The Employer has not provided something which he is to provide by the date for providing it shown on the Accepted Programme. Is this a compensation event?
1 Like
This is a compensation event. The Works Information should give details of anything, such as Plant and Materials, which the Employer is to provide and of any restrictions on when it is to be provided. The Contractor is required to include this information on the programme under Clause 31.2. The Contractor notifies the Project Manager of the event as a compensation event (see Clause 60.1(3) and Clause 61.3).