About the JCT Contracts category
|
|
0
|
487
|
27 February 2020
|
JCT Fluctuations
|
|
3
|
31
|
20 September 2023
|
JCT D&B16 SC Deferment of possession
|
|
2
|
69
|
29 August 2023
|
JCT Design And Build - Lump Sum - Client Omissions
|
|
1
|
116
|
12 July 2023
|
JCT Sub-Contract SBCSub/A - Subcontractor Delays
|
|
1
|
87
|
27 June 2023
|
Webinar - Understanding Key Documents of a JCT Design and Build Contract
|
|
4
|
324
|
19 June 2023
|
Webinar - Understanding What Sums Properly Due JCT Design & Build Contract Part 2 - Loss and Expense Claims
|
|
5
|
358
|
7 June 2023
|
Release of retention monies
|
|
1
|
156
|
6 June 2023
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
125
|
22 May 2023
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
10
|
1068
|
2 May 2023
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
367
|
13 April 2023
|
JCT D&B 2016 Prolongation Prelims
|
|
1
|
208
|
10 February 2023
|
Contract execution - Are wet signatures a legal requirement?
|
|
1
|
227
|
18 January 2023
|
JCT Final Account
|
|
2
|
695
|
16 January 2023
|
Construction Programmes
|
|
3
|
247
|
15 January 2023
|
Webinar - Control of the Works by Employer’s Agent, Site Manager, Contractor and Employer under JCT D&B Contract
|
|
2
|
925
|
23 December 2022
|
Webinar - Control of the Quality under JCT D&B Contract
|
|
4
|
444
|
23 December 2022
|
PQS approving a variation and instructing to proceed - but not agreeing the cost
|
|
1
|
300
|
1 December 2022
|
Extension of Time - L&E Claim
|
|
0
|
261
|
16 November 2022
|
Valuing Sub-Subcontract Costs
|
|
0
|
252
|
3 November 2022
|
JCT D&B 2016 - Novated Consultant Disagreement
|
|
1
|
244
|
2 November 2022
|
JCT contract used for a demolition project
|
|
3
|
596
|
18 October 2022
|
JCT2016DB - Contractors Design Documents
|
|
2
|
365
|
10 October 2022
|
Re-Sequencing/Speeding up to minimise delay
|
|
0
|
277
|
30 August 2022
|
JCT Design and Build
|
|
0
|
285
|
3 August 2022
|
JCT D&B 2016 and sub-contractors
|
|
1
|
436
|
28 July 2022
|
JCT DB 2016 Corresponding Subcontract
|
|
1
|
303
|
27 July 2022
|
Delayed Access JCT SBC/Q 2016
|
|
0
|
374
|
7 July 2022
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
8
|
468
|
24 June 2022
|
JCT Major Projects - discrepancy in Period for Completion
|
|
1
|
274
|
22 June 2022
|