
|
2
|
178
|
9 March 2022
|
NEC4 - Project Manager's Instructions after Completion Date
|
|
3
|
244
|
8 March 2022
|
ECC3 Option A - Defined cost CEs
|
|
2
|
332
|
7 March 2022
|
Professional Service Subcontract - Why no 'Short' version?
|
|
4
|
282
|
7 March 2022
|
NEC3 - Option Y (UK) 2 - Payment Notice
|
|
1
|
175
|
6 March 2022
|
CECA rates contract data part 2
|
|
1
|
236
|
6 March 2022
|
Labour Only Sub-Contractors
|
|
3
|
171
|
4 March 2022
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
185
|
28 February 2022
|
NEC3 Professional Services Contract - Provision of Resource
|
|
4
|
174
|
28 February 2022
|
X7 daily damages
|
|
1
|
132
|
21 February 2022
|
Inflation in Contracts that are in delay without X1
|
|
1
|
267
|
16 February 2022
|