NEC ECC- CE assessment without an accepted Programme
|
|
1
|
1156
|
10 May 2019
|
NEC3 ECC: Can Employer retract a "negative" CE
|
|
1
|
650
|
30 April 2016
|
Who under the PSC has the authority in the absence of a Project Manager?
|
|
1
|
650
|
20 January 2015
|
If a court rules an adjudicator's decision to be a nullity, is it legally permissible for the losing party to refuse to pay the adjudicator's fees?
|
|
1
|
650
|
6 February 2013
|
Can the Employer replace the Supervisor?
|
|
1
|
650
|
12 October 2012
|
NEC ECS: Are people costs deemed to be included within the fee when not identified as Key People in the Contract Data?
|
|
1
|
1155
|
8 November 2017
|
NEC ECC: Does Certification bring forward Completion Date?
|
|
2
|
530
|
4 March 2019
|
NEC3 ECC Option A - What are the implications of a change of subcontractor where they are carrying out the vast majority of the works?
|
|
1
|
649
|
7 April 2016
|
What is the procedure for the Contractor submitting a revised programme to the Project Manager?
|
|
1
|
649
|
12 October 2012
|
The Contractor has terminated because the Employer has had a provisional liquidator appointed to it (R6). What is the termination procedure?
|
|
1
|
649
|
12 October 2012
|
The Contractor has terminated because the Employer has made an arrangement with his creditors (R4). What is the amount due?
|
|
1
|
649
|
12 October 2012
|
Nec3 pm disagrees with ce evaluation/quotation
|
|
1
|
648
|
22 January 2016
|
On termination, can the Employer complete the works?
|
|
1
|
648
|
12 October 2012
|
Who bears the cost of an event which is at the Contractor’s risk, if the amount recovered from the insurer does not cover the whole cost of the event?
|
|
1
|
648
|
11 October 2012
|
NEC ECC: What next if PM rejects a notified CE?
|
|
1
|
1152
|
7 January 2018
|
NEC ECC: Is the introduction of new 'target dates' outside of those in the contract a CE?
|
|
3
|
458
|
7 December 2017
|
NEC ECC: Change in Client design due to unforseen ground conditions (which have been deleted in contract)
|
|
2
|
940
|
11 November 2019
|
NEC and Sales of Goods Act
|
|
1
|
1151
|
3 April 2014
|
Are the Employer’s rights affected by the issue of the Defects Certificate in respect of a Defect the Supervisor has not found?
|
|
1
|
647
|
15 October 2012
|
Is early warning required for a compensation event which has already been notified?
|
|
1
|
647
|
12 October 2012
|
The Contractor can recover a delay by acceleration. Can this still be recognised under R21?
|
|
1
|
647
|
12 October 2012
|
NEC ECC: Changes in staff levels under option C
|
|
1
|
646
|
2 November 2018
|
Are tests to be done before Key Dates?
|
|
1
|
646
|
14 October 2012
|
What do the Parties provide for tests and inspections as stated in the Works Information?
|
|
1
|
646
|
14 October 2012
|
The Project Manager has instructed the Contractor to stop or not start work for reasons other than default by the Employer or Contractor. Can either Party terminate?
|
|
1
|
646
|
12 October 2012
|
NEC ECC: Prevention wording compared to NEC3
|
|
3
|
812
|
11 May 2020
|
NEC3 ECC: Assessment of a Compensation Event under NEC3 Short Form
|
|
1
|
1148
|
7 November 2016
|
Howdi jon Michael Fulton here from NZ, still working on the CIAL term services contract with Christchurch Airport. my question, we originally signed the term service contract with a performance bond of 100% of task order but quickly changed to 50% throug
|
|
1
|
1148
|
18 February 2013
|
What are the components to be included within the ssocc option A for peoples cost
|
|
1
|
1147
|
5 December 2013
|
What should the Contractor do if he does not require access on the dates stated in the Contract Data?
|
|
1
|
645
|
12 October 2012
|
How long does it take for a certified payment to be made?
|
|
1
|
645
|
10 October 2012
|
Early Warning Between Notification of Compensation Event
|
|
2
|
937
|
27 August 2021
|
Completion and Retention - NEC3
|
|
3
|
810
|
12 December 2023
|
NEC ECC: How to assess CE amount for inflation before completion?
|
|
1
|
644
|
15 November 2018
|
What are 'co-lateral warranties'?
|
|
1
|
1144
|
18 January 2013
|
NEC ECC: What are the procedures for assessing and making interim payments?
|
|
1
|
1143
|
3 January 2020
|
NEC ECC: Missed KPI - What happens to the incentive payment?
|
|
1
|
1142
|
17 January 2020
|
Do all excavators require thorough examinations as required by Lifting Operations and Lifting Equipment Regulations (LOLER)?
|
|
1
|
1142
|
25 January 2013
|
NEC ECC: Under option D, do I have to pay if subcontract supply payment application late?
|
|
1
|
642
|
11 April 2017
|
Can either Party terminate if the other Party has had a bankruptcy order made against him?
|
|
1
|
642
|
11 October 2012
|
What is the first payment?
|
|
1
|
642
|
10 October 2012
|
NEC ECC: Can a CE change a sectional Completion Date?
|
|
1
|
1141
|
4 July 2018
|
NEC 3 Option B - Use of BoQ to remeasure a bill item
|
|
1
|
1141
|
16 March 2018
|
NEC3 ECC: Weather Delay
|
|
1
|
1141
|
30 January 2017
|
NEC ECC: Are non-job specific items disallowable
|
|
4
|
721
|
25 April 2018
|
NEC3 ECC: SSCC - Charge 41 Application
|
|
1
|
1140
|
9 October 2016
|
Procurement: What is the difference between the "notice of prior information " and the "contract notice"?
|
|
1
|
641
|
24 September 2015
|
What might the Employer’s particular health and safety requirements be?
|
|
1
|
641
|
12 October 2012
|
How are decisions made at the risk reduction meeting recorded?
|
|
1
|
641
|
12 October 2012
|
How are changes to the Prices arising from compensation events assessed?
|
|
1
|
641
|
9 October 2012
|