We are the Contractor and have an NEC3 Option A Subcontract.
The Subcontractor has damaged an item of equipment that we are supplying and he is installing. The Subcontractor acknowledges he caused the damage.
We wish to recover the cost of replacing the damaged item from the Subcontractor.
What is the correct mechanism for doing this under the Contract?