|
About the Legal and Disputes category
|
|
0
|
447
|
27 February 2020
|
|
Webinar - Payment and the Construction Act
|
|
13
|
946
|
22 February 2024
|
|
Webinar - Adjudication in the Construction and Engineering Industries
|
|
3
|
520
|
20 April 2023
|
|
Webinar - The Five Methods of Dispute Resolution under JCT D&B 2016
|
|
1
|
496
|
14 September 2022
|
|
Rejoinder in Adjudication
|
|
2
|
515
|
23 July 2022
|
|
Construction Adjudication
|
|
0
|
340
|
20 July 2022
|
|
What sort of evidence needs to be provided for a contractor in order to prove events related to a claim?
|
|
2
|
764
|
4 March 2022
|
|
Letters of Intent, breach of contract and copyright (This is a big-un)
|
|
1
|
552
|
6 December 2021
|
|
Adjudication Update
|
|
3
|
652
|
19 May 2021
|
|
Webinar - Contractual Entitlements (Part 1) What are Contractual Entitlements
|
|
6
|
528
|
8 March 2021
|
|
ICC Target Cost Contract: Disallowed costs prior to completion?
|
|
1
|
743
|
6 October 2020
|
|
How difficult is it to demonstrate skill and care has not been used?
|
|
6
|
875
|
2 October 2020
|
|
LEGAL: Under NHBC is there legislation that a Employer who wants to appoint a third party to carry out works they have to send out works to tender and obtain at least three quotes to prove that they were mitigating their loss
|
|
2
|
646
|
10 July 2020
|
|
JCT: Rights for set-off and/or pay less notices
|
|
1
|
625
|
2 June 2020
|
|
LEGAL: Does a Pay Less have to state the word "Nil" to be valid?
|
|
1
|
599
|
1 June 2020
|
|
Legal/disputes: What are the actions parties can take if one of the arbitrators has been absent for an unreasonable length of time?
|
|
2
|
1107
|
29 May 2020
|
|
LEGAL: How can you remove squatters from a building?
|
|
1
|
583
|
28 April 2020
|
|
Legal: Non-binding adjudication decision
|
|
2
|
665
|
30 March 2020
|
|
Bespoke Contract: Is inflation/ price escalation considered as an Indirect cost
|
|
1
|
669
|
5 March 2020
|
|
Contract error - was unaware of contract signed up to?
|
|
1
|
608
|
3 March 2020
|
|
NEC ECS: Impact on client of dispute between PC and SC
|
|
2
|
599
|
23 January 2020
|
|
Legal and Disputes: Terminating A Sub-contract
|
|
1
|
543
|
10 October 2019
|
|
Can an employer make a claim for negligent design, and if so how does this work?
|
|
2
|
680
|
31 January 2019
|
|
Legal: Responsibility for tree roots disrupting work progress
|
|
5
|
836
|
6 December 2018
|
|
Bespoke Contract - Contract "Determined"
|
|
1
|
643
|
30 November 2018
|
|
Claims: why is notice required before a certificate of termination is issued
|
|
2
|
729
|
12 November 2018
|
|
WI hard-copy drawing references another drawing which has not been included in hard-copy. Is the referenced drawing included in the WI?
|
|
1
|
496
|
31 October 2018
|
|
General contract question: can application be submitted anyway?
|
|
1
|
536
|
30 October 2018
|
|
Must the answers to Tender Clarification questions (pre-tender) be considered as part of the Contractual Documents once awarded?
|
|
10
|
3301
|
10 July 2018
|
|
NEC: Is a change to the site boundary a compensation event?
|
|
3
|
1194
|
17 May 2017
|