If the Employer wishes to terminate for a reason other than those stated in the termination table, what must he do?

If the Employer wishes to terminate for a reason other than those stated in the termination table, what must he do?

1 Like

Under Clause 90.2, the Employer has authority to terminate for any reason, besides those listed in the termination table. If the Employer wishes to exercise this right, he must notify the Project Manager and the Contractor and give details of his reason for terminating (see Clause 90.1).