|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
36
|
15 May 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
33
|
21 April 2026
|
|
Does cl50.2 provide a valid method for reducing the amount due without the need to reopen implemented CEs?
|
|
2
|
33
|
20 April 2026
|
|
NEC 4 remeasurement timescales
|
|
6
|
98
|
13 April 2026
|
|
NEC3 Short Contract hitting cashflow credit limit
|
|
1
|
24
|
27 February 2026
|
|
NEC Termination Process and the Role of The Employer
|
|
6
|
93
|
18 February 2026
|
|
Inflation uplift calculation fro Framework
|
|
1
|
32
|
6 December 2025
|
|
60.1 - (4) The Project Manager gives an instruction to stop or not to start any work or to change a Key Date
|
|
4
|
168
|
12 November 2025
|
|
NEC4 TSC - Task Order Option A
|
|
1
|
79
|
20 October 2025
|
|
NEC 4 Option A - Scope Reduction
|
|
1
|
83
|
25 September 2025
|
|
NEC4 ECC Option D - Adjusting Quantities in BoQ
|
|
1
|
93
|
24 September 2025
|
|
NEC Option A Risk Register Exclusions
|
|
1
|
39
|
15 August 2025
|
|
Are legal fees allowable?
|
|
2
|
96
|
10 July 2025
|
|
NEC3 Option C: Recovering Prelims
|
|
1
|
67
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
72
|
10 July 2025
|
|
Late issue of project managers assumptions
|
|
3
|
124
|
10 July 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
115
|
22 June 2025
|
|
Quotation Assessments Under X2
|
|
1
|
158
|
15 May 2025
|
|
Can a CE allow the Fee Percentage to be adjusted?
|
|
1
|
102
|
24 April 2025
|
|
NEC4 Option C - X1 & X2, Increase in employers national insurance contributions
|
|
2
|
605
|
10 April 2025
|
|
Inconsistency or Ambiguity in Works Information
|
|
1
|
124
|
31 March 2025
|
|
Inclusion of 'Unimplemented' CE in Forecast and Assessment
|
|
1
|
81
|
25 March 2025
|
|
Option A - 60.1 (1) Used to claim back measure not realised
|
|
1
|
59
|
26 February 2025
|
|
Liquidated Damages on paperwork
|
|
2
|
143
|
21 January 2025
|
|
NEC4 Core Clause 63.4
|
|
1
|
204
|
13 December 2024
|
|
What are the implications of the contract data pt1 stating secondary options in (1 General) section but no reference to it later in the contract data or vice versa?
|
|
3
|
131
|
25 September 2024
|
|
Contract Document Clarifications
|
|
2
|
110
|
19 September 2024
|
|
NEC3 using different subcontractor quotations to add / omit works
|
|
2
|
345
|
13 September 2024
|
|
How do we secure fair compensation amidst main contractor delays and disputes under NEC3?
|
|
2
|
114
|
29 August 2024
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
320
|
15 August 2024
|