About the JCT Contracts category
|
|
0
|
617
|
27 February 2020
|
JCT D&B 2016 with BoQ - Quantities change risk on time
|
|
0
|
18
|
16 January 2025
|
Preliminaries Allocation in JCT Contract
|
|
0
|
20
|
19 November 2024
|
Payment notices
|
|
4
|
56
|
4 November 2024
|
Webinar - Overview of the JCT Design and Build Contract
|
|
5
|
612
|
30 October 2024
|
Time Bar for EWN on JCT DB contact
|
|
0
|
28
|
11 October 2024
|
Jct subcontract
|
|
0
|
25
|
2 October 2024
|
Webinar - Control of the Quality under JCT D&B Contract
|
|
3
|
639
|
30 August 2024
|
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
|
|
8
|
1036
|
24 June 2022
|
JCT SBC Valuing Omissions
|
|
1
|
160
|
4 July 2024
|
Weather, ground conditions and recovery of cost - JCT SBC/XQ 2016
|
|
1
|
155
|
4 July 2024
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
910
|
16 February 2024
|
Is Retention held on all Loss & Expense; cl 4.14.2.3 JCT SBC 2016
|
|
1
|
200
|
21 June 2024
|
Bespoke Contract
|
|
1
|
212
|
10 June 2024
|
Provisional Sum - JCT DB 2016 - allowance also in CSA
|
|
2
|
228
|
7 June 2024
|
JCT Unamended Contract Query
|
|
0
|
134
|
17 May 2024
|
JCT (ICD) 2016 Inconsistency of documents - Rectification Period
|
|
1
|
457
|
15 April 2024
|
Webinar - Consequences of failing to complete the works before the completion date and LADs under JCT D&B Contract
|
|
11
|
1781
|
6 March 2024
|
Webinar - Contractor Obligations under JCT D&B Contract for Subcontracting and H&S
|
|
2
|
330
|
16 February 2024
|
Webinar - Understanding Contracts Documents and how they Work Together
|
|
6
|
758
|
16 February 2024
|
JCT D&B SFC Time at large
|
|
1
|
412
|
28 November 2023
|
JCT ICD16 - Defect found after rectification period, Contractor unwilling to correct
|
|
2
|
255
|
24 November 2023
|
JCT retention release but more work keeps on being instructed
|
|
2
|
339
|
23 November 2023
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
719
|
22 November 2023
|
Reckoning Days and Pay Less Notices
|
|
2
|
892
|
20 November 2023
|
Design manufacturer and supply on a JCT
|
|
0
|
300
|
3 December 2022
|
Payment of Pro-Forma Invoices
|
|
0
|
352
|
7 March 2023
|
JCT ICSub/A 2016 Intermediate Sub-Contract Article 3A; Sub-Contract Sum & Final Sub-Contract Sum
|
|
4
|
365
|
18 October 2023
|
Webinar - Control of the Works by Employer’s Agent, Site Manager, Contractor and Employer under JCT D&B Contract
|
|
3
|
1111
|
4 October 2023
|
JCT Fluctuations
|
|
3
|
253
|
20 September 2023
|