What can the Employer do if the Contractor produces substandard work?
1 Like
The Employer can:
Insist that the Contractor corrects the Defect to provide the quality specified in the Works Information (Clause 43.1)
Recover the cost of having it corrected by other people if the Contractor fails to correct the Defect within the defect correction period (Clause 45.1),
Accept the Defect and also a quotation from the Contractor for reduced Prices, an earlier Completion Date, or both, in return for a change to the Works Information (Clause 44).