I am reaching out to seek some clarification regarding the submission of an updated programme under the NEC4 ECSC contract. As it stands there has not been a defined timescale for submitting an updated programme within the scope and it did not define the detail to which the programme was needed unlike the ECC. Given this situation, should the contractor be submitting an impacted programme to assess the change to the Completion Date?
At present, the contractor is merely indicating the timeframe as a number of weeks without providing any evidence or detailed explanation of how this time has been calculated. This lack of substantiation makes it challenging to accurately assess the impact on the Completion Date.
Could you please provide guidance on whether an impacted programme should be submitted in this scenario?