What is the procedure for appointing a Subcontractor?
1 Like
Clause 26.2 details the procedure for appointing Subcontractors. The Contractor gives the name of each Subcontractor he plans to appoint to the Project Manager. The Contractor must then wait for the Project Manager’s acceptance before appointing the proposed Subcontractor.