|
Programme changes communicated to the Contractor without a PMI
|
|
2
|
53
|
15 May 2026
|
|
Managing Unused Tasks in an Accepted NEC3 PSC Quotation
|
|
1
|
40
|
21 April 2026
|
|
Programme acceptance where no PM response
|
|
5
|
56
|
17 April 2026
|
|
NEC4 which programme dates?
|
|
5
|
143
|
10 July 2025
|
|
CE that includes extra over / weekend working rates
|
|
1
|
78
|
10 July 2025
|
|
NEC4: Maintaining Terminal Float while CE delay is being assessed
|
|
2
|
528
|
23 November 2024
|
|
NEC4 - CL 61.1 vs 61.3
|
|
2
|
323
|
15 August 2024
|
|
CE's on Option A Contract
|
|
4
|
857
|
23 February 2024
|
|
NEC4: Developing quotation time
|
|
1
|
243
|
9 November 2023
|
|
Is there a switch date in NEC 3?
|
|
1
|
489
|
18 October 2023
|
|
Clause 63 - Assessment of CE's on NEC3 TSSC's & Switch Date
|
|
1
|
237
|
11 October 2023
|