: An Employer has decided not to undertake some additional works for reasons only known to them at the current time. NEC3 ECC Option A.
2 Likes
Only real negatives to the Employer to instruct CEβs after Completion is that the Contractor will not be pushed to carry out the works in a certain timescale, as they will no longer be threatened with delay damages if they have achieved Completion. Also the defect date will be fixed following Completion, so there will be e reduced period for the extra works for which the Contractor is liable to correct defects. You may also want to check things like insurances if that could be any issue.