I’m having an issue with the inclusion of prelims within a CE, I’ve summarized the position of the Client and the Contractor below, could someone possibly advise?
The issue: The inclusion of prelims on an NEC4 Option C CE. The Contractor has raised a Compensation Event for work under 60.1(1), the NCE is accepted by the client and they are assessing the Compensation Event. The issue arises with the inclusion of Prelims, most notably the Contractors staff members, Project Manager(PM) and Commercial Manager(CM). The contractor believes they should be included, the client believes they should not be. There is no dispute that the PM/CM worked on the CE.(80% of the work has been completed)
Client: The client believes that in the Activity Schedule for pricing the works and in setting the Target Cost, a Commercial Manager was priced at 100%. Because there is still only 1 Commercial Manager on site, if they allow the inclusion of the Commercial Manager within the CE, it would increase his time within the Target to 110% and therefore cannot be included with the CE
Contractor: The Contractor believes that the Activity Schedule and the build up to that Target Cost is irrelevant when Assessing Compensation Events, as per clause 55.2 The Activity Schedule is not Part of the Scope or Site Information. The Defined cost incurred on providing the CE should be included in the CE assessment irrespective if any time was previously included in a previous forecast.