Can the Project Manager delegate his actions?

Can the Project Manager delegate his actions?

1 Like

Yes. Clause 14.2 allows the Project Manager to delegate any of his actions after he has notified the Contractor. As such, references to the Project Manager in the contract can also extend to his delegate. The Project Manager can also cancel any such delegation.