About the JCT Contracts category
|
|
0
|
614
|
27 February 2020
|
Jct subcontract
|
|
0
|
9
|
2 October 2024
|
Webinar - Control of the Quality under JCT D&B Contract
|
|
3
|
635
|
30 August 2024
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
8
|
1021
|
24 June 2022
|
JCT SBC Valuing Omissions
|
|
1
|
151
|
4 July 2024
|
Weather, ground conditions and recovery of cost - JCT SBC/XQ 2016
|
|
1
|
154
|
4 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
896
|
16 February 2024
|
Is Retention held on all Loss & Expense; cl 4.14.2.3 JCT SBC 2016
|
|
1
|
147
|
21 June 2024
|
Bespoke Contract
|
|
1
|
212
|
10 June 2024
|
Provisional Sum - JCT DB 2016 - allowance also in CSA
|
|
2
|
204
|
7 June 2024
|
JCT Unamended Contract Query
|
|
0
|
132
|
17 May 2024
|
JCT (ICD) 2016 Inconsistency of documents - Rectification Period
|
|
1
|
453
|
15 April 2024
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1778
|
6 March 2024
|
Webinar - Contractor Obligations under JCT D&B Contract for Subcontracting and H&S
|
|
2
|
330
|
16 February 2024
|
Webinar - Understanding Contracts Documents and how they Work Together
|
|
6
|
736
|
16 February 2024
|
Webinar - Overview of the JCT Design and Build Contract
|
|
4
|
590
|
16 January 2024
|
JCT D&B SFC Time at large
|
|
1
|
404
|
28 November 2023
|
JCT ICD16 - Defect found after rectification period, Contractor unwilling to correct
|
|
2
|
241
|
24 November 2023
|
JCT retention release but more work keeps on being instructed
|
|
2
|
298
|
23 November 2023
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
714
|
22 November 2023
|
Reckoning Days and Pay Less Notices
|
|
2
|
761
|
20 November 2023
|
Design manufacturer and supply on a JCT
|
|
0
|
295
|
3 December 2022
|
Payment of Pro-Forma Invoices
|
|
0
|
346
|
7 March 2023
|
JCT ICSub/A 2016 Intermediate Sub-Contract Article 3A; Sub-Contract Sum & Final Sub-Contract Sum
|
|
4
|
351
|
18 October 2023
|
Webinar - Control of the Works by Employer’s Agent, Site Manager, Contractor and Employer under JCT D&B Contract
|
|
3
|
1111
|
4 October 2023
|
JCT Fluctuations
|
|
3
|
251
|
20 September 2023
|
JCT D&B16 SC Deferment of possession
|
|
2
|
395
|
29 August 2023
|
JCT Design And Build - Lump Sum - Client Omissions
|
|
1
|
554
|
12 July 2023
|
JCT Sub-Contract SBCSub/A - Subcontractor Delays
|
|
1
|
282
|
27 June 2023
|
Webinar - Understanding Key Documents of a JCT Design and Build Contract
|
|
4
|
491
|
19 June 2023
|