Clause 16.1 - Notice of Early Warning
|
|
1
|
792
|
19 January 2023
|
NEC4 45.2 Accepting defects for option C
|
|
1
|
770
|
11 October 2021
|
NEC ECC: What items should be included / allowed for when calculating percentage for peoples overheads?
|
|
5
|
4447
|
9 July 2021
|
NEC Option A - Client has omitted a section of works. Can we claim as lump sum even though it is omitted?
|
|
1
|
715
|
7 February 2023
|
NEC3 ECC: Removing Scope
|
|
2
|
3144
|
25 July 2016
|
What is the purpose of Option X15?
|
|
1
|
6802
|
16 October 2012
|
NEC ECC: Can a Project Manager reassess a compensation event
|
|
4
|
4082
|
10 August 2022
|
Missing of Secondary Option Clause X5 in NEC3
|
|
4
|
720
|
12 October 2022
|
NEC3 ECC Take over/Completion
|
|
2
|
1655
|
29 September 2020
|
NEC3 TSC Option A and X19 Secondary Option
|
|
2
|
2913
|
17 July 2016
|
ECC Option C Contract - WI
|
|
1
|
1127
|
5 August 2021
|
NEC3 ECSC: What are the main differences between long and short form ECC
|
|
2
|
5121
|
14 January 2022
|
Contractor assessment of application unreasonable - NEC3 Option C
|
|
4
|
674
|
5 October 2023
|
What is included in an NEC3 ECC acceleration quote?
|
|
3
|
4146
|
7 November 2014
|
NEC3 ECC: Can the Completion Date be set as a Key Date?
|
|
1
|
5752
|
4 June 2015
|
NEC4 clause 51.1 & 51.2 late payment
|
|
1
|
562
|
6 June 2023
|
On an NEC Option C is private health insurance a Defined Cost or included in the Fee?
|
|
2
|
2538
|
2 December 2013
|
NEC ECC: Does the period for reply apply to the Contractor as well
|
|
6
|
2949
|
11 September 2019
|
Dispute Resolution
|
|
1
|
312
|
23 January 2023
|
NEC4 option C and clause 52.2 account records
|
|
2
|
1424
|
3 September 2020
|
JCT: Can a contractor working under JCT refuse a works instruction if costs are not agreed before hand
|
|
1
|
5285
|
14 July 2017
|
Letters of Intent, breach of contract and copyright (This is a big-un)
|
|
1
|
520
|
6 December 2021
|
NEC ECC: Interpretation of NEC4 SOCC
|
|
1
|
1588
|
25 June 2020
|
NEC3 ECC: The requirements of Early Warning Clause 16.1
|
|
1
|
4985
|
19 February 2016
|
Welcome to ReachBack
|
|
1
|
2543
|
28 November 2021
|
NEC ECC: Under option A, can I charge Prelims, for Compensation events if it does not change the planned Completion date?
|
|
3
|
5662
|
7 June 2023
|
NEC 3: Option C Descope
|
|
1
|
1414
|
25 March 2021
|
What is the definition of a Subcontractor under NEC3
|
|
3
|
9913
|
7 February 2013
|
Does my work with asbestos insulating board (AIB) need a licence or is it notifiable non-licensed work?
|
|
1
|
43035
|
14 January 2013
|
NEC ECC: Notifying Defects against an accepted Contract's Design
|
|
5
|
2427
|
12 October 2022
|
NEC3 ECC: Option E Fee on Fee
|
|
1
|
2351
|
11 October 2017
|
NEC3 PSC: X9 - transfer of intellectual property rights
|
|
2
|
3379
|
23 January 2019
|
NEC3 ECC: what should be included in the percentage for overheads and profit asked for in the Contract Data Part Two?
|
|
1
|
4121
|
7 July 2016
|
NEC 4 Schedule of Cost Components and IT costs
|
|
1
|
1288
|
19 July 2022
|
NEC3 ECC - Purchase of Plant or equipment - Residual Value
|
|
3
|
908
|
23 January 2023
|
What happens if the PM incorrectly assesses a compensation event under ECC3
|
|
4
|
8087
|
28 January 2014
|
NEC: ECC Option A - how do I assess Compensation Events when the Shorter Schedule of Cost Components does not include rates for People?
|
|
1
|
4028
|
16 January 2016
|
Removing a Provisional Sum
|
|
1
|
1259
|
27 January 2022
|
Acceptance of Contractors design by PM
|
|
1
|
3952
|
10 March 2014
|
FIDIC: Under FIDIC, If contemporary record not available , how to evaluate a prolongation claim?
|
|
1
|
3879
|
11 April 2014
|
Does the upcoming change in Employers National Insurance contribution constitute a X2 change in law and therefore a Compensation Event
|
|
3
|
1540
|
17 December 2021
|
NEC3 ECCCould additional work be instruction after Completion – what are the potential disadvantages of this?
|
|
1
|
3853
|
16 December 2015
|
Does anyone know where I can find some free NEC3 templates?
|
|
1
|
3832
|
18 September 2015
|
NEC4 Option A - Quote substantiation
|
|
3
|
851
|
17 January 2023
|
NEC ECC: TQs not part of contract
|
|
6
|
3587
|
29 June 2023
|
NEC4 Option C - Staff Costs within a CE
|
|
2
|
1633
|
20 August 2023
|
Can a Project Manager issue an instruction to proceed without an agreed quotation for an Early Warning?
|
|
4
|
12581
|
19 November 2014
|
NEC4 Option 4 - Missing Fee Percentage in Contract Data part two
|
|
3
|
4430
|
27 November 2021
|
NEC ECC: Deemed acceptance of CE Quotation outside of time period
|
|
5
|
1136
|
8 February 2023
|
Can the client stand the contractor down for weather if weather risk is contractors responsibility
|
|
4
|
699
|
23 July 2023
|