Is the Contractor liable for a matter if it is notified after the end of the liability date?
|
|
1
|
713
|
14 November 2012
|
The Employer has terminated because the Contractor has had a receiver appointed over the whole its assets (R9). What is the amount due?
|
|
1
|
712
|
12 October 2012
|
NEC ECC: Contractor failing to provide as detailed in the WI
|
|
2
|
581
|
26 July 2019
|
If a payment is conditional on the completion of a Supervisor’s test which has not been carried out, when is the payment due?
|
|
1
|
711
|
14 October 2012
|
What happens if a compensation event reduces the total Defined Cost?
|
|
1
|
711
|
9 October 2012
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
729
|
22 November 2023
|
Can the Project Manager delegate his actions?
|
|
1
|
710
|
12 October 2012
|
Can the Project Manager extend the period for reply?
|
|
1
|
710
|
12 October 2012
|
The Contractor has terminated because the Project Manager has instructed him to stop work due to a default by the Employer (R19). What is the termination procedure?
|
|
1
|
710
|
12 October 2012
|
Can either Party terminate if the Parties have been released under the law from further performance of the whole of the contract?
|
|
1
|
710
|
12 October 2012
|
NEC ECC: Weekend working to mitigate delay
|
|
2
|
1029
|
21 November 2017
|
NEC ECC: Amendment to secondary clause wording such as X22
|
|
3
|
891
|
27 March 2020
|
The Contractor has terminated because he has been released under the law from performance of the contract (R17). What is the amount due?
|
|
1
|
708
|
12 October 2012
|
Contractors sometimes demand 'prelims' on the extension of time. How are these calculated?
|
|
1
|
1258
|
5 February 2013
|
NEC ECC: Equipment Minimum Hire Period and CECA
|
|
5
|
727
|
17 March 2020
|
NEC ECC: Entitlement to a CE if the duration of works undertaken by Others is unspecified in the Works Information
|
|
1
|
707
|
2 February 2018
|
What can the Employer do if the Contractor produces substandard work?
|
|
1
|
707
|
16 October 2012
|
NEC PSC: Option E - Contractually, what is the best way(s) to control programme and cost for design works?
|
|
1
|
706
|
6 June 2019
|
NEC ECC: Contractor has not acted on a PM's instruction does this effect the value of the CE?
|
|
1
|
706
|
31 October 2017
|
What are the Working Areas?
|
|
1
|
706
|
12 October 2012
|
NEC ECC: Option B - Can the contractor ask to re-price the BoQ
|
|
1
|
1254
|
4 May 2020
|
NEC ECC: Take over and Insurances
|
|
1
|
1254
|
23 July 2018
|
What sort of Defect would need to be corrected urgently?
|
|
1
|
705
|
15 October 2012
|
The Supervisor may instruct the Contractor to search for a Defect until when?
|
|
1
|
705
|
14 October 2012
|
The Employer or Others have not worked within the conditions stated in the Works Information. Is this a compensation event?
|
|
1
|
705
|
10 October 2012
|
NEC3 - Clause 61.6 - Contractor Stating Durations as an Assumption
|
|
2
|
183
|
9 July 2024
|
Letter of intent is it worth the paper its written on? should a contractor begin work on a LOI alone
|
|
0
|
315
|
3 March 2023
|
NEC3 ECC: Employer works elsewhere affecting the project - is this a compensation event?
|
|
1
|
704
|
3 July 2016
|
Does the Contractor do any further work after a termination certificate has been issued?
|
|
1
|
704
|
11 October 2012
|
For what reasons may the Employer terminate the contract?
|
|
1
|
704
|
11 October 2012
|
When does the Project Manager submit policies and certificates for insurances provided by the Employer to the Contractor?
|
|
1
|
704
|
11 October 2012
|
What does Defined Cost include?
|
|
1
|
704
|
10 October 2012
|
X5 sectional completion dates vs contract date
|
|
2
|
1022
|
25 May 2022
|
NEC 3 Option A disputed defects
|
|
1
|
703
|
27 November 2020
|
Is float between planned Completion and the Completion Date available to either party?
|
|
2
|
1020
|
14 January 2014
|
Release Notes upto 2023-05-30 Academy
|
|
0
|
314
|
30 May 2023
|
NEC ECS: Compensation Events - Recovery of Material Costs
|
|
3
|
497
|
3 May 2018
|
NEC ECC: Rates used to Value a CE quotation under Option A
|
|
1
|
1247
|
14 January 2020
|
JCT Contracts: Late Payments
|
|
2
|
1018
|
8 January 2019
|
NEC ECS: Option B - Change of Methodology by Subcontractor
|
|
1
|
701
|
12 November 2018
|
NEC3 Option A - No breakdown of an activity in the Activity Schedule
|
|
3
|
881
|
19 July 2022
|
Are Prices reduced if a compensation event reduces the total Defined Cost and the event is a correction of an assumption for assessing an earlier compensation event?
|
|
1
|
700
|
15 October 2012
|
Who checks whether the Contractor’s work has reached the specified quality standards?
|
|
1
|
700
|
14 October 2012
|
What is the Fee?
|
|
1
|
700
|
12 October 2012
|
NEC ECC: 31.3 – Programme Acceptance - level of detail
|
|
1
|
699
|
23 July 2019
|
NEC ECC: Can I retract a programme under option A
|
|
1
|
699
|
26 August 2017
|
If a compensation event includes a change to the Works Information provided by the Contractor, how is the event assessed?
|
|
1
|
699
|
9 October 2012
|
NEC ECC: Is it a Compensation Event for PM instruction issued under NEC3 Clause 17.1?
|
|
4
|
786
|
27 July 2020
|
What is the amount retained?
|
|
1
|
698
|
16 October 2012
|
How long does the Project Manager have to accept or withhold acceptance of the Contractor's design?
|
|
1
|
698
|
12 October 2012
|