|
NEC3 Short Form - Incorrect description in BOQ
|
|
1
|
508
|
21 March 2020
|
|
With regard to building regulations, what is meant by the term ‘short-lived’ materials?
|
|
1
|
508
|
14 February 2013
|
|
What does Spatial Development mean in a planning context?
|
|
1
|
508
|
29 January 2013
|
|
What does Safeguarding Zone mean in a planning context?
|
|
1
|
508
|
29 January 2013
|
|
How do I view progress on an application?
|
|
1
|
508
|
25 January 2013
|
|
Is it okay to demolish a building by setting fire to it?
|
|
1
|
508
|
25 January 2013
|
|
When will a breach of the rules of natural justice will be committed by an Adjudicator?
|
|
1
|
508
|
18 January 2013
|
|
NEC4 Option B - Subcontractor
|
|
2
|
414
|
31 January 2023
|
|
NEC ECC: PM assessment unlinks activities on critical path which are not dependant on one another, is this permissable?
|
|
2
|
414
|
27 June 2018
|
|
NEC3 ECC Option A Contract - Contractor Delay
|
|
1
|
507
|
11 May 2020
|
|
NEC ECC: What to include/amend in tenders from now on? (COVID-19)
|
|
1
|
507
|
28 April 2020
|
|
NEC ECS: Correcting a defect we know the end Client has accepted
|
|
1
|
507
|
13 September 2019
|
|
NEC ECC: Change in the WI between tender and construction - what should have been allowed for
|
|
1
|
507
|
26 April 2018
|
|
NEC ECC: Information for H&S file (as builts etc)
|
|
1
|
507
|
15 November 2017
|
|
With regard to public procurement, what is meant by the term 'attestation'?
|
|
1
|
507
|
22 February 2013
|
|
If any substance is found which was not identified in a preliminary statement about the nature of the site, is it necessary to contact the local authority?
|
|
1
|
507
|
15 February 2013
|
|
If an individual wishes to prune or fell a tree within a Conservation Area, what procedure needs to be followed?
|
|
1
|
507
|
7 February 2013
|
|
Who should carry out a fire risk assessment?
|
|
1
|
507
|
25 January 2013
|
|
When a contractual appointment process is being designed with the object of securing the appointment of an adjudicator, within how many days must the notice of intention to refer be referred to him or her?
|
|
1
|
507
|
18 January 2013
|
|
NEC3 Opt B Ambiguity? Time Bar?
|
|
1
|
285
|
11 October 2023
|
|
NEC ECC: Who sets up the adjudicators contract?
|
|
1
|
506
|
24 October 2019
|
|
NEC ECC : What can be included within quotation?
|
|
1
|
506
|
31 January 2019
|
|
What happens if a contractor needs to register for VAT part way through a JCT minor works contract?
|
|
1
|
506
|
1 March 2017
|
|
Procurement: Which social issues can be included in the public procurement process?
|
|
1
|
506
|
22 February 2013
|
|
With regard to Building Regulations, what legislation covers electrical wiring?
|
|
1
|
506
|
14 February 2013
|
|
What does Bulky Goods mean in a planning context?
|
|
1
|
506
|
28 January 2013
|
|
How high can I build an extension without permission?
|
|
1
|
506
|
25 January 2013
|
|
Regulation 13(6) requires contractors to prevent unauthorised access to sites, and regulation 27(2) requires sites to be identified with signs and/or fenced off. Isn’t this the same thing?
|
|
1
|
506
|
24 January 2013
|
|
If a party speaks to the adjudicator via telephone at any time, is there any procedure related to this that needs to be borne in mind?
|
|
1
|
506
|
18 January 2013
|
|
Moving Materials between working areas
|
|
2
|
413
|
14 October 2021
|
|
NEC3 ECC: Proof of the Fee, does the Employer have the right to ask for a build up/audit of the fee after signing the contract?
|
|
2
|
413
|
9 October 2016
|
|
NEC4 Option B & Option D
|
|
3
|
201
|
23 November 2024
|
|
NEC ECC: Clause regarding the calculation of the monthly payment by the Project Manager?
|
|
1
|
505
|
29 January 2020
|
|
NEC ECC : Option A - Lack of detailed information listed within the SSCC
|
|
1
|
505
|
2 June 2017
|
|
Is there any requirement with regard to water closets contained within the existing Building Regulations?
|
|
1
|
505
|
15 February 2013
|
|
What is involved in preparatory investigation of a potential building site?
|
|
1
|
505
|
15 February 2013
|
|
What are the drawbacks of using a PIN as a call for competition?
|
|
1
|
505
|
13 February 2013
|
|
What is the council's process for planning applications?
|
|
1
|
505
|
25 January 2013
|
|
What are the requirements for projects for voluntary organisations, eg scout huts, churches etc?
|
|
1
|
505
|
24 January 2013
|
|
Can a contractor have a negative impact upon a global claim?
|
|
1
|
505
|
18 January 2013
|
|
NEC ECC: We have X2 but 60.1(19) deleted. Can we still claim a compensation event for Covid-19?
|
|
1
|
504
|
28 April 2020
|
|
Is there a European standard that exists with regard to cowls and roof ventilation outlets?
|
|
1
|
504
|
15 February 2013
|
|
I thought the Management of Health and Safety at Work Regulations 1999 (MHSWR) required risk assessments, so why don’t I have to do specific design risk assessments?
|
|
1
|
504
|
24 January 2013
|
|
When are contribution proceedings available?
|
|
1
|
504
|
18 January 2013
|
|
What are the key points to pay heed to with regard to claims?
|
|
1
|
504
|
18 January 2013
|
|
What are the potential consequences of compromising or a deviating from agreed adjudication procedure without the prior express authority of your client?
|
|
1
|
504
|
18 January 2013
|
|
A person slipped over in the shop but said they were unhurt. Much later they told us they had gone the next day to their GP who then referred them to hospital
|
|
1
|
504
|
14 January 2013
|
|
New features - Capture carbon consumption forecast and actuals
|
|
3
|
356
|
14 May 2021
|
|
NEC 4 ECC Option A - Compensation event notified in error
|
|
1
|
503
|
18 March 2022
|
|
NEC3 PSC Option E - failed design
|
|
1
|
503
|
4 January 2021
|