About the General category
|
|
0
|
358
|
27 February 2020
|
Release of retention monies
|
|
1
|
156
|
6 June 2023
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
125
|
22 May 2023
|
Webinar - An Introduction to the Extensions of Time Provisions under JCT D&B Contract
|
|
10
|
367
|
13 April 2023
|
JCT Final Account
|
|
2
|
695
|
16 January 2023
|
Valuing Sub-Subcontract Costs
|
|
0
|
252
|
3 November 2022
|
JCT contract used for a demolition project
|
|
3
|
596
|
18 October 2022
|
JCT D&B 2016 and sub-contractors
|
|
1
|
436
|
28 July 2022
|
Changes in Legislation
|
|
3
|
506
|
19 May 2022
|
Webinar - Default, Repudiation, Insolvency and Termination Under JCT D&B
|
|
5
|
411
|
7 April 2022
|
Webinar - Overview of Payment Provisions under JCT D&B Contract - Listed items and deductions
|
|
3
|
445
|
24 March 2022
|
JCT Sub-Contract Particulars
|
|
1
|
345
|
7 November 2021
|
Jct db 2016 eot
|
|
0
|
303
|
27 October 2021
|
Contractor orders, increased cost and client position
|
|
3
|
321
|
18 August 2021
|
Webinar - Contractor Obligations under JCT D&B Contract - Design and Quality Standards
|
|
6
|
469
|
23 June 2021
|
JCT: Acceleration & Pre-Agreed Adjustment
|
|
0
|
639
|
17 June 2021
|
JCT 5 day payment issue
|
|
2
|
652
|
22 April 2021
|
NEC3 PSC revised programme rejection
|
|
1
|
421
|
6 April 2021
|
JCT Design & Build Contract 2016 – Supply Of Documents
|
|
1
|
496
|
16 March 2021
|
JCT D&B 2016 Cost Variation
|
|
2
|
541
|
6 January 2021
|
JCT D&B16: What rights are available during defects liability period and Contractors obligation after termination?
|
|
1
|
801
|
15 July 2020
|
JCT: What is the difference between Force Majeure & Excepted Risks JCT 2016 D&B
|
|
4
|
1419
|
15 July 2020
|
JCT: Withheld RFI cause for delay
|
|
1
|
632
|
14 July 2020
|
JCT D&B16: The suspension of work without reasonable cause..
|
|
2
|
553
|
10 July 2020
|
JCT D&B16: Does the Contractor's obligation to insure the works cease when a new Contractor is appointed?
|
|
2
|
482
|
10 July 2020
|
JCT D&B16: Is it feasible to amend the Contract terms?
|
|
2
|
440
|
8 July 2020
|
JCT DB16: In the event of insolvency, can a Employer damage the Contractor's property?
|
|
1
|
417
|
8 July 2020
|
JCT D&B Contract EOT Query
|
|
1
|
463
|
6 July 2020
|
JCT: Can i refuse to action a variation instruction on the grounds of incomplete information being provided therein
|
|
1
|
408
|
23 June 2020
|
JCT: Conflict in the measurement of variations
|
|
4
|
566
|
22 June 2020
|