|
About the General category
|
|
0
|
477
|
27 February 2020
|
|
JCT main contract
|
|
2
|
20
|
3 May 2026
|
|
JCT Sub-Contract
|
|
1
|
27
|
29 April 2026
|
|
Damage and payments
|
|
0
|
33
|
2 July 2025
|
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
9
|
977
|
16 February 2024
|
|
JCT (ICD) 2016 Inconsistency of documents - Rectification Period
|
|
1
|
481
|
15 April 2024
|
|
Webinar - Contractor Obligations under JCT D&B Contract for Subcontracting and H&S
|
|
2
|
341
|
16 February 2024
|
|
JCT D&B SFC Time at large
|
|
1
|
426
|
28 November 2023
|
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
5
|
761
|
22 November 2023
|
|
Design manufacturer and supply on a JCT
|
|
0
|
310
|
3 December 2022
|
|
Release of retention monies
|
|
1
|
431
|
6 June 2023
|
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
364
|
22 May 2023
|
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
574
|
13 April 2023
|
|
JCT Final Account
|
|
2
|
1149
|
16 January 2023
|
|
Valuing Sub-Subcontract Costs
|
|
0
|
416
|
3 November 2022
|
|
JCT D&B 2016 Relevant Matter Clauses
|
|
4
|
1822
|
28 October 2022
|
|
JCT contract used for a demolition project
|
|
3
|
1665
|
18 October 2022
|
|
JCT D&B 2016 and sub-contractors
|
|
1
|
1150
|
28 July 2022
|
|
Changes in Legislation
|
|
3
|
1102
|
19 May 2022
|
|
Webinar - Default, Repudiation, Insolvency and Termination Under JCT D&B
|
|
5
|
554
|
7 April 2022
|
|
JCT Sub-Contract Particulars
|
|
1
|
575
|
7 November 2021
|
|
Jct db 2016 eot
|
|
0
|
449
|
27 October 2021
|
|
Contractor orders, increased cost and client position
|
|
3
|
427
|
18 August 2021
|
|
JCT: Acceleration & Pre-Agreed Adjustment
|
|
0
|
979
|
17 June 2021
|
|
JCT 5 day payment issue
|
|
2
|
1205
|
22 April 2021
|
|
NEC3 PSC revised programme rejection
|
|
1
|
618
|
6 April 2021
|
|
JCT Design & Build Contract 2016 – Supply Of Documents
|
|
1
|
643
|
16 March 2021
|
|
JCT D&B 2016 Cost Variation
|
|
2
|
695
|
6 January 2021
|
|
JCT D&B16: What rights are available during defects liability period and Contractors obligation after termination?
|
|
1
|
1146
|
15 July 2020
|
|
JCT: What is the difference between Force Majeure & Excepted Risks JCT 2016 D&B
|
|
4
|
2185
|
15 July 2020
|