Hi,
I would be grateful if someone can answer this query.
Scenario
Accepted programme shows piling commencing 2nd November. Contractor found some betterment on the programme, so planned to commence piling works 16 October. However, client delay resulted in Contractor being stood and piling being pushed back to 2nd November.
Is the Contractor still entitled to time/prolongation costs?