NEC3 ECC: Option B applying subcontract fee percentage
|
|
1
|
784
|
18 April 2016
|
NEC3 ECC Option D - Costs due to Correction of Defects
|
|
1
|
784
|
11 February 2016
|
NEC3 ECC: Does the Contractor have to use the Bill of Quantities under Option B when compiling a quotation, if applicable?
|
|
1
|
784
|
20 October 2015
|
The Contractor has terminated because the Employer has passed a resolution for winding-up (R7). What is the amount due?
|
|
1
|
784
|
12 October 2012
|
Under NEC Option B how to assess and quantify compensation event claims with potential underlying weather cause
|
|
5
|
804
|
22 April 2021
|
NEC3 ECC: Can you claim for delay costs in a CE if you are paid on Actual costs?
|
|
1
|
783
|
9 June 2016
|
If the Employer wishes to terminate for a reason other than those stated in the termination table, what must he do?
|
|
1
|
783
|
11 October 2012
|
NEC ECC: Accepted programme
|
|
3
|
984
|
27 March 2020
|
NEC ECC: Can the Supervisor notify multiple Defects in one communication?
|
|
2
|
638
|
5 April 2018
|
How high should the guardrails on a scaffold be?
|
|
1
|
1389
|
25 January 2013
|
NEC3 Option C Insurance Premium Cost Recovery
|
|
2
|
1134
|
19 May 2021
|
Can you explain to me what is meant by the term Acceptance Criteria in Prince2?
|
|
1
|
781
|
27 March 2015
|
NEC3 ECC: Do you price prelims at tender to planned Completion or Completion Date?
|
|
1
|
781
|
23 February 2015
|
Can Key Dates be changed?
|
|
1
|
781
|
12 October 2012
|
NEC ECSC: Indemnities Cl.81.2
|
|
3
|
982
|
5 December 2019
|
Exam Question NEC 4
|
|
1
|
1388
|
13 October 2022
|
NEC3 ECC option D - Compensation Events
|
|
1
|
780
|
14 October 2015
|
NEC3 ECC: Compensation events and associated insurance
|
|
1
|
780
|
31 March 2015
|
What is Site Information?
|
|
1
|
780
|
12 October 2012
|
The Contractor has terminated because the Employer has not paid an amount certified (R16). What is the termination procedure?
|
|
1
|
781
|
12 October 2012
|
The Contractor included subcontractor's claim in their Quotation for a CE
|
|
4
|
877
|
26 September 2022
|
The Employer has not provided something which he is to provide by the date for providing it shown on the Accepted Programme. Is this a compensation event?
|
|
1
|
779
|
10 October 2012
|
NEC ECS: Assessing prolongation ECC
|
|
1
|
1385
|
15 August 2018
|
Procurement: What are the benefits of using a VEAT?
|
|
1
|
1384
|
2 August 2013
|
JCTSBC2016 - Contractor's Design (Recitals 11 & 12)
|
|
0
|
348
|
22 May 2023
|
NEC3 ECSC: Delay to completion
|
|
1
|
778
|
26 August 2015
|
NEC4 - Project Manager's Instructions after Completion Date
|
|
3
|
977
|
8 March 2022
|
NEC3 ECC: Is defined cost a cost excluding mark-up?
|
|
2
|
1127
|
24 November 2016
|
When does the Contractor correct a notified Defect?
|
|
1
|
776
|
15 October 2012
|
Fee on CEs where the BoQ rates are used
|
|
4
|
155
|
23 July 2024
|
NEC ECC: Payment for Attendance at Subcontractor Works
|
|
1
|
775
|
26 February 2019
|
NEC ECC: What Contractors could reasonably allow for.
|
|
2
|
1124
|
16 July 2018
|
NEC ECC: Can I claim for prelims on omitted work on short form contract using BOQ
|
|
1
|
774
|
22 May 2017
|
New to jct contracts - Adding an addumdum for additional services
|
|
1
|
774
|
26 February 2016
|
What is meant by 'joint and several liability'?
|
|
1
|
774
|
18 January 2013
|
Can the Contractor’s liability for Defects be limited under Option X18?
|
|
1
|
774
|
14 November 2012
|
How are parties protected against claims, proceedings, compensation and costs due to an event which are at their risk?
|
|
1
|
774
|
10 October 2012
|
NEC4 ECSC: Who exactly is the Client under the ECSC and how can communications/instructions be controlled?
|
|
4
|
489
|
1 August 2018
|
What procedures are there to get the contractor to work in line with his programme within the SBC05 (rev 2006) other than serving a notice
|
|
1
|
773
|
26 June 2014
|
ECC Option A - Project Manager 1
|
|
1
|
772
|
19 August 2021
|
The Project Manager accepts a Defect and the reduced Prices and earlier Completion Date. Can the Contractor be held liable for the Defect?
|
|
1
|
772
|
15 October 2012
|
What is the procedure for appointing a Subcontractor?
|
|
1
|
772
|
12 October 2012
|
What period do the insurances in the Insurance Table cover?
|
|
1
|
772
|
10 October 2012
|
Forecast Assessment and Correction of Assumption
|
|
1
|
434
|
14 November 2022
|
Calculation of Defined cost on Option A subcontract. SC Data Part 2 has no rates
|
|
1
|
1372
|
29 November 2013
|
ECC NEC3 Option E - Can the Employer offset/deduct Contractor costs due to breakdwon of sub-contractor equipment?
|
|
1
|
771
|
11 March 2016
|
NEC3 ECSC Can CE's be reassessed?
|
|
3
|
968
|
22 September 2020
|
FIDIC Yellow: Is contractor liable to do anything under IFC in FIDIC yellow book?
|
|
4
|
865
|
27 July 2019
|
NEC ECC: Can a weather event lead to unexpected physical conditions
|
|
3
|
967
|
11 February 2020
|
NEC ECC: Option A contract expiratoin
|
|
1
|
769
|
5 April 2017
|