Exam Question NEC 4

Hi

I am doing an exam and have very little support as I am the first person in my organisation to do it or anything like it.

I was wondering if I could get some advice

The question is a riot starts outside a police station

Walls and windows broke. Contractor vans and employees cars damaged. Who pays and what’s the process?

I believe it to be the client for both under section 80 with the process for pays a compensation event 60.1(12)

This is and NEC 4 TSC exam

Am I correct?