How are changes to the Prices arising from compensation events assessed?
1 Like
Changes to the Prices are assessed as the effect of the compensation event upon:
the actual Defined Cost of the work already done
the forecast Defined Cost of work not yet done and
the resulting Fee (see clause 63.1).