When does the Contractor correct a notified Defect?
|
|
1
|
776
|
15 October 2012
|
NEC ECC: Payment for Attendance at Subcontractor Works
|
|
1
|
775
|
26 February 2019
|
How are parties protected against claims, proceedings, compensation and costs due to an event which are at their risk?
|
|
1
|
775
|
10 October 2012
|
NEC4 ECSC: Who exactly is the Client under the ECSC and how can communications/instructions be controlled?
|
|
4
|
490
|
1 August 2018
|
NEC ECC: What Contractors could reasonably allow for.
|
|
2
|
1124
|
16 July 2018
|
NEC ECC: Can I claim for prelims on omitted work on short form contract using BOQ
|
|
1
|
774
|
22 May 2017
|
Can the Contractor’s liability for Defects be limited under Option X18?
|
|
1
|
774
|
14 November 2012
|
ECC Option A - Project Manager 1
|
|
1
|
772
|
19 August 2021
|
The Project Manager accepts a Defect and the reduced Prices and earlier Completion Date. Can the Contractor be held liable for the Defect?
|
|
1
|
772
|
15 October 2012
|
What is the procedure for appointing a Subcontractor?
|
|
1
|
772
|
12 October 2012
|
What period do the insurances in the Insurance Table cover?
|
|
1
|
772
|
10 October 2012
|
Forecast Assessment and Correction of Assumption
|
|
1
|
434
|
14 November 2022
|
Calculation of Defined cost on Option A subcontract. SC Data Part 2 has no rates
|
|
1
|
1372
|
29 November 2013
|
NEC ECC: Can a weather event lead to unexpected physical conditions
|
|
3
|
970
|
11 February 2020
|
ECC NEC3 Option E - Can the Employer offset/deduct Contractor costs due to breakdwon of sub-contractor equipment?
|
|
1
|
771
|
11 March 2016
|
NEC3 ECSC Can CE's be reassessed?
|
|
3
|
968
|
22 September 2020
|
NEC ECC: Raising a CE under an incorrect clause
|
|
2
|
1117
|
30 January 2020
|
NEC ECC: Option A contract expiratoin
|
|
1
|
769
|
5 April 2017
|
NEC3 ECC: If the Employer omits elements of work, is the Contractor entitled to loss of profit?
|
|
1
|
1367
|
5 September 2016
|
TSC Option X19
|
|
1
|
768
|
15 July 2016
|
Can the Project Manager instruct the Contractor to remove an employee?
|
|
1
|
768
|
12 October 2012
|
NEC3 ECC: Under recovery
|
|
2
|
627
|
14 April 2015
|
NEC ECC: PWDD at Completion Option A
|
|
1
|
1365
|
8 November 2019
|
NEC3 ECC: Payment of risk under a target cost contract
|
|
1
|
767
|
20 June 2016
|
Why might the Employer not want to correct a Defect?
|
|
1
|
767
|
15 October 2012
|
How should the Contractor deal with loss of and damage to the works, Plant and Materials?
|
|
1
|
767
|
10 October 2012
|
NEC ECC: Option A Priced Against A ProvidedActivity Schedule
|
|
2
|
626
|
5 April 2017
|
NEC ECC: Can a CE introduce a new contractual Sectional Completion?
|
|
1
|
1363
|
23 January 2019
|
NEC TSC: Service Manager - Delegated powers
|
|
1
|
766
|
25 July 2017
|
NEC3 PSC Expenses - Target Cost
|
|
1
|
766
|
14 July 2017
|
How would you incoporate NEC3 into a disseration question?
|
|
2
|
625
|
2 October 2014
|
NEC3 ECC: What happens if an "implemented" CE does not go ahead
|
|
1
|
764
|
2 February 2016
|
NEC3 ECC: Compensation Events and Fees
|
|
1
|
764
|
1 February 2016
|
When does the defects correction period begin?
|
|
1
|
764
|
15 October 2012
|
NEC contracts notification of no response to CE
|
|
2
|
1109
|
24 February 2021
|
NEC ECC: Termination of NEC 4 Contract (Option A)
|
|
1
|
1358
|
12 February 2020
|
NEC3 ECC Option D: Change in Works Info initiated by PM vs. initiated by the Contractor
|
|
1
|
763
|
15 October 2015
|
The Employer or Others have not worked within the times shown on the Accepted Programme. Is this a compensation event?
|
|
1
|
763
|
10 October 2012
|
NEC ECC: Option A - Activity schedule changes to prices for the Price of work done to date
|
|
1
|
762
|
3 October 2017
|
NEC: Coronavirus what are the contractual implication with the NEC?
|
|
1
|
1354
|
16 March 2020
|
The Employer has terminated because the Contractor has made an arrangement with his creditors (R4). What is the amount due?
|
|
1
|
761
|
12 October 2012
|
NEC ECS: Terminal Float pricing?
|
|
1
|
1352
|
9 April 2019
|
Do defects have to be corrected?
|
|
1
|
759
|
15 October 2012
|
NEC ECSC: How does one assess the Contractors liability for a weather event that impacts on a scope increase CE?
|
|
2
|
619
|
1 August 2018
|
NEC3 ECC: Revised programmes
|
|
1
|
758
|
15 January 2016
|
What is the minimum amount of cover or minimum level of indemnity the Contractor has to provide for loss of or damage to property caused by activity in connection with the contract?
|
|
1
|
758
|
10 October 2012
|
Why should the Contractor submit revised programmes?
|
|
1
|
757
|
12 October 2012
|
NEC ECC: If an Employer has a contractor with a Contractor to demolish and rebuilt a site, does the Contractor have rights to sell the scrap materials from that site?
|
|
2
|
1099
|
29 June 2020
|
Under an NEC 3 Option A the Employer fails to provide detailed working drawings
|
|
2
|
618
|
22 February 2017
|
NEC ECC: Plant cost recoverable?
|
|
1
|
756
|
13 November 2018
|