|
Should changes in law under NEC3 ECC clause X2 be notified even if they are planned to come into effect after the Completion Date?
|
|
3
|
51
|
17 July 2026
|
|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
84
|
15 May 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
59
|
21 April 2026
|
|
Programme acceptance where no PM response
|
|
5
|
96
|
17 April 2026
|
|
NEC4 which programme dates?
|
|
5
|
168
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
89
|
10 July 2025
|
|
NEC4: Maintaining Terminal Float while CE delay is being assessed
|
|
2
|
569
|
23 November 2024
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
345
|
15 August 2024
|
|
CE's on Option A Contract
|
|
4
|
870
|
23 February 2024
|
|
NEC4: Developing quotation time
|
|
1
|
254
|
9 November 2023
|
|
Is there a switch date in NEC 3?
|
|
1
|
499
|
18 October 2023
|
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
244
|
11 October 2023
|