|
Should changes in law under NEC3 ECC clause X2 be notified even if they are planned to come into effect after the Completion Date?
|
|
3
|
43
|
17 July 2026
|
|
Payment under Clause 50.7
|
|
2
|
101
|
7 October 2025
|
|
NEC3 SOCC 12 (d) special allowances - can maternity pay be considered a recoverable cost?
|
|
1
|
137
|
22 June 2025
|
|
London Interbank Lending Rate-
|
|
0
|
20
|
9 June 2025
|
|
NEC4 TSC contracts
|
|
2
|
68
|
2 April 2025
|
|
Liquidated Damages on paperwork
|
|
2
|
152
|
21 January 2025
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
344
|
15 August 2024
|
|
Instructing works outside Contractor's original Scope
|
|
8
|
636
|
21 July 2024
|
|
Built Connections 2024 - NEC User Group Conference
|
|
0
|
481
|
4 March 2024
|
|
PSC4 - People or Subcontractor
|
|
1
|
268
|
25 April 2024
|
|
NEC3 Option B - Preliminary Item
|
|
0
|
409
|
17 February 2023
|
|
Is failure to comply with a constraint in the Works Information a Defect
|
|
1
|
490
|
1 November 2023
|
|
Assignment or Novation?
|
|
2
|
685
|
26 October 2023
|
|
Contract Programme renegotiation due to Contractor Delay
|
|
3
|
338
|
20 October 2023
|
|
Programme for Acceptance under NEC 3
|
|
1
|
278
|
9 October 2023
|
|
Quotation under a Proposed Instruction for a significant delay to site access
|
|
3
|
364
|
20 July 2023
|
|
PSC Payment of Subconsultant Costs
|
|
3
|
615
|
18 July 2023
|
|
NEC4 PSC Option A X1 Price Adjustment Factor Calculator
|
|
1
|
613
|
16 May 2023
|
|
Construction Law Help
|
|
0
|
515
|
27 February 2023
|
|
NEC3 Option A Quotation Period for Reply
|
|
2
|
593
|
24 February 2023
|
|
NEC3 Option A - WI Ambiguity
|
|
1
|
508
|
6 December 2022
|
|
NEC4 Option A - Novated Design and Liability for Scope Changes
|
|
3
|
1034
|
27 October 2022
|
|
JCT D&B 2016 and sub-contractors
|
|
1
|
1158
|
28 July 2022
|
|
Import Taxes - Defined Cost or Other Amounts?
|
|
1
|
496
|
15 June 2022
|
|
Contractor Assumptions
|
|
1
|
889
|
7 June 2022
|
|
NEC Option A - An ambiguity between Works Information and Activity Schedule (contract documents)
|
|
1
|
628
|
28 February 2022
|
|
Is it possible to use NEC 4 Secondary Clasues in a NEC 3 option A Sub-Contract?
|
|
1
|
659
|
31 January 2022
|
|
ECC Option A - Project Manager 1
|
|
1
|
808
|
19 August 2021
|
|
Option A - Secondary Option X7 Delayed Damages Included
|
|
2
|
2167
|
5 August 2021
|
|
ECC Option C Contract
|
|
2
|
1212
|
5 August 2021
|