How long does the Project Manager have to accept or withhold acceptance of the Contractor's design?

On receiving the particulars of the Contractor’s design, how long does the Project Manager have to accept or withhold acceptance?

1 Like

The Project Manager replies to the Contractor’s submission within the period for reply detailed in the Contract Data (see Clause 13.3).