How are decisions made at the risk reduction meeting recorded?

How are decisions made at the risk reduction meeting recorded?

1 Like

Clause 16.4 outlines this procedure. The Risk Register is revised by the Project Manager to record the decisions made at the meeting. The revised Risk Register is then given to the Contractor.