|
Payment under Clause 50.7
|
|
2
|
79
|
7 October 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
115
|
22 June 2025
|
|
London Interbank Lending Rate-
|
|
0
|
14
|
9 June 2025
|
|
NEC4 TSC contracts
|
|
2
|
57
|
2 April 2025
|
|
Liquidated Damages on paperwork
|
|
2
|
142
|
21 January 2025
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
318
|
15 August 2024
|
|
Instructing works outside Contractor's original Scope
|
|
8
|
555
|
21 July 2024
|
|
Built Connections 2024 - NEC User Group Conference
|
|
2
|
475
|
10 May 2024
|
|
PSC4 - People or Subcontractor
|
|
1
|
254
|
25 April 2024
|
|
NEC3 Option B - Preliminary Item
|
|
0
|
405
|
17 February 2023
|
|
Is failure to comply with a constraint in the Works Information a Defect
|
|
1
|
481
|
1 November 2023
|
|
Assignment or Novation?
|
|
2
|
667
|
26 October 2023
|
|
Contract Programme renegotiation due to Contractor Delay
|
|
3
|
316
|
20 October 2023
|
|
Programme for Acceptance under NEC 3
|
|
1
|
270
|
9 October 2023
|
|
Quotation under a Proposed Instruction for a significant delay to site access
|
|
3
|
344
|
20 July 2023
|
|
PSC Payment of Subconsultant Costs
|
|
3
|
585
|
18 July 2023
|
|
NEC4 PSC Option A X1 Price Adjustment Factor Calculator
|
|
1
|
595
|
16 May 2023
|
|
Construction Law Help
|
|
0
|
510
|
27 February 2023
|
|
NEC3 Option A Quotation Period for Reply
|
|
2
|
575
|
24 February 2023
|
|
NEC3 Option A - WI Ambiguity
|
|
1
|
499
|
6 December 2022
|
|
NEC4 Option A - Novated Design and Liability for Scope Changes
|
|
3
|
1014
|
27 October 2022
|
|
JCT D&B 2016 and sub-contractors
|
|
1
|
1147
|
28 July 2022
|
|
Import Taxes - Defined Cost or Other Amounts?
|
|
1
|
487
|
15 June 2022
|
|
Contractor Assumptions
|
|
1
|
876
|
7 June 2022
|
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
622
|
28 February 2022
|
|
Is it possible to use NEC 4 Secondary Clasues in a NEC 3 option A Sub-Contract?
|
|
1
|
652
|
31 January 2022
|
|
ECC Option A - Project Manager 1
|
|
1
|
799
|
19 August 2021
|
|
Option A - Secondary Option X7 Delayed Damages Included
|
|
2
|
2153
|
5 August 2021
|
|
ECC Option C Contract
|
|
2
|
1210
|
5 August 2021
|
|
NEC4 Client Liabilities
|
|
4
|
1944
|
5 May 2021
|