Compensation Events Time Only
|
|
1
|
489
|
10 November 2023
|
Can the NEC3 Term Service Contract (TSC) include design and if so where would it be detailed?
|
|
1
|
489
|
18 September 2015
|
NEC ECC: What fee percentage should be applied to accommodation?
|
|
5
|
1583
|
1 March 2018
|
NEC ECC: Under the NEC what does "Access Date" mean
|
|
3
|
3443
|
15 August 2019
|
Work information
|
|
3
|
610
|
12 March 2021
|
NEC3 - How to calculate cost saving proposal
|
|
7
|
1364
|
23 May 2023
|
NEC ECC: Isn't 11.2(23) a double negative?
|
|
1
|
485
|
4 July 2019
|
Can a NEC3 early warning notice also be a project managers instruction?
|
|
2
|
2226
|
1 November 2014
|
NEC3 ECSC - Payment under the Engineering and Construction Short Contract?
|
|
2
|
2225
|
19 January 2015
|
ECC Option A contract - Defect
|
|
2
|
1251
|
5 August 2021
|
What is the purpose of a risk reduction meeting?
|
|
1
|
2722
|
12 October 2012
|
NEC ECC: Option B, where a item of work is reduced, can we claim for specilised material not used?
|
|
1
|
484
|
28 April 2017
|
NEC ECC: The Contract is late and LDs may be levied - the PM has instructed a change!
|
|
5
|
1568
|
22 June 2017
|
Forecast costs in a CE - Forecast from when?
|
|
4
|
543
|
21 June 2023
|
NEC3: How can I forecast defined cost of a compenation event if rates are not included in SSCC?
|
|
1
|
2715
|
19 January 2016
|
NEC3 ECC: Assessment of a de-scope of works (from PMI)
|
|
3
|
1919
|
14 May 2016
|
NEC3: Response to an early warning
|
|
2
|
3939
|
17 April 2015
|
NEC 3 Option E Compensation Events
|
|
4
|
3042
|
19 January 2022
|
NEC 3 Option A – Payment of a Sub-contractors Invoice
|
|
2
|
2207
|
25 February 2014
|
Are monies paid for compensation event subject to retention?
|
|
2
|
2203
|
30 September 2014
|
NEC ECC Option C - Equipment rates
|
|
2
|
2201
|
23 July 2023
|
Miscalculation in activity schedule
|
|
6
|
455
|
25 April 2023
|
NEC ECC: YUK3 - what do I need to know
|
|
3
|
3373
|
19 December 2018
|
NEC3 ECC - When is a Pay Less Notice issued?
|
|
2
|
3892
|
10 January 2018
|
NEC3 - Defect Correction or Change of Accepted Design
|
|
2
|
692
|
8 March 2021
|
NEC3 - Recovery of Cost from Subcontractor
|
|
1
|
476
|
2 December 2022
|
Advanced payment for material products not yet manufactured
|
|
3
|
598
|
17 April 2023
|
NEC3 Option B - Payment against rates for holidays
|
|
5
|
1538
|
6 February 2013
|
NEC ECC: Accepting Defects cl 44
|
|
4
|
2993
|
29 January 2018
|
NEC ECC: Deemed Programme Acceptance
|
|
3
|
3333
|
3 November 2017
|
X13 Performance Bond - Recoverable cost?
|
|
1
|
835
|
19 August 2020
|
What is the purpose of the end of liability date?
|
|
1
|
2639
|
14 November 2012
|
NEC3 Works Information - Document/Information by Reference
|
|
2
|
679
|
3 October 2022
|
NEC3 payment and defects
|
|
2
|
3815
|
21 July 2014
|
NEC3 Pricing acceleration under option C
|
|
1
|
2626
|
29 August 2014
|
Standing Time when Access not given to Areas
|
|
4
|
1656
|
8 December 2014
|
Under NEC3 PSC, how do you control expenses and staff rates?
|
|
3
|
1850
|
10 March 2015
|
NEC ECC Option C: Activity Schedule, Risk and total of the Prices (target cost)
|
|
5
|
2684
|
11 December 2020
|
NEC3: ESC Option A - Omission of Items by Employer
|
|
5
|
1507
|
19 November 2020
|
Under NEC3 ECC, can a Key Date be instructed to be completed early?
|
|
3
|
1845
|
15 December 2014
|
NEC ECC: Option A - difference between activity schedule and Works Information regarding payment
|
|
5
|
2673
|
17 June 2020
|
Contract amenment deleting Clause 19 and 60.1(19) with force majeure clause
|
|
2
|
2122
|
19 November 2014
|
NEC ECC Option C float and the assessment of value in compensation events
|
|
2
|
2120
|
20 October 2014
|
NEC ECC: CECA rates for Plant hired for a Compensation Event
|
|
1
|
4595
|
6 December 2019
|
NEC ECS: Option A ECC X7 not identified in contract, can the Contractor still apply for delays?
|
|
1
|
2582
|
29 July 2019
|
NEC3 and the Specification for Highway Works
|
|
4
|
516
|
25 March 2022
|
NEC ECC: Can Project Manager ONLY notify compensation events which they are obliged to notify?
|
|
2
|
1180
|
12 October 2018
|
NEC3 ECC: Ambiguity within the Works Information
|
|
1
|
2563
|
16 September 2015
|
Which Accepted Programme Should I Use?
|
|
7
|
1279
|
5 June 2017
|
NEC TSC Option C - PM's assessment of a comp event
|
|
2
|
660
|
16 December 2021
|