About the Legal and Disputes category
|
|
0
|
443
|
27 February 2020
|
Webinar - Payment and the Construction Act
|
|
13
|
908
|
22 February 2024
|
Webinar - Adjudication in the Construction and Engineering Industries
|
|
3
|
517
|
20 April 2023
|
Webinar - The Five Methods of Dispute Resolution under JCT D&B 2016
|
|
1
|
482
|
14 September 2022
|
Rejoinder in Adjudication
|
|
2
|
501
|
23 July 2022
|
Construction Adjudication
|
|
0
|
335
|
20 July 2022
|
What sort of evidence needs to be provided for a contractor in order to prove events related to a claim?
|
|
2
|
753
|
4 March 2022
|
Letters of Intent, breach of contract and copyright (This is a big-un)
|
|
1
|
550
|
6 December 2021
|
Adjudication Update
|
|
3
|
640
|
19 May 2021
|
Webinar - Contractual Entitlements (Part 1) What are Contractual Entitlements
|
|
6
|
524
|
8 March 2021
|
ICC Target Cost Contract: Disallowed costs prior to completion?
|
|
1
|
721
|
6 October 2020
|
How difficult is it to demonstrate skill and care has not been used?
|
|
6
|
808
|
2 October 2020
|
LEGAL: Under NHBC is there legislation that a Employer who wants to appoint a third party to carry out works they have to send out works to tender and obtain at least three quotes to prove that they were mitigating their loss
|
|
2
|
632
|
10 July 2020
|
JCT: Rights for set-off and/or pay less notices
|
|
1
|
612
|
2 June 2020
|
LEGAL: Does a Pay Less have to state the word "Nil" to be valid?
|
|
1
|
584
|
1 June 2020
|
Legal/disputes: What are the actions parties can take if one of the arbitrators has been absent for an unreasonable length of time?
|
|
2
|
1085
|
29 May 2020
|
LEGAL: How can you remove squatters from a building?
|
|
1
|
581
|
28 April 2020
|
Legal: Non-binding adjudication decision
|
|
2
|
661
|
30 March 2020
|
Bespoke Contract: Is inflation/ price escalation considered as an Indirect cost
|
|
1
|
664
|
5 March 2020
|
Contract error - was unaware of contract signed up to?
|
|
1
|
604
|
3 March 2020
|
NEC ECS: Impact on client of dispute between PC and SC
|
|
2
|
597
|
23 January 2020
|
Legal and Disputes: Terminating A Sub-contract
|
|
1
|
514
|
10 October 2019
|
Can an employer make a claim for negligent design, and if so how does this work?
|
|
2
|
665
|
31 January 2019
|
Legal: Responsibility for tree roots disrupting work progress
|
|
5
|
824
|
6 December 2018
|
Bespoke Contract - Contract "Determined"
|
|
1
|
642
|
30 November 2018
|
Claims: why is notice required before a certificate of termination is issued
|
|
2
|
712
|
12 November 2018
|
WI hard-copy drawing references another drawing which has not been included in hard-copy. Is the referenced drawing included in the WI?
|
|
1
|
495
|
31 October 2018
|
General contract question: can application be submitted anyway?
|
|
1
|
532
|
30 October 2018
|
Must the answers to Tender Clarification questions (pre-tender) be considered as part of the Contractual Documents once awarded?
|
|
10
|
3185
|
10 July 2018
|
NEC: Is a change to the site boundary a compensation event?
|
|
3
|
1172
|
17 May 2017
|